What construction bosses think of Latham
Q Do you see any evidence of government becoming a best-practice client ?   Yes 33% No 67%
Q What proportion of your organisation’s government-funded projects use the New Engineering Contract?     Average 5%
Q What proportion of your contracts have a partnering arrangement with the employer ?     Average 22%
Q For single-stage design-and-build tenders, what proportion have three or fewer tenderers?     Average 18%
Q For two-stage design-and-build tenders, what proportion have five or fewer tenderers?     Average 61%
Q In instances involving substantial site investigation costs, these costs are      
a paid by the employer     Average 57%
b shared between tenderers   Average 9%
Q Are costs being saved by      
a prefabrication and pre-assembly becoming part of the design considerations?   Yes 71% No 29%
b the development of standard products and processes?   Yes 64% No 36%
c improvement in designers’ knowledge on the performance of components and materials?   Yes 52% No 48%
Q Does your organisation have quality assurance certification for      
a management? Yes 79% In process 9% No 12%
b construction? Yes 90% In process 7% No 3%
Q If you have a quality assurance certification, is it improving your      
a productivity?   Yes 62% No 38%
b product?   Yes 90% No 10%
Q What proportion of your tenders do you feel are evaluated fairly?     Average 74%
Q What proportion of interim payments are received within the period specified in the contract?     Average 69%
Q If you have experienced adjudication, does this provide a satisfactory way forward? Yes 27% No 20% n/a 53%
Source: Drivers Jonas. The project manager surveyed chief executives at Britain’s top 200 contractors in autumn 1998, of whom some 70 responded.