In October 2003, St Peter’s Rugby Football Club, occupiers of a clubhouse and sports field in Cardiff, engaged Michael John Construction (MJC) under a JCT IFC 1998 contract. The club required that their site be cleared of the former clubhouse in order for it to be sold to developers. The work reached practical completion in August 2004. Problems arose regarding payment of the contractor’s invoices. MJC referred the dispute to adjudication in May 2005.

Unable to distinguish the true identity of the employer, an unincorporated football club, MJC served the adjudication notice on the current trustee, Mr Matthews, ‘on behalf of St Peter’s RFC’. The adjudicator awarded £92,571 plus interest and costs in favour of MJC.

In August 2005 it was then disclosed during the Part 24 enforcement proceedings that the true trustees at the time the contract was entered into were Mr Golledge, Mr Childs, and Mr Carpanini. A second adjudication was then commenced between MJC and the three original trustees, including Mr Matthews as the signatory. The adjudicator again made an award in favour of the contractor. When the Part 24 application came before the court, HHJ Coulson QC ruled against the defendant (see Michael John Construction Ltd v Golledge & Ors [2006] EWHC 71, TCC, 27 January 2006). Both the three original trustees and their agent Mr Matthews (Director of Development and signatory at the time of the contract) were held to be personally liable.

The club then served a notice of arbitration on MJC in the name of ‘St Peter’s RFC’. It was not accepted by the caimant as a valid notice since it did not reflect the findings of the enforcement action. During the arbitration, the arbitrator permitted further evidence that had not been put before the court or the adjudicators, and determined that the identity of the parties who concluded the construction contract was in fact Mr Matthews on behalf of himself and the Club. The claimant appealed under s67 of the Arbitration Act 1996.