| Table 1: Changes to patterns of working | |
| Conventional | New |
| Routine, individual tasks | Creative, Group Tasks |
| Isolated activity | Interactive activity |
| Owned Space | shared space as needed |
| Low space use | high space use |
| Single work setting | Multiple, varied work settings |
| Table 2: Indicative Fit-out costs | |||
| Business Sector | Fit-out £/m2* | Cellularisation Factor** (%) | Average Space use (m2/person) |
| Legal (London) | 600-800 | 40-50 | 16 |
| Legal (regional city) | 400-500 | 35-50 | 16 |
| Banks (London) | 800-1150 | Oct-30 | 16 |
| Accountancy (London) | 400-600 | Oct-30 | 9 |
| Media (London) | 350-600 | Oct-30 | 19 |
| Corporate (London) | 500-1000+ | 15-25 | 18 |
| Corporate (out of town) | 400-1000+ | 15-25 | 11 |
| Computer (out of town) | 450-650 | Oct-30 | 19 |
| *Costs for net internal area based on fit-out from developer's finish at November 1997 price levels. Costs exclude furniture, IT equipment, professional fees, relocation costs and VAT but include preliminaries associated with a lump-sum contract | |||
| **The cellularisation factor is the ratio of occupied cellular space to net internal floor space and is expressed as a percentage. | |||
| Table 3: Indicative rates for fit-out of general office space from shell and core | ||
| Open Plan (£/m2) | Part cellular (£/m2) | |
| Commercial space, out of town location | 350-400 | 450-550 |
| Corporate space, city/west end of London | 450-500 | 600-800 |
| costs are for net internal area at November 1997 price levels and include preliminaries for a lumpsum contract but exclude furniture, IT wiring and equipment, professional fees, relocation costs and VAT. | ||
| Table 4: Indicative rates for fit-out of specialist areas from shell and core for corporate sector offices in the city/west end of London | |
| £/m2 | |
| Reception Area | 1650 - 2150 |
| Senior Executive Offices | 1100 - 1400 |
| Meeting Areas | 550 - 800 |
| Conference Suites | 1200 - 1400 |
| Computer Suites | 850 - 1500 |
| Back-of-house / storage | 450 - 500 |
| Restaurant | 1500 - 220 |
| kitchen | 1800 - 2300 |
| Gymnasium / fitness centre | 800 - 1000 |
| Table 5: Indicative rates for fit-out of specialist areas from shell and core for commercial sector offices in the South-east | |
| £/m2 | |
| Reception area | 850 - 1100 |
| Computer suite | 700 - 1000 |
| Back-of-house / storage | 250 - 400 |
| Restaurant / kitchen | 1300 - 1700 |
| Table 6: Cost and Programme comparisons for different types of contract | ||||||
| Project Type | Traditional / Sequential time (weeks) | Cost (£/m2) | Fast time (weeks) | Cost (£/m2) | Accelerated time (weeks) | Cost (£/m2) |
| City of London, 15,800 m2 Professional/cellular (lawyer) | Overall-61 Construction - 40 | 650-750 | Overall - 52 | 650 - 750 | overall - 42 | 800 - 1000 |
| Construction - 32 | ||||||
| City of London, 15 800 m2 commercial / open plan (bank) | Overall - 60 | 850 - 1050 | overall - 48 | 850 - 1050 | overall - 38 | 1000 - 1400 |
| Construction 36 | Construction - 36 | Construction - 28 | ||||
| Regional city, 4600 m2 Professional / cellular (lawyer) | overall - 34 | 430 - 450 | Overall - 30 | 430 - 540 | Overall - 25 | 540 - 650 |
| Construction - 20 | Construction 20 | Construction - 16 | ||||
| Out-of-town, 7900 m2 Commercial / open plan (Computer) | Overall - 40 | 380 - 540 | Overall - 30 | 380 - 540 | Overall - 26 | 480 - 650 |
| Construction - 22 | Construction - 22 | Construction - 18 | ||||
| Table 7: Preliminaries and fees for alternative procurement routes. | |
| Procurement Route | Preliminaries and contractor‘s fees (%) |
| Sequential, fixed lump sum | 7 - 10 |
| Two stage, fixed lump sum | 7 - 10 |
| Negotiated , fixed lump sum | 7 - 10 |
| Management Contracting | 8 - 12 |
| Construction Management | 8 - 14 |
| Cost Model | ||
| Item | Unit | Price Range £ |
| Demountable partitions | ||
| Frame with plasterboard | m2 | 50 - 60 |
| Frame and hung panel system | m2 | 55 - 60 |
| Extra for part-glazed panel | m2 | 40 - 60 |
| Fully demountable monobloc | ||
| Solid wall | m2 | 55 - 100 |
