Welcome to building.co.uk. This site uses cookies. Read our policy.

Compare and contrast
Lion Plaza Swiss Re
 2000 
   
July 2000 Construction starts  
   
  December 2000 Work starts
 2001 
   
   
   
September 2001 Steel erection starts  
  October 2001 Steel erection starts
 2002 
   
   
   
September 2002 Steelwork contractor Wescol goes into receivership  
  November 2002 Topping out ceremony
 2003 
   
   
  June 2003 Last piece of glass installed
Autumn 2003 Handover of shell and core due  
  December 2003 Interior fit-out due for completion
 2004 
March 2004 First tenant, White & Case, due to move in