Electrical contractor Waring & Marriott has overcome a tight contract programme and restricted space to complete the installation of the main switchboard at a new Nottinghamshire printworks.
The contract included the design of a main switchboard with two 250 kVA panels, which would fit into a narrow, corridor-like plantroom too small for a conventional panel.

The design, order and installation had to be completed in six weeks to meet commissioning schedules for two new printing presses.

The solution involved the Memshield 2 MPS modular panelboard system from MEM Circuit Protection and Control.