| Storage wall | m2 | 180 - 200 |
| - laminate faced chipboard | m2 | 180 - 200 |
| - stove-enamelled mild steel | m2 | 300 - 350 |
| Single-glazed office front | m2 | 65 - 100 |
| Ditto but with etched glass | m2 | 150 + |
| Double-glazed office front, interstitial blinds | m2 | 140 - 180 |
| Ditto but with etched glass | m2 | 250 + |
| Metal stud partitions | ||
| One layer plasterboard both sides | m2 | 25 - 35 |
| Two layers plasterboard both sides, insulated | m2 | 35 - 48 |
| Ditto but with one-hour fire resistance | m2 | 43 - 55 |
| Extra for curved work | m2 | 20 |
| Glazed partitions | ||
| Frameless glazing | m2 | 180 - 200 |
| Framed double-glazed partition | m2 | 175 - 195 |
| Glass block screen | m2 | 250 - 450 |
| Fire-resisting security partition including allowance for doors, etc: | ||
| - 30/30 minutes' flare insulation/integrity rating | m2 | up to 500 |
| - 60/60 minutes' fire insulation/integrity rating | m2 | up to 850 |
| - 120/120 minutes' fire insulation/integrity rating | m2 | up to 1350 |
| Internal doors | ||
| Non-fire rated doors | ||
| - ply faced | each | 50 - 85 |
| - hardwood veneer | each | 85 - 125 |
| - laminate-faced | each | 190 - 260 |
| 30-minute fire-rated doors | ||
| - ply faced | each | 80 - 110 |
| - hardwood veneer | each | 100 - 200 |
| - laminate faced | each | 190 - 260 |
| - matched hardwood veneer | each | 300 - 420 |
| 60-minute fire-rated doors | ||
| - ply faced | each | 100 - 160 |
| - hardwood veneer | each | 150 - 210 |
| - laminate-faced | each | 200 - 315 |
| Adjustment factor for full-height doors | each | 19.75 |
| Adjustment factor for overpanels | each | 19.75 |
| Extra for non-fire-rated vision panel | each | 80 - 100 |
| Extra for 30-minute firerated vision panel | each | 100 - 150 |
| Non fire-rated doorsets | ||
| - softwood | each | 30 - 45 |
| - hardwood | each | 100 - 160 |
| 60-minute fire-rated doorsets | ||
| - softwood | each | 85 - 100 |
| - hardwood | each | 140 - 200 |
| Allowance for ironmongery | ||
| - satin anodised aluminum | each | 150 - 300 |
| -stainless steel | each | 300 - 500 |
| Wall Finishes | ||
| Panelling | ||
| -Timber | m2 | 235-285 |
| -Fabric-Covered framed panelling | m2 | 190+ |
| -acoustic panelling | m2 | 280+ |
| Plasterboard | ||
| -drylining and emulsion | m2 | Dec-15 |
| -drylining on metal fittings and emulsion | m2 | 15 - 20 |
| Stonework | ||
| -limestone cladding | m2 | 250 - 370 |
| -granite cladding | m2 | 250 - 420 |
| -marble cladding | m2 | 160 - 200 |
| Tiling | ||
| -ceramic titling to public areas | m2 | 40 - 60 |
| -ditto but for kitchen/washroom areas | m2 | 35 - 45 |
| -extra for render backing | m2 | 08-Oct |
| Hygenic finishes | ||
| -laminate panel | m2 | 55 - 65 |
| -antibacterial paint finish | m2 | 20 - 25 |
| Applied finishes | ||
| -plaster and emulsion | m2 | Nov-16 |
| -polished plaster | m2 | 75 - 110 |
| -vinyl wall covering | m2 | Jul-16 |
| -high-quality vinyl covering | m2 | 15 - 25 |
| -fabric wall covering | m2 | 15 - 35 |
| -special paint finishes | m2 | 08-Oct |
| Floor Finishes | ||
| Timber | ||
| -maple/beech sprung strip flooring | m2 | 60 - 100 |
| -marquetry flooring | m2 | 250+ |
| Raised floors | ||
| -MOB light duty. 100-300 mm cavity | m2 | 26 - 33 |
| -MOB medium duty, 150 mm cavity | m2 | 26 - 35 |
| -ditto but with bonded vinyl sheet | m2 | 40 - 50 |
| -MOB medium duty, 300 mm cavity sheet | m2 | 30 - 40 |
| -ditto but with bonded vinyl sheet | m2 | 45 - 54 |
| -MOB heavy duty, 100-300 mm cavity | m2 | 38 - 55 |
| -ditto but with bonded vinyl sheet | m2 | 53 - 70 |
| Allowance for bridging obstructions to single pedestal | each | Dec-20 |
| Taking up and storing tiles | m2 | allow 10 |
| Protection to floor tiles | m2 | allow 2 |
| Cavity barriers | ||
| -30-minute fire resistance, 100-200 mm cavity | m | 08-Sep |
| -ditto but 60-minute fire resistance | m | 10-Nov |
| -30 minute fire resistance, 300-400 mm cavity | m | 13 - 16 |
| Hard surface finishes | ||
| -ceramic tiles | m2 | 35 - 53 |
| -matt porcelain tiles | m2 | 55 - 85 |
| -non-slip mosaic tiles | m2 | 48 - 60 |
| -natural slate tiles | m2 | 60 - 80 |
| -20mm polished granite | m2 | 200 - 250 |
| -20mm polished travertine marble | m2 | 125 - 140 |
| -insitu terrazzo | m2 | 120 - 140 |
| -terrazzo tiles | m2 | 35 - 45 |
| Extra for floor levelling | m2 | 03-Apr |
| Extra for 65 - 70 mm sand:cement screed, float finish | m2 | Oct-14 |
| Extra for making up with concrete, up to 300mm | m2 | 20 - 35 |
| Extra for plywood underlay | m2 | 08-Oct |
| Sheet and tile finishes | ||
| -linoleum tiles | m2 | 15 - 18 |
| -sheet / tile vinyl, standard duty | m2 | 14 - 24 |
| -ditto but heavy duty | m2 | 16 - 26 |
| -antistatic vinyl tiles | m2 | 15 - 20 |
| -sheet/tile vinyl safety flooring | m2 | 25 - 35 |
| Carpet tiles | ||
| -heavy duty for office areas | m2 | 18-30 |
| -heavy duty antistatic | m2 | 34-40 |
| Carpet | ||
| -cut-and-loop pile, 80% wool, 20% nylon, medium duty | m2 | 16 - 19 |
| -ditto but heavy duty | m2 | 36 - 40 |
| -broadloom | m2 | 55 - 75 |
| -handwoven | m2 | 100+ |
| -extra for underlay | m2 | 03-Apr |
| Ceiling Finishes | ||
| Jointless plasterboard | ||
| -one layer on metal fixing | m2 | 18 - 28 |
| -two layers on metal fixing | m2 | 21 - 30 |
| -plasterboard feature suspended ceiling | m2 | 95+ |
| -fibrous plaster feature suspended ceiling | m2 | 95 - 140 |
| Fibre tiles | ||
| -mineral fibre, plain, exposed grid | m2 | 14 - 18 |
| -mineral fibre, acoustic, exposed grid | m2 | 18 - 22 |
| -high-density mineral fibre, exposed anti-corrosive grid | m2 | 32 - 35 |
| -glass-reinforced gypsum, plain semi-concealed grid | m2 | 31 - 42 |
| -resin-bonded glasswool, plain. semi-concealed grid | m2 | 28 - 32 |
| -compressed rockwool, acoustic, concealed grid | m2 | 22 - 25 |
| Metal tiles | ||
| -non-perforated tiles, suspended ceiling | m2 | 25 - 35 |
| -ditto but moisture resistant | m2 | 35 - 50 |
| -perforated tiles, demountable concealed grid | m2 | 35 - 50 |
| -ditto but linear grid | m2 | 38 - 50 |
| perforated tiles, hinged, concealed grid | m2 | 35 - 50 |
| -perforated tiles lay-in grid | m2 | 30 - 45 |
| -perforated accoustic quality mega-panel tile | ||
| -hinge access, tartan grid | m2 | 55 - 75 |
| Taking down and storing files | m2 | 08-Oct |
| Building Services | ||
| Mechanical Installations | ||
| Extension of air-conditioning and heating system into general office areas | ||
| -variable air-volume | m2 | 90 -110 |
| -four-pipe fan-coil units | m2 | 80 -130 |
| -underfloor displacement ventilation | m2 | 25 - 50 |
| -Hiross underfloor air-conditioning system | m2 | 100 - 120 |
| -extra over for suspended ceiling for chilled ceiling including water distribution | m2 | 100 - 150 |
| -extra over for installing floor diffusers | m2 | 14 - 16 |
| -low-pressure hot water permimeter heating | m2 | 15 - 20 |
| Extension of controls and building management systems | m2 | Aug-16 |
| Electrical installations | ||
| Extension of small power distribution circuits into general office areas | ||
| -general | m2 | 09-Dec |
| -trunking, cables and sockets | m2 | 02-Apr |
| -busbar and sockets | m2 | 2.50 - 3.50 |
| -floor outlet boxes | m2 | 04-May |
| Extension of lighting circuits in general office extras | ||
| (LG3 Category 2 luminaires to 500 lux) | ||
| -general | m2 | 32 - 40 |
| -wiring | m2 | Oct-15 |
| -luminaires | m2 | 20 - 27 |
| Extension of lighting controls into office areas | m2 | 04-May |
| Supplies to HVAC equipment in office areas | m2 | 0.50 - 1.50 |
| Protective Installations | ||
| Extension of sprinkler systems into office areas | m2 | Oct-19 |
| fully addressable fire alarm system | m2 | 05-Oct |
| IT/Data cabling distribution, cabinets and patch panels | m2 | 1.50 - 7.50 |
| Regional Variations | |
| All costs are based on schemes located in the outer London area. For projects in other regions, costs should be adjusted bt he factors shown below. | |
| Inner London | 1.04 |
| South-east | 0.97 |
| South-west | 0.94 |
| East-midlands | 0.91 |
| West-midlands | 0.92 |
| East anglia | 0.94 |
| Yorkshire and Humberside | 0.91 |
| North-west | 0.95 |
| North | 0.91 |
| Scotland | 0.93 |
| Wales | 0.92 |
| Northern Ireland | 0.86 |