| Table 1: Comparison of specification standards for 1960-1970s and 1990s office buildings | ||
| 1990 | 1960s-1970s | |
| Floor loadings | 5 kN/m2 + 1 kN/m2 | 3 kN/m2 |
| Floor-to-floor heights | 3.6 - 4.1m | 2.8 - 3.6 m |
| Floor-plate size | 1000-2000m2 | 700-1200m2 |
| Floor-plate width | 15 - 18m | 10 - 14m |
| Table 2: Guide rates | |
| Refurbishment options | £/m2 gross floor area |
| Cosmetic refurbishment | 270 - 380 |
| Refurbishment of services and internal finishes | 490 - 700 |
| Extensive refurbishment including alterations to structure and cladding | 810 - 1050 |
| Table 3: Sensitivity analysis of development yield for three rental incomes | |||
| scenario 1 | scenario 2 | scenario 3 | |
| 5100 m2 space at | £130/m2 | £160/m2 | £195/m2 |
| Anticipated rental income (5100 m2 x rent) | £663,000 | £816,000 | £995,000 |
| Time to purchase at 7% yield per year (100÷7) | 14.3 years | 14.3 years | 14.3 years |
| Gross development value (income x years to purchase) | £9,481,000 | £11,669,000 | £14,229,000 |
| Residual profit/loss (gross development value less total development cost of £11,500,000, see table below) | -£2,019,000 | £169,000 | £2,729,000 |
| Actual development yield (anticipated income ÷ development costs) | 5.77% | 7.10% | 8.65% |
| Table 4: Feasibility appraisal for estimated development costs | ||
| £ | total £ | |
| Construction costs | ||
| Demolition | 150,000 | |
| Refurbishment - 6250 m2 @£815/m2 | 5,100,000 | |
| External works | 50,000 | |
| Planning, building regulations fees, survey work, say 1% of construction cost | 50,000 | |
| Professional fees @ 12% | 640,000 | |
| Finance costs @ 9% a year based on 50% of construction period | 415,000 | 6,405,000 |
| Site/existing building purchase | ||
| 5500 m2 building @ £540/m2 | 2,970,000 | |
| Acquisition costs and fees @ 2% | 60,000 | |
| Finance costs @ 9% a year | 420,000 | 3,450,000 |
| Marketing and letting fees | 100,000 | |
| Development profit @ 12% | 1,095,000 | |
| Void period | ||
| Finance costs of 9% a year for six months loss of rent | 450,000 | |
| Total development cost | 11,500,000 | |
| Cost breakdown | |||
| Element cost (£) | Cost/m2 gfa (£) | % of total cost | |
| Demolitions and alterations | 142 535 | 22.81 | 2.69 |
| Note: all stripping out and pulling down includes taking away debris and making good to any remaining surfaces | |||
| Stripping out existing radiator heating services and boilers etc | 5500 m2 @ | £1.50 | |
| Stripping out water and waste services | 5500 m2 @ | £1 | |
| Stripping out electrical services | 5500 m2 @ | £1 | |
| Removing floor finishes and hacking off existing screeds | 5200 m2 @ | £7 | |
| Hacking off existing wall plaster | 1900 m2 @ | £3 | |
| Taking down suspended ceiling | 5200 m2 @ | £1.80 | |
| Removing finishes and fittings to toilet areas | 140 m2 @ | £5 | |
| Removing finishes to stairwell treads and risers | 130 m2 @ | £2.50 | |
| Removing staircase balustrades | 150 m @ | £8 | |
| Pulling down block spandrel walls, partition walls and doors | 1000 m2 @ | £4 | |
| Pulling down timber and demountable partitions and doors | 1200 m2 @ | £2.50 | |
| Removing doors from openings in partitions | 50 nr @ | £10 | |
| Removing precast concrete external cladding panels | 1700 m2 @ | £6 | |
| Removing galvanised mild steel single-glazed windows | 1100 m2 @ | £3 | |
| Removing 300 x 400 mm reinforced concrete upstands | 900 m @ | £12 | |
| Removing asphalt roof coverings and screeds | 1100 m2 @ | £6 | |
| Taking down four-storey steel escape staircase including breaking out foundations | 1 @ | £1,000 | |
| Filling to door opening, one brick thick about 1.5 x 2.1 m through 225 mm reinforced concrete wall | 5 @ | £150 | |
| Cutting to enlarge opening through half-brick internal wall; new opening 1100 x 2100 mm; existing opening 800 x 2100 mm; forming jambs square; new precast lintel, drypack to existing lintel | 10 @ | £100 | |
| Cutting out defective reinforced concrete; blast-clean reinforcement and repalce with repair mortar in areas not exceeding 2 m2 | 25 m2 @ | £30 | |
| Include for taking down external signage | allow | £500 | |
| Cutting to form opening 1.485 x 2.1 m through 150 mm reinforced concrete wall including 15 Ronafix modified mortar to jambs and head | 2 @ | £300 | |
| Cutting to form openings 1.20 x 1.80 through 150 mm rinforced concrete wall including 15 Ronafix modified mortar to jambs and head | 40 @ | £250 | |
| Breaking out to form opening 8 x 6 through 300 mm reinforced concrete floor oever entrance foyer including additional framing steelwork | 48 m2 @ | £100 | |
| Filling in existing duct openings 2 x 5 m in 300 mm reinforced floors including new concrete, formwork to soffit, 10 mm reinforcement and scabbling edges of existing floor | 10 @ | £160 | |
| Diamond saw cutting new openings 2 x .5 m in 300 mm reinforced concrete floor including 15 Ronafix modified mortar to edges | 10 @ | £670 | |
| Breaking out to form four openings 5 x 2.5 m through 300 mm reinforced concrete floor slab for new staircase | 50 m2 @ | £70 | |
| Substructure | 12 200 | 1.95 | 0.23 |
| 150 mm reinforced concrete ground slab and thinkcening to extended slab dowelled in along one edge | 130 m2 @ | £80 | |
| 200 x 150 mm deep reinforced concrete upstand kerb | 180 m2 @ | £10 | |
| Frame | 142 700 | 22.83 | 2.69 |
| Structural steel cantilever extension 700 mm long, one end bolted to frame and perimeter edge beam (1200 m @ 70 kg/m); measure per m2 extended floor area | 625 m2 @ | £160 | |
| Structural steel strengthening to one bay for new plant room over | 2 t @ | £1,500 | |
| Structural steel frame to lightweight plant room enclosure at roof level including plant support steelwork | 4 t @ | £1,000 | |
| Bracing to new stairshaft | 4 t @ | £1,300 | |
| Trimming to new riser openings | 2 t @ | £1,500 | |
| Fireboard protection to structural steel generally | 1100 m2 @ | £25 | |
| Upper floors | 57 500 | 9.2 | 1.08 |
| 200 mm reinforced concrete extensio nto upper floor slabs including formwork, reinforcement and dowelling to existing structure 500 m2 @ £80.00200 x 300 mm reinforced cocrete perimeter upstands including formwork and reinforcement | 700 m @ | £25 | |
| Roof | 61 500 | 9.84 | 1.16 |
| 150 mm reinforced concrete slab to extended roof area including formwork and reinforcement | 125 m2 @ | £48 | |
| Warm deck insulation, screed and 19 mm asphalt roofing on felt including work to parapets etc | 1200 m2 @ | £30 | |
| Lightweight coated steel cladding to plant room | 125 m2 @ | £60 | |
| Perimeter edge and gutter detail to plