With the cricket season fast approaching, Dobson White Boulcott was forced to bend the procurement rules to complete a very mixed-use project.
Dobson White Boulcott had to sidestep the normal rules of procurement to complete the £3.9m Derwent Gateway Centre in double quick time. The client needed the 3,306m2 cricket club and community centre built in less than nine months ready for the start of the 2004 cricket season. While the overall 33-week project came in slightly late, QS DWB managed to get the cricket facilities up and running in good time.
"We didn't have time for the normal procurement steps," explains Richard Dobson, co-founder of DWB. Instead the firm did a very early tender for the contractor, "based on profit, margins, overheads and their ability to manage sub-contractors, rather than a full bill of quantities", he reveals.
Dobson said the complexity of the project and the tight timeframe meant the project's success would hinge on getting decent local subbies.
"We needed a contractor with a good handle on local sub-contractors and with sufficient size and weight to deal with them," says Dobson. To find the right outfit DWB drew on its own contacts and took advice from the client, Derbyshire County Cricket Club and Derwent Community Team. They chose Bowmer and Kirkland's Derbyshire office.
The project's complexity stemmed from the different uses of the building and its corresponding mix of design features.
The scheme combines three elements: a cricket club and grandstand, which is primarily timber-clad; a cricket coaching hall, which maximises daylight through translucent materials; and a community sports centre, which is clad in plastic strips.
The building's cladding had the highest potential to scupper the project schedule as it had been used very little in the UK. The curved and coloured plastic, supplied by German firm Rodeca and manufactured in Poland, was specified by architect and project manager, Fluid.
The cladding looked fragile, we had our moments with it, but the client had the courage of our convictions
Richard Dobson, co-founder of DWB
"It looked fragile and we had our moments with it, but the client had the courage of our convictions," says Dobson.
In the event the material proved both very easy to fix and good value. The bill for external walls came in at £324,544 or £98.17 per metre.
The cricket facilities were completed two weeks late but still in time for May 2004.
The community and sports elements were six weeks behind programme, but Dobson says this was due to electricity supplier EDF turning up late and he emphasised that it was the cricket facilities that were the most time-critical.
The project kept within budget after DWB agreed a guaranteed maximum price with the contractor before work started on site. The ability to clinch this deal was one of the advantages of bringing in the contractor early, concludes Dobson.