Elemental cost analysis of out-turn cost of building (January 2003)
ElementTotal cost/m2 (out-turn)cost/m2 gfa% splitNotes
Substructure405,500208.267.41concrete strip foundations and reinforced ground floor slab; anti vibration provisions
Superstructure    
Frame200,800103.133.67structural steel frame
Roof292,300150.135.34Planja metal deck with Trocal single-ply membrane; feature rainwater goods
Stairs000 
External walls546,500280.689.99aluminium curtain walling, Sto render system, cedar wood cladding; galvanised mesh screens
Windows and external doors57,00029.281.04 
Internal walls127,54765.512.33plasterboard metal stud partitions
Internal doors29,91615.370.55hardwood veneer doors in hardwood frames
Internal finishes    
Wall finishes86004.420.16emulsion paint; tiled splashbacks
Floor finishes50,75826.070.93raised access flooring; carpet tiles generally; vinyl to wet kitchen and WC
Ceiling finishes53,05827.250.97Casoline curved or flat plasterboard
Fittings    
Fittings51,17726.290.94kitchenette area; general signage; laboratory fittings
Sanitary fittings20001.030.04 
Services    
Public health/mechanical735,464377.7413.44 
Electrical333,511171.306.10 
Cleanrooms 995,669511.3818.20 
Lifts000 
BWIC39,40020.240.72 
Site works    
Hard and soft landscaping552,400283.7210.10access road; timber cribb wall; general planting and paving; ramps; balustrades
External services and drainage243,500125.064.45below-ground drainage, manholes and services; transformer and enclosure
Service connections9,7004.980.18 
Sundries181,70093.323.32 
Prelims and pre-con fee 418,500214.957.65 
Overheads and profit135,00069.342.47 
Total5,470,0002809.45100