N G Bailey's innovative lighting installation has played a part in the fast track completion of a new UK hq for Talisman Energy (UK) in Aberdeen.
The rapid installation was made possible by a plug-and-play approach to the lighting, using equipment from Hager. "By using Hager's Klik system, not only did we significantly cut down on labour time, but due to the flexibility it gave us, we came onto site far earlier than normal. The first fix for the entire installation was completed in just a few days," said N G Bailey's project manager Kenny Mitchell. The project took under a year.
Source
Electrical and Mechanical Contractor