Time and money: How Alma compares with Rogate
Alma HouseRogate House
TenderFinal accountPrice adjusted for inflationTenderTarget final account
Numbers of residential units108108 192192
Budget (£m)5.386.357.6212.613.3
Unit cost (£)49,80058,80070,56065,50069,270
Construction period117 weeks115 weeks 88 weeks90 weeks
Start on site dateFebruary 1997February 1997 September 2000September 2000
Completion dateMay 1999April 1999 May 2002June 2002
Output weeks per unit1.081.06 0.460.47
Output per week (£)46,00055,00066,000143,000148,000
Time and money: How Alma compares with Rogate
Alma HouseRogate House
TenderFinal accountPrice adjusted for inflationTenderTarget final account
Numbers of residential units108108 192192
Budget (£m)5.386.357.6212.613.3
Unit cost (£)49,80058,80070,56065,50069,270
Construction period117 weeks115 weeks 88 weeks90 weeks
Start on site dateFebruary 1997February 1997 September 2000September 2000
Completion dateMay 1999April 1999 May 2002June 2002
Output weeks per unit1.081.06 0.460.47
Output per week (£)46,00055,00066,000143,000148,000