| Reid’s breakdown of the Holyrood budget (£m) | |
| Building | |
| Site, demolition and archaeology | 5.7 |
| Fit-out | 19.5 |
| Current construction commitment | 212.9 |
| Fees (capped lump sum) | 50.3 |
| Site organisation costs | 17.5 |
| VAT on current commitment | 37.3 |
| Construction reserve | 32.4 |
| Estimated VAT on reserve | 5.7 |
| BUILDING TOTAL | 381.3 |
| Landscaping | 15.2 |
| SUBTOTAL | 396.5 |
| Programme contingency | 4.6 |
| TOTAL BUDGET | 401.1 |
| Contingency fund items | 2.83 |
| Comprising: | |
| QBH carpentry and joinery | £240,000 |
| Mechanical and plumbing | £53,494 |
| Timber/linoleum flooring | £600,000 |
| Building management system | £178,806 |
| Toilet fit-out | £500,000 |
| QBH ceilings and partitions | £380,000 |
| QBH blast doors | £128,000 |
| Scaffolding | £750,000 |