| PFI’s progress: Annual breakdown | ||
| Year | Number of signed projects | Capital value (£m) |
| 1987 | 1 | 180 |
| 1988 | 0 | 0 |
| 1989 | 0 | 0 |
| 1990 | 2 | 336 |
| 1991 | 2 | 6 |
| 1992 | 5 | 518.5 |
| 1993 | 1 | 1.6 |
| 1994 | 2 | 10.5 |
| 1995 | 11 | 667.5 |
| 1996 | 38 | 1559.5 |
| 1997 | 60 | 2473.7 |
| 1998 | 86 | 2706.8 |
| 1999 | 86 | 2407.3 |
| 2000 | 108 | 3680.4 |
| 2001 | 84 | 2150.4 |
| 2002 | 67 | 7698.9 |
| 2003 | 47 | 14432.1 |
| 2004 | 7 | 935.4 |
| N/A* | 19 | 203.2 |
| Total | 626 | 39967.7 |
| (*PFI projects completed but not attributed to a particular year, according to government statistics.) | ||
| The table above shows that as the UK PFI market matures, projects have become bigger and have increased the capital value of individual contracts. | ||
| What’s the hold-up? CPA’s report on education and healthcare PFIs | |
| Schools | |
| Target | 650 rebuilt/remodelled schools to be provided in the period 2001-2004 |
| Progress | Target missed: About 430 schools completed (260 PFI). Remaining 220 PFI schools in pipeline |
| CPA’s comments | “The growing number of school projects being delivered through PFI and a sharp rise in related construction activity are evidence that good progress has been made. However, the new-build target for April 2004 has been missed, although the remaining projects are under way.” |
| Health | |
| Target | 100 new hospitals by 2010 |
| Progress | 33 started before 2001. Improved performance during last year. LIFT schemes started in 2001/04 to 31 against target of 46. Major schemes especially vulnerable to delay. Average nine starts per year required over next four years to secure target |
| Target | 20 treatment centres to be developed by 2004 |
| Progress | Target exceeded: 26 NHS treatment centres open |
| Target | 500 primary care centres by December 2004 |
| Progress | Target at risk: Only 285 primary care centres created by June 2004 |
| Target | 3000 GP surgeries to be modernised by December 2004 |
| Progress | Target at risk: Only 2200 modernised by June 2004 |
| CPA’s comments | “The protracted delays to many of the larger, major hospital schemes are of particular concern.” |