| Copper lead times comparision | ||
| Element | Dec 04-Dec 05 | Dec 05-Jun 06 |
| HV/LV switchgear | 8 to 12 weeks* | 16 to 20 weeks |
| Copper SWA cables (Standard Booklet Cables) | 10 days | 2 weeks |
| Copper pipework, standard sizes | 3 to 5 days | 5 to 10 days** |
| * technical projects up to 16 weeks | ||
| ** likely to get nearer to 10 days if stock continues to reduce | ||