Table 1: Redundancy and N + 1 | |||
System description | Number and capacity of modules | Total installed capacity | Redundant installed capacity |
1 module | 1 x 1000 kVA | 1000 kVA | Zero |
1 + 1, (ie N =1) | 2 x 1000 kVA | 2000 kVA | 1000 kVA |
2 + 1, (ie N = 2) | 3 x 500 kVA | 1500 kVA | 500 kVA |
3 + 1, (ie N = 3) | 4 x 350 kVA | 1400 kVA | 400 kVA |
4 + 1, (ie N = 4) | 5 x 250 kVA | 1250 kVA | 250 kVA |
etc. |
Table 2: Cost summary | ||||
Element | Range within analysis | Cost model | ||
Max £/m2 | Min £/m2 | £/m2 | % | |
Environmental control systems | 1200 | 640 | 940 | 27 |
Ventilation systems | 190 | 150 | 160 | 5 |
Electrical installations | 2200 | 1500 | 1905 | 55 |
Protective installations | 250 | 200 | 227 | 6·5 |
Communications installations | 200 | 150 | 155 | 4·5 |
Special installations | 100 | 50 | 80 | 2 |
Total | 4140 | 2690 | 3467 | 100 |
PROJECT DETAILS | |
Cost datum Third quarter 2004 | |
Location Central London | |
Gross office internal floor area 35000 m2 | |
Data centre net area 1000 m2 | |
Procurement route Competitively tendered lump sum with contractor’s design responsibility | |
DESIGN CRITERIA | |
External design temperatures | |
Winter – 4°C (saturated) | |
Summer 28°C db, 19°C wb | |
Internal design temperature | |
Offices 22°C +/- 2°C | |
Fresh air ventilation 15 litres/s/person | |
COST BREAKDOWN | |
ENVIRONMENTAL CONTROL | |
Chilled water plant for enhanced cooling to data centre, serving 1000 W/m2 with redundancy to N + 1 standard: 1000 m2 at £425/m2 | £425/m2 |
Chilled water distribution within data centre to free-standing cooling units with associated water softening plant, condensate, humidification and insulation. 1000 m2 at £515/m2 | £515/m2 |
Environmental control total | £940/m2 |
VENTILATION SYSTEM | |
Supply and extract ventilation, including dedicated gas extract system. Low level distribution, including floor grilles: 1000 m2 at £160/m2 | |
Ventilation system total | £160/m2 |
ELECTRICAL INSTALLATION | |
Mains distribution with single incoming hv, N + 1 transformers, distribution busbars and cables. 1000 m2 at £140/m2 | £140/m2 |
Standby generators with redundancy to N + 1 standard, controls, fuel storage, exhaust flues. 2250 kVA at £190/kVA. | £427/m2 |
UPS back-up system, 10 minute batteries with 10 year life, input/output switchboard. (2 + 1) 600 kVA at £215/kVA | £387/m2 |
Critical mains distribution and lv switchboards, pdus, transfer switches for dual-fed equipment. 1000 m2 at £730/m2 | £730/m2 |
Cabinet supplies, dual armoured cable fed via BS 4343 outlets. 600 supplies at £230 each. | £138/m2 |
Lighting, suspended luminaires, wiring and controls. 1000 m2 at £48/m2 | £48/m2 |
Data cable containment, underfloor cable basket. 1000 m2 at £35/m2 | £35/m2 |
Electrical installations total | £1905/m2 |
PROTECTIVE INSTALLATIONS | |
Gaseous extinguishing system using inert gas. 1000 m2 at £192/m2 | £192/m2 |
Leak detection, underfloor adjacent to cooling plant and pipework. 250 m at £80/m | £20/m2 |
Earthing and bonding 1000 m2 at £15/m2 | £15/m2 |
Protective installations total | £227/m2 |
COMMUNICATIONS INSTALLATIONS | |
Analogue addressable fire detection and alarm system providing Category L1 cover plus interface with gaseous system. 1000 m2 at £30/m2 | £30/m2 |
Extra for very early smoke detection, aspirating system sensing above and below raised floor. 1000 m2 at £50/m2 | £50/m2 |
Security, cctv, intruder detection and access control, linked to main system (based on 20 cameras and four access points) 1000 m2 at £75/m2. | £75/m2 |
Communications installations total | £155/m2 |
SPECIAL INSTALLATIONS | |
Building energy management system, controls and monitoring, interfaced to main building management system. | |
1000 m2 at £80/m2 | £80/m2 |
Special installations total | £80/m2 |
TOTAL COST OF DATA CENTRE SERVICES | £3467/m2 |
EXCLUSIONS | |
Inflation beyond third quarter 2004 | |
General builders’ work | |
Specialist builders’ work such as floor strengthening, blast protection, screening for electromagnetic interference | |
Fit-out works beyond the data centre boundaries | |
External works such as enhanced hv supply or dual hv feeds | |
Main contractor’s overheads, profit and attendance | |
Main contract preliminaries | |
Professional and prescribed fees | |
Contingencies and design reserve | |
Tax allowances | |
VAT |