facebook
Twitter
Linkedin
Feedback

Friday25 July 2014

Passivhaus diaries, part eight: The wall openings

  • Email
  • Comments (20)
  • Save

I'm back now from Devon after an enjoyable but busy break with family and friends. This week, we'll be looking at how to address window and door openings within the cavity walls. We've obviously got to have windows and doors in our Passivhaus but they are a bit of a bind, creating all sorts of challenges regarding airtightness and thermal bridges. It would be a lot easier to just have insulation all the way around!

Windows

We have spent a lot of time developing the detailing for window openings, modelling various permutations in PHPP, the Passivhaus planning software, to try to address issues of insulation, airtightness, thermal bridging and thermal bypass:

Scroll down to view images of vertical section (from side) and horizontal section (from above).

Insulation

The Ecopassiv timber windows that we will be using in the build are triple glazed and have a whole-window U-value of just under 0.8W/m2K (and glazing U-value of 0.6W/m2K). As well as being triple glazed, with low-emissivity coatings and argon fill, windows for Passivhaus-level projects usually have to have some insulation in the frame (in this case polyurethane).

Thermal bridging

Windows are necessary thermal bridges within buildings, although they are also of course a source of solar energy: it is a matter of the energy balance. The challenge is to try to minimise any potential heat loss as far as possible, while using the optimum glazing specification.

For the Denby Dale Passivhaus we have decided to position the windows halfway within the insulation layer, to try to improve performance and minimise thermal bridging. In Passivhaus circles there are debates about possibly positioning windows further forward to get more solar gain, but the physics on this is as yet unclear.

At Denby Dale we will be placing the windows within a plywood form box we have created ourselves, which will be built in by the masons on the site within the blockwork. The advantages of this are that we've got a formwork for the openings within the masonry and that there's no mucking about.

Of course the plywood box itself acts as a bit of a thermal bridge but it only goes halfway through the cavity. It is a cheap and effective way of giving structural support for the windows and doors, and allows relative ease of attaining the required airtightness.

We are trying to wrap the insulation around the frame as much as possible. The fact that the Ecopassiv windows are inward-opening windows also helps with this, as the thicker part of the frame is on the outside.

Because the windows are going to be placed within insulation layer, we needed some way of sealing the exposed fibreglass. For this we're going to use a cavity closer – in this case it is a three-sided pre-formed aluminium closer – let into the window frame and then sealed with mastic to the stone outside. We've also got a more traditional aluminium sill, very common in Europe but less so here, finished in the same way.

Airtightness

The plywood box we've developed for the window openings is a four-sided box screwed and glued with foamed PVA glue so that it gives a good basis for airtightness. Internally we will be using traditional two-coat wet plaster on the concrete block walls, which is airtight in its own right. The concrete blocks on their own are, of course, not airtight.

By contrast, dot and dab plasterboard is not generally airtight either, because the dabs behind the plasterboard do not seal the non-airtight blockwork. Parging blockwork before dot and dabbing might make it airtight, but I feel – from a good construction point of view – that with wet plastering you're sure of what you've done.

Junctions are always going to be difficult for airtightness because you get differential movement between different materials. In this case we've got plywood, wet plaster and the window, so we'll be using the Pro Clima airtightness product Contega, which is an adhesive-backed tape stuck to the plywood with a fleece wrapped into the wet plaster, making the junction between the plywood and plaster airtight even after the inevitable shrinkage cracking.

Another weak point will be between window and plywood box, and there we will use another Pro Clima tape, Tescon Profile, which permanently seals the gap between the window and the plywood.

The finished detail is going to look pretty traditional, apart from deeper reveals. There will be plaster walls and plasterboard on top of plywood boxes in the head and jambs. And at the bottom we're going to have a nice timber window board.

Thermal bypass

As I've discussed in previous blogs, thermal bypass is about ensuring that wind movement does not degrade the performance of the insulation. The aluminium cavity closer mentioned previously will be let into a groove in the front of the frame with a silicon mastic and then is masticked traditionally against the stonework reveal. The result will be that we are not getting any air movement through the insulation at this point but we are still maintaining the insulation at the front of the frame.

Doors

We are having a bit more trouble with the final detailing for the doors. Thanks to blog commentators John Carney and heinbloed, who have highlighted the cold bridge problem at the edge of the floor slab and threshold. Although this has been modelled in PHPP and has been deemed within acceptable parameters, we are still looking for solutions to help reduce the thermal bridge. We have some ideas, but are very open to suggestions, as the ideal threshold does not seem to exist. In particular, do tell us if you know of a suitable insulated threshold that could be fitted into a rebate in the concrete slab!

On site

We have had a site visit from representatives from Kirklees council around the Denby Dale site, including councillors, architects, planners and engineers. It was great to have an opportunity to explain the concepts of Passivhaus design to important local decision-makers, and we were asked some challenging and interesting questions, particularly about the relationship between Passivhaus standards and the Code for Sustainable Homes.

Otherwise, the walls are coming up – at first-floor level now – and the timber I-beam first-floor structure has been installed.

Vertical section


Vertical section

Horizontal section


Horizontal section

Key

1. 300mm dritherm32 fibre glass insulation

2. 100mm natural Yorkshire stone in lime/sand mortar

3. 100mm dense concrete block in cement/sand mortar

4. preformed aluminium cavity closer powder coated

5. Two coat wet plaster

6. 18mm ply permanent formwork box

7. Air-tightness tapes

8. Cavity tray

For more information, go to www.greenbuildingstore.co.uk/denbydalehouse.

Related company resources

Share

Readers' comments (20)

  • Hi Bill, Great work! It's fantastic to see these issues getting discussed. I was wondering - could the thermal bridge be reduced by using a discontinuous steel angle upon which you mount a 50x50 batten? The batten could support the threshold. This would allow the concrete slab to be cut back thereby allow greater continuity of the insulation. Whilst remembering that timber performs about four times worse than your insulation it is about ten times better than the concrete. The benefit of this solution would also be to raise surface temperatures which would avoiding condensation risk and mould growth. Of course using the detail that I've suggested you could just the door moved forward – rather than cutting the concrete back – but this would not have such a significant impact upon heat loss (the benefit to surface temps would probably be affected to a lesser extent.) By now it may be to late to make this suggestion....

    Unsuitable or offensive? Report this comment

  • Why is there a cavity tray below the cill?

    Unsuitable or offensive? Report this comment

  • Green ethics will continually become a greater and greater part of all our lives whether in the medium of construction or anything else. It's great to see it embraced is such a positive manner.

    Unsuitable or offensive? Report this comment

  • Thank you Mark for your continued support. We have not sorted the thresholds yet and it is not too late. Your suggestion of cutting back the slab and supporting the threshold with timber is certainly a possibility. We were thinking of taking it further and fabricating a fiberglass box section filled with PUR. However, easier said than done.

    Unsuitable or offensive? Report this comment

  • Stuart. As you can see from the photos above we actually did not put in cavity trays below windows. When building in cavity construction here in W Yorkshire, it is normal to have a square cut stone cill with the window masticed on top. This detail with the high exposure on the Pennines can fail, hence the cavity tray. The Denby Dale House will have aluminum extension cills giving far less risk.

    Unsuitable or offensive? Report this comment

  • I want to question why the posting from Tradesman Building Supplies has been allowed to remain. It is clearly pure advertising and does not contribute in any way to discussion of the Denby Dale Passivhaus. The company's products seem to have few if any specific environmental credentials. For example their 'eco' window does not appear to go beyond building regs in performance, and does not have any form of timber certification. Their environment policy seems to rely entirely on carbon offsetting (a controversial measure in itself) with no other measures of any sort.

    Unsuitable or offensive? Report this comment

  • Bill - I'm sorry for not responding to the treshold detail problem earlier. I thought that the manufacturer of the doors could come up with a insulated treshold. Many of the manufacturers are German speaking and communication can be difficult. However they are always keen to solve customer's challenges - particularly as I'm sure it will generate repeat business. Mark Siddall's suggestion is good and your idea of a GRP box section is a step further - but a manufacturers' addition would cause less problems on site. Sorry I have no suggestion as a solution.

    Unsuitable or offensive? Report this comment

  • Bill I live near saltash amnd will be building in a couple of years or so. Are you able to provide any services? Adam

    Unsuitable or offensive? Report this comment

  • Adam, I always take interest in projects in the South West. Please e mail info@greenbuildingstore.co.uk

    Unsuitable or offensive? Report this comment

  • Bill, what has happened since August? I have told lots of people about this blog as it is so good. Lets have some updates. Good luck.

    Unsuitable or offensive? Report this comment

View results 10 per page | 20 per page

Have your say

You must sign in to make a comment

sign in register
  • Email
  • Comments (20)
  • Save
Sign in

Email Newsletters

I'm searching for in
Desktop Site | Mobile Site