Public health servicesUnit Rate (£/m2 gifa)
Incoming supply
New service from existing site supply, including metering and valves. Item @ £54 000
2.51
Cold water services
Sterilisation and filtration equipment; booster pump set and ancillaries; water storage tanks and ancillaries; distribution pipework, fittings, accessories, insulation, including final connections to appliances. Item @ £517 000
24.05
Potable cold water distribution pipework, fittings, accessories, insulation, including final connection to appliances Item @ £51 0002.37
Hot water services
Calorifiers, pipework, fittings, accessories Insulation, including final connections to appliances. Item @ £324 000
15.07
Above ground drainage
Above ground internal soil and vent pipework, fittings, accessories. Item @ £395 000
18.37
Rainwater installation
Above ground rainwater installation; gutters, downpipes, outlets and connections. 21 500 m2 @ £1/m2
1.00
Preliminaries
Testing and commissioning
 
Item @ £21 0000.98
Item @ £49 0002.28
Public health services total66.63
Mechanical services
Gas installation
Gas supplies for catering and laboratories. From existing plantroom to new building via link bridge. Item @ £25 000
1.16
Heat source
From existing steam plant. New distribution from existing plantroom to new building via link bridge, serving calorifiers, ahus and plate heat exchangers; total capacity 4·5 MW; steam and condensate distribution system. Item @ £163 000
7.58
Space heating
MTHW heating system serving ahu’s and dhws calorifiers; including 3 nr 1100 kW plate heat exchangers (at 50% each), pump sets, valves, steel pipework, fittings, accessories and insulation. Item @ £550 000
25.58
LTHW heating system serving radiators to staff only areas and lst radiators/radiant panels to patient and non staff areas; including 2 nr 1200 kW plate heat exchangers (at 100% each), pump sets, valves, mild steel pipework,fittings, accessories and insulation. 18 610 m2 @ £53/m245.88
Cooling
CHW system serving ahus and fan coil units to individual spaces on each floor; including 2 nr 920 kW air cooled chillers (at 100% each), fan coil units, pump sets, pressurisation unit valves, mild steel pipework, fittings, accessories and insulation.13 575 m2 @ £42/m2
26.52
DX cooling systems to server rooms; total capacity 20 kW. 4 nr @ £7,0001.30
VentilationAir handling units; 30 nr with a total duty of 63 m3/s. Item @ £640,00029.77
Supply and extract ventilation system serving laboratories, operating theatres, wards and kitchen/dining etc; ductwork, dampers, attenuators, grilles, fittings, insulation and accessories. 11 200 m2 @ £118/m261.47
Toilet extract ventilation, total duty 8 m3/s; dampers, attenuators, ductwork, grilles, fittings and accessories. Item @ £175 0008.14
Controls
Central ddi control system including head end. System includes mccs, local starters/isolators and associated power, control and communication wiring and wire ways. Item @ £645 000
30.00
Protective installations
Dry riser installation, 4 nr risers Item @ £37 000
1.72
Preliminaries
Testing and commisioning Item @ £110 000
5.12
Preliminaries Item @ £390 000 18.14
Mechanical Installations Total262.38
Electrical installation
HV installation
Incoming hv main from existing site network. 3 MVA capacity. Item @ £110 000
5.12
Packaged sub-stations at lower ground and roof levels including hv supply to roof. Item @ £380 00017.67
LV distribution
LV distribution to local boards; XLPE/SWA/LSF cabling generally; containment; power supplies to mechanical plant and lift motor rooms Item @ £396 000
18.42
Distribution boards; complete with mcb/hrc protective devices as required.Item @ £89 0004.14
Small power installation
Supplies to final circuits; including containment. Item @ £530 000
24.65
Emergency power installation
2 nr 1000 KVA generators; flues; connections to hv panel; distribution including containment. Item @ £328 000
15.26
UPS systems and associated equipment; 2 @ 30Kw, 1 @ 60 kW. Item @ £50 0002.33
Lighting installation
Lighting installation; recessed modular fluorescent fittings complying with LG3 category 2 for offices; recessed modular fluorescent fittings with diffusers to corridor/ancillary areas; colour corrected fluorescent lamps & compact low energy lamps to ward areas. Item @ £455 000
21.16
External lighting
Item @ £74 000
3.44
Emergency lighting installation; central battery/inverter units; mics cables. Item @ £418 00019.44
Bed head trunking installation
Bed head trunking installation including cabling; incorporating room lighting, night light, reading light, small power outlets, nurse call system controls, data and telephone outlets and medical gas outlets. Item @ £271 000
12.60
Communications installations
IT structured cabling installation; active equipment, containment, wiring, outlets suitable for voice or data communication. 14 915 m2 @ £21/m2
14.57
Fire alarm installation; analogue addressable system; detectors, call points, sounders, beacons, control panel; linked to existing hospital system. Item @ £582 00027.07
Nurse call installation; fully multiplexed type to all patient areas. 8350 m2 @ £43/m216.70
Radio and television system installation to all ward areas; cabling and outlets. 4200 m2 @ £6/m21.17
Telephone installation; containment, wiring and outlets. Item @ £67 0003.12
Security installation
CCTV installation to external façade; power and control wiring; cameras; monitors; duplex recording equipment. Item @ £86 000
4.00
Security and access control installation; audio visual door entry system to wards; swipe card door access to wards and main areas; intruder alarm system. Item @ £113 0005.26
Protective installations
Earthing and bonding 21 500 m2 @ £1/m2
1.00
Lightning protection 21 500 m2 @ £1/m21.00
Preliminaries
Testing and commissioning Item @ £127 000
5.91
Preliminaries Item @ £305 000 14.19
Electrical installations total238.22
Lift Installation
All figures include preliminaries and testing and commissioning
33 person bed passenger lift, traction, each serving four floors. 4 nr @ £120 00022.33
2000kg theatre goods lift, traction, each serving four floors. 2 nr @ £96 000 8.93
2500 kg goods lift, traction, serving four floors. 1 nr @ £120 0005.58
Lift Installation total36.84
Exclusions
Main contractors profit, overheads, attendances and preliminaries
Builderswork in connection with engineering services
Loose furniture, fittings and equipment
Sanitaryware
Below ground drainage
Statutory authority connection charges
Professional fees
VAT
Inflation beyond fourth quarter 2001
Any works in associated buildings
Special installations
Medical gases installation; pipework, outlets, valves and fittings. Item @ £775 00036.05
Special installations total36.05
Total building services installation cost£640.12