Copper lead times comparision
ElementDec 04-Dec 05Dec 05-Jun 06
HV/LV switchgear 8 to 12 weeks*16 to 20 weeks
Copper SWA cables (Standard Booklet Cables)10 days 2 weeks
Copper pipework, standard sizes3 to 5 days 5 to 10 days**
* technical projects up to 16 weeks
** likely to get nearer to 10 days if stock continues to reduce