Shopping Centres | ||
Unit rate (£/m2 gifa) | Element cost /m2gifa) | |
Sanitaryware | 1.60 | |
Sanitaryware to public toilets and centre management | 1.60 | |
Disposal installations | 10.75 | |
Rainwater disposal; cast iron downpipes and fittings. | 10.75 | |
Water installations | 3.75 | |
Domestic water installations; capped off supplies to retail units, hot and cold water service to landlord’s areas. | 3.75 | |
Space heating and air treatment | 25.95 | |
Supply and extract ventilation installation to mall; indirect gas-fired heat source; chilled water/dx circuits including chiller plant; air handling units; perimeter ductwork distribution; high quality diffusers. | 11.30 | |
Condenser water circuit to retail units. | 14.00 | |
Warm air curtains to mall entrances. | 0.65 | |
Ventilation | 22.60 | |
Mall/shop extract and smoke extract systems; mall extract through the rear of shop units. | 10.75 | |
General ventilation systems; discrete extract systems to loading bays, service corridors, plant rooms, toilets etc, with provision for make-up air. | 11.85 | |
Gas installation | 1.20 | |
Gas installation to air handling plant. | 1.20 | |
Electrical installations | 47.55 | |
HV connection. | 1.10 | |
Mains and sub mains distribution; including power supplies to mechanical plant. | 12.70 | |
Standby generation and essential supplies; landlord’s requirements only. | 6.10 | |
Small power to landlord’s areas. | 5.00 | |
Allowance for ducts and access wireways. | 4.85 | |
Landlord’s lighting; to back of house, toilets and centre management areas. | 7.00 | |
Mall lighting. | 9.70 | |
External lighting. | 1.10 | |
Protective installations | 25.00 | |
Lightning protection. | 1.10 | |
Sprinkler installation; distribution and heads to back of house areas; connections to retail units; share of infrastructure. | 18.50 | |
Hosereel installation. | 1.60 | |
Wet riser installation. | 2.70 | |
Earthing and bonding. | 1.10 | |
Communications installations | 15.70 | |
Fire alarm system; fully addressable, smoke detectors, infrared sensors and public address. | 13.00 | |
CCTV system. | 2.70 | |
Special installations | 21.50 | |
BMS control installation. | 21.50 | |
TOTAL COST | 175.60 |