| Elemental cost analysis for Chipping Norton Leisure Centre (gross floor area 3,050 m2) | |||||
| Main element | Breakdown | £ | £/m2 | % | Specification |
| Substructure | 302,321 | 99.12 | 7.49 | ||
| Superstructure | |||||
| frame | 194,108 | 63.64 | 4.81 | Steel frame, glue-laminated timber column and beam | |
| upper floors | 19,224 | 6.30 | 0.48 | Parallel-strand timber beam, plywood deck | |
| roof | 438,468 | 143.76 | 10.87 | Aluminium standing seam on steel/aluminium/timber deck. Thermally broken glass/ | |
| stairs | 6,248 | 2.05 | 0.15 | Beech joinery | |
| external walls | 307,947 | 100.97 | 7.63 | Outer leaf brickwork/oak cladding. Inner leaf blockwork | |
| windows and external doors | 42,073 | 13.79 | 1.04 | Aluminium, thermally broken glazing units/curtain walling. Sliding door units | |
| internal walls and partitions | 138,424 | 45.38 | 3.43 | Fairfaced/block/brick | |
| internal doors | 81,342 | 26.67 | 2.02 | Timber doorsets | |
| subtotal | 1,227,834 | 402.57 | 30.44 | ||
| Internal finishes | |||||
| wall finishes | 132,666 | 43.50 | 3.29 | Douglas fir lining to pool hall | |
| floor finishes | 171,425 | 56.20 | 4.25 | Battened timber flooring to dry sports spaces/tiling to wet areas. Rubber to public areas | |
| ceiling finishes | 41,435 | 13.59 | 1.03 | Plastered suspended ceilings, acoustic where appropriate. Timber deck to pool hall | |
| subtotal | 345,526 | 113.29 | 8.56 | ||
| Fittings and furnishings | 136,805 | 44.85 | 3.39 | ||
| Services | |||||
| sanitary appliances | 20,484 | 6.72 | 0.51 | ||
| mechanical installation | 442,403 | 145.05 | 10.97 | Cross plate heat exchangers to pool AHU. Localised mech vent to fitness suite | |
| electrical installation | 304,329 | 99.78 | 7.54 | Low-energy luminaires. Thermostatically controlled radiant panels to sports hall | |
| moving floor installation | 70,488 | 23.11 | 1.75 | ||
| filtration installation | 82,337 | 0.86 | 2.04 | Sodium hypochlorite with ultraviolet filtration | |
| builders’ work in connection | 8,102 | 2.66 | 0.20 | ||
| subtotal | 928,143 | 304.31 | 23.01 | ||
| Building | 2,940,629 | 964.14 | 72.89 | ||
| External works | |||||
| Site works | 472,674 | 154.98 | 11.72 | Access road, carpark, four-court multi use games area, entrance court, soft landscaping | |
| Drainage | 144,640 | 47.42 | 3.59 | ||
| External services | 90,022 | 29.52 | 2.23 | ||
| subtotal | 707,336 | 231.91 | 17.53 | ||
| Preliminaries | 386,285 | 126.65 | 9.58 | ||
| Total project cost | 4,034,250 | 1,322.70 | 100 | ||
| Contingencies | 125,250 | ||||