The claimant applied for summary judgment arising out of an adjudication decision and claimed for costs on an indemnity basis. In the course of the adjudication the adjudicator rejected the defendant’s challenge to his jurisdiction, finding that there was a contract in writing between the parties.

The defendant challenged the enforcement proceedings on three grounds. First, the adjudicator did not have the necessary jurisdiction to decide the dispute because there was no contract in writing.

Secondly, because the defendant is a company based in Jersey, the service claim form was invalid. Although the defendant had received the claim form, the claimant had not obtained permission from the court to serve the claim outside of jurisdiction. The defendant’s final challenge was that the claim form did not include a statement of the ground on which the claimant was entitled to serve it out of the jurisdiction.

There were three issues before judge Coulson. The first issue to be decided by the court was whether or not there was a contract in writing. In order to answer this question the court was to examine whether or not, when the jurisdiction point was raised in front of the adjudicator, the parties agreed to be bound by his conclusions.

The second issue was whether or not the service of claim form was invalid because the claimant had not obtained permission from the court.

Finally, what was the effect of the claimant’s omission to include a statement of the ground on which the claimant was entitled to serve the defendant outside jurisdiction?