| Material assessment: ground slab | ||
| Total embodied carbon emissions/m2 of slab area103.2 | ||
| Concrete mix based on 30% PFA substitution of OPC | ||
| Kg embodied carbon/unit | Kg embodied carbon/m2 gifa | |
| Excavation (m3)/ PFA mix | 11.1 | 6.66 |
| Disposal (m3) | 16.7 | 10.02 |
| Blinding, 75mm thick (m3) | 9 | 0.72 |
| Concrete, 200 thick, OPC cement (m3) | 309.1 | 61.82 |
| Reinforcement, A252 mesh (kg) | 0.44 | 1.72 |
| Movement joints (m) | 8.7 | 0.44 |
| Damp proof membrane (m2) | 0.7 | 0.7 |
| Insulation board (m2) | 1.7 | 1.7 |
| Total embodied carbon emissions/m2 of slab area | 83.8 | |
| Exclusions: demolition and disposal of slab construction at end of life | ||
| Building assessment: distribution centre | ||||
| £/m2 gifa | % | Kg embodied carbon/m2 gifa | % | |
| Substructure | 59 | 17.4 | 146.5 | 42.3 |
| Frame, upper floors and stairs | 60.7 | 17.9 | 68.4 | 19.7 |
| Roof | 48.5 | 14.3 | 41.6 | 12 |
| External walls, windows and doors | 14.7 | 4.3 | 13.3 | 3.8 |
| Internal walls and doors | 0.8 | 0.2 | 2.3 | 0.7 |
| Internal finishes | 4.4 | 1.3 | 5.6 | 1.6 |
| Building services installation, including dock levellers | 31.8 | 9.4 | 30.2 | 8.7 |
| External works and services | 81.4 | 24 | 38.6 | 11.1 |
| Preliminaries | 37.5 | 11.1 | ||
| Total construction cost/m2 gifa | 338.8 | 100 | ||
| Total embodied carbon emissions/m2 | 346.5 | 100 | ||
| Exclusions: site preparation, site abnormals, distribution centre and administration area fit-out, operating equipment, professional fees | ||||