| Elemental cost breakdown, Scottish Gas HQ | ||||
| Office building, including fit-out, of 10,568 m2 gross internal floor area, comprising four storeys and basement | ||||
| ELEMENT | Total cost £ | Cost £/m2 gifa | % split | |
| SUBSTRUCTURE | 489,000 | 46.03 | 2.39 | rotary and continuous flight auger piles; ground beams; retaining wall; reinforced concrete basement slab |
| SUPERSTRUCTURE | ||||
| Frame and upper floors | 2,598,000 | 244.54 | 12.67 | fully exposed insitu reinforced concrete frame; enhanced finish; coffered floor slabs |
| Roof | 376,500 | 35.44 | 1.84 | insitu reinforced concrete slab; Sarnafil roof covering; soffit to external |
| Stairs | 341,700 | 32.16 | 1.67 | precast concrete stair cores; feature atrium staircase |
| External walls | 2,089,900 | 196.71 | 10.19 | aluminium curtain walling; horizontal sun-screens |
| Windows and external doors | 73,600 | 6.93 | 0.36 | revolving main entrance door; pass doors; emergency exit doors |
| Internal walls and partitions | 971,700 | 91.46 | 4.74 | core fit-out including cubicles; tenant system partitions; smoke curtains |
| Internal doors | 291,900 | 27.48 | 1.42 | timber laminate doors to cores; steel doors to plant areas |
| FINISHES | ||||
| Wall finishes | 89,400 | 8.41 | 0.44 | emulsion paint; tiled splashbacks |
| Floor finishes | 727,500 | 68.48 | 3.55 | raised access floors; fixing of diffusers, carpet tiles; granite to reception |
| Ceiling finishes | 77,400 | 7.29 | 0.38 | ceiling finishes to the core areas |
| Fittings and furnishings | 367,200 | 34.56 | 1.79 | blinds; signage; integrated furniture; mobile racking; kiosk |
| SERVICES | ||||
| Sanitary appliances | 144,400 | 13.59 | 0.70 | |
| Special equipment | 454,000 | 42.73 | 2.21 | kitchen equipment |
| Disposal installations | 94,500 | 8.89 | 0.46 | syphonic drainage and waste services |
| Water installations | 108,100 | 10.18 | 0.53 | for toilet cores, vending, shower facilities and kitchen areas |
| Heat source | – | 0.00 | 0.00 | bought as part of package plant room |
| Space heating and ventilation systems | 2,131,000 | 200.58 | 10.40 | displacement ventilation through plenum floor; electric trench heating to glazed areas; ventilating systems passive chilled beams; fan coil units to restaurant areas; stand-alone cooling to communications rooms |
| Electrical installations | 2,168,000 | 204.07 | 10.58 | HV/LV substation; landlord’s and small power to desks; lighting; emergency lighting; generator back-up; uninterrupted power supply; sound insulation to generator room |
| Gas installations | 14,800 | 1.39 | 0.07 | |
| Lift and conveyor installations | 340,800 | 32.08 | 1.66 | three passenger lifts; one goods lift |
| Protective installations | 72,900 | 6.86 | 0.36 | lightning protection; earthing |
| Communications installations | 788,300 | 74.20 | 3.85 | fire alarm and voice evacuation; structured cabling; security; data cabling to desks |
| Special installations | 461,800 | 43.47 | 2.25 | building management system |
| EXTERNAL WORKS | ||||
| Site works | 587,000 | 55.25 | 2.86 | external car park; extensive soft landscaping; granite plaza area; benches |
| Drainage | 150,600 | 14.18 | 0.73 | below ground floor slab and site area |
| External services | 131,300 | 12.36 | 0.64 | |
| Minor building works | 3,800 | 0.36 | 0.02 | |
| Trade contractor preliminaries | 1,930,900 | 181.75 | 9.42 | allowances extracted from trade contractor packages |
| CM staff, organisation and fees | 2,423,300 | 228.10 | 11.82 | |
| TOTAL | 20,499,300 | 1929.53 | 100.00 | |
| Notes Figures shown cover whole project costs including shell-and-core works, landlord’s category A fit-out, tenant’s category A enhancements and tenant’s category B fit-out and external works. Cost breakdown calculated by converting final accounts, or anticipated final accounts, of trade packages into elemental form. | ||||
| Trade packages were tendered between February 2002 and March 2003 | ||||