It was not only the scheme's incredibly short construction programme that was making Scrine apprehensive. There were a host of other challenges to overcome. "There were a large number of complicated services to install, space inside the building was restricted, and there was a ban on out of hours working," explains Scrine. Outside the building things were no better: "There was no site storage, and we knew there'd be the usual problem of deliveries to a City site," he adds.
The ambitious project will see the reincarnation of Britannic House. The drab 1960's megalith that was petrochemical giant BP's old hq will be turned into a stunning speculative office block and given a new name: CityPoint. The building's rebirth will involve recladding the entire tower, extending the office floor plates, and adding a new seven-storey annexe, a top floor restaurant and a basement health club. The revamp will set developer Wates City of London Properties back over £160 million.
"With capital tied up in the scheme we had to pressurise its construction," says Rodney Clutton, joint managing director of Wates City. To ensure the developer received a prompt return on its capital, the refurbishment went ahead only after Wates City had pre-let the new annexe and first eight floors of the tower, along with floors 20 to 22 to a brace of US legal firms.
This made the services engineers' already difficult task of meeting the 90-week construction period more formidable. Scrine's biggest worry now was how to schedule the works to allow the tenants to occupy the building months before the services were complete.
Despite Scrine's reservations, AMEC Capital Projects Building Services1 successfully tendered for the project and were appointed in late 1998, when it was still known by its more familiar moniker of Matthew Hall. The JCT 81 (with amendments) contract gave AMEC responsibility for the detailed services design of the shell and core installation and for a gamut of services including: mechanical, electrical, public health, fire engineering, fire alarms and security and, unusually, a £4 million building package.
Consulting engineer Foremans produced a concept design for the scheme, based on a four-pipe fan coil system serving the offices. Fortunately for the contractor, fit-out to the tenant's floors was outside the contract.
"We were appointed on 6 October 1998 and were given a completion date of 14 December 2000," says Scrine, "and somewhere between these two dates we had to achieve some 70 handovers to allow the tenants to move in." AMEC had just three months to review the design concepts, assess their buildability and to investigate how the services could be co-ordinated. "The conclusion was that if we wanted to meet the programme, our installation had to be right first time," says Scrine.
Rather than rush into design, AMEC decided to take a step back. "It was worthwhile because it allowed time to get our mindset clear," explains Scrine, "We had a three month design audit period to understand the job and to look at how the services would fit. But the biggest challenge was getting design certainty."
In the countdown period before the project took off, AMEC Capital Projects Building Services called on the skills of another part of the AMEC Group, the equally concisely named AMEC Central Engineering and Design, who in turn called in consultant Ove Arup to help finalise the design. Other specialists on-board at this early stage included the boiler, chillers, pumps and air handling unit manufacturers. "It was a very intensive period," recalled Scrine.
AMEC assigned a team of 22 cad draughtsmen to the project. They worked with the design team to produce three-dimensional detail drawings, while the ductwork contractor was linked to the network through AMEC's file server. "This had the advantage of giving us co-ordinated drawings at a very early stage," explained Scrine.
The scale of the installation is impressive. There are over 40 separate pumped systems and 70 separate air handling systems. "With such a difficult site we knew that we were going to have to use extensive off-site assembly and prefabrication for many of the services and equipment modules," explained Scrine, "Or, to put it another way, things had to be built-in and not bolted on."
"The extent of prefabrication on this project is unrivalled in terms of its complexity," says Scrine. Over 95% of the primary and secondary pipework has been prefabricated, and 60% of the plant has been delivered to site as prefabricated modules ready to drop into place. Everything from pumpsets to distribution boards were modularised.
“If we wanted to meet the programme, our installation had to be right first time” – Bob Scrine.
Aside from the programme advantages, prefabrication also reduced the size of the workforce and their facilities, on the congested site. It also brought the usual quality benefits factory manufacture brings to an installation. Most important of all, prefabrication allowed the modules to be stored off-site. Nevertheless, in the rooftop plantroom many of the ahus would have to be craned into position and wrapped in tarpaulin before the steelwork roof structure was in place.
"We had some big discussions and debates with co-ordinating contractor John Mowlem," says Jerry Gardiner, senior mechanical project manager. The three-month design review period finished in January 1999, and AMEC started installing the services in February 1999. By Easter, the boiler and chiller plant were safely in the depths of the basement plantroom.
Four separate plantrooms were created in the refurbished building, with floors 24-35 served from a rooftop plantroom. However, the weight of the plant including the cooling towers was too heavy for the existing structure so, 125 m up, the top two floors of the building had to be demolished and rebuilt to cope with the increased load. "It worried me stiff," admitted Oliver Simm, project director of co-ordinating contractor John Mowlem.
Structural constraints forced the engineers to use over 20 pipework and ductwork risers, and a series of electrical risers clustered around the building's central core. Aside from the rooftop plantroom serving the tower's top floors, there are three main plant areas. The basement serves the floors up to level 14 and, via a separate riser, up to level eight of the annexe. Level 14 plant supplies the offices up to level 23 while a smaller plantroom on level eight, in the west annexe, serves that side of the extension.
The majority of AMEC's work was in the basement, where the boilers, part of the air handling plant and most of the electrical installation is located. "With the three tower cranes fully occupied feeding materials to the cladding contractors racing up the outside of tower, we knew getting plant and materials into the basement was not going to be easy," explains Gardiner. "It was obvious that the only way we could keep things under our control was to put in our own crane."
Project manager John Shreeves and Partners had lumped all builder's work relating to the m&e into the services package. "This meant we had to cut holes and build all the walls connected with the services and paint them afterwards," explained Scrine, "but having the contractor under our control allowed us to decide what to build and when." With a builder's work package valued at over £4 million, AMEC employed its own contractor.
Commissioning
To meet handover dates for tenant's floors the services installation had to be prioritised. Working with the contractor from the project's outset was specialist Burgess Commissioning. Its role was to ensure the right first time principle, that AMEC was keen to embrace for the main service runs, was extended to the service connections on the tenanted floors.
The contractor had two deadlines to meet for the tenant areas: an A-date and a B-date. The A-date was the date installation had to be complete to that area for the fit-out contractors to connect to, while the B-date was when services had to be live ready for the tenants to move in.
At the first B-date of the end of August 2000, Scrine had to prove that the services systems would deliver. This involved the commissioning contractor testing off-site. For the air supply system the volume control dampers in the ductwork were pre-set by inserting a perforated plate in the ductwork to simulate the predicted pressure drop of the ductwork system.
On-site, a portable ductwork leakage test unit was connected to each branch duct via the damper access door, the dampers set and the branch velocity probe calibrated again using a perforated plate to simulate the resistance. The same principle of simulating the floor load to set valve positions was used for the water services.
With the project about 90% complete, the team is confident of meeting the December 2000 deadline. Bob Scrine admits that next time around there are some things AMEC would do differently: "There is room for improvement," he says. "Next time round we'd ensure the modular plant was pre-wired before coming to site.
Pointing the way for services
Servicing 36 storeys is a tall task. Taller still when the building is for multiple-tenants, but a task that m&e consulting engineer Foremans met head-on. The client’s brief was simple: a flexible, high-class development suitable for commercial letting. Foremans had worked with Wates on several previous projects so was aware of the client’s wishes, which made the design process faster. To make sense of the scale of CityPoint servicing was broken down into sizable chunks. The building is effectively split into three sections with a separate plantroom serving each area. Plantrooms are sited in the basement, on level 14 and at roof height on level 36, these feed floors up to level 12, levels 15 – 23 and levels 36 – 24 respectively. In addition, each floor is divided into east and west zones for separate letting if required. The physical nature of the structure had a large impact on the choice of services. The floor-to-floor depth is just over 3 m, and the false ceiling void is very tight. Also, Foremans decided on a series of shallow multiple risers to maximise the lettable area and the services distribution on the floors. The tight areas available for the services plant by using this system, Foremans says, limited its choice to that of an air-side four-pipe system. Within the main tower every floor is virtually identical, the only difference being the core areas, where some have lift shafts running through and others have none. Eight risers per floor provide supply and extract services. These are sited on a riser duct around the central core. Water services are similarly provided. Scheduled heating at 70°C is supplied to the floors by three 6 MW gas-fired boilers housed in the basement. These produce medium temperature hot water to serve the air handling units coils and plate heat exchangers via secondary mthw circuits. In order to balance the hvac systems prior to occupation, a section of duct with a damper in it has been installed to simulate the completed version. When a tenant completes the section it is simply rebalanced. A motorised fire damper serves the dual purpose of a balancing damper. Pipework risers have been completed as a loop, into which tenants can tap their pipework to serve fan coils. Efficiency measures Various measures have been taken to reduce energy consumption. Foremans says that it avoided the use of specific heat recovery plant due to space constraints in the plantrooms. All air handling plant incorporates thermal wheels. The segmenting of the building also plays a part, enabling the shutting down of systems in specific areas. Control is on airside by pressure transducers in the ductwork which feed back into the inverter drive of the supply/extract fans. A velocity sensor on the supply air branch also checks whether the correct amount of air is entering each area. An alarm sounds in the main building control room to signal any adjustments required via the bems. Electrical services Electricity is supplied to the building via two Solkor ring mains from London Electricity so, if one part of the ring fails, the supply is carried by the other ring. The maximum demand is 9 MVA, which is split into two sections, 6 MVA for the landlords supply and 3 MVA for the main tenants and three chillers. Electricity is supplied to the floors by high voltage cables that run through the building to 13 sub-stations in the plantrooms. This was necessary due to the vast size of the building to avoid power loss; if low voltage cabling was used for distribution, the power drops would be so large that massive copper cables would be needed. From the sub-stations, transformer built-in package units bring the electricity supply down to 400 V and low voltage busbars feed the landlord’s plant and tenants supplies via lv switchboards. There are two main 800 A runs in the tower and six runs in the attached low-rise buildings. Tenants distribution panels consisting of lighting and small power distribution boards, metering, connections to the bems and changeover contactors are all housed in a purpose-made factory built panel. The engineers perceived this as the best way of achieving quality of installation on site. All the panels can be monitored for energy use and within the panels we provide the automatic changeover systems to shed load of non-essential supplies. A separate landlords distribution centre consists of rising busbars, which are dedicated and encapsulated for security. These feed the landlords small power distribution boards which provide services to the floors, lift lobbies, staircases, toilets, etc. Four 1300 kVA diesel emergency generators located in the basement with discharge flues at roof level back-up the landlord’s system. These also provide fire-fighting and life safety systems in the building, 50% of the tenants lighting and part of their small power. There is also flexibility to supply individual tenants ups systems if required. The entire m&e system is run from a central control room in the main building, the building energy management system being a Johnson Controls’ Metasys. Commissioning of the project is ongoing.Costs
Total construction cost: £160 million M&E installation: £44 millionDownloads
Cross-section of Citypoint tower
Other, Size 0 kb
Source
Building Sustainable Design
Postscript
1AMEC Capital Projects Building Services was called Matthew Hall when the firm started the CityPoint project. Andrew Pearson BEng MSc is technical editor of Building.
Credits
Client Wates City of London Properties Co-ordinating contractor John Mowlem Construction Architect Sheppard Robson International Client's agent, project manager, and quantity surveyor John Shreeves and Partners Services consultant Foremans Structural engineer Bunyan Meyer and Partners Shell and core services installation AMEC Capital Projects Building Services (formerly known as Matthew Hall) Commissioning management Burgess Commissioning