Welcome to building.co.uk. This site uses cookies. Read our policy.

Information gathering6 weeks
Invasive site trail holes20 weeks
Determination of impacts and collation of C3 and C4 quotations14 weeks for each
Arrangement of new service connections25 weeks
Abandonment of existing assets 13 weeks
Preparation to construct minor works5 weeks
Preparation to construct major works13 weeks
Construction and commissioning of minor works6 weeks
Construction and commissioning of major worksSeveral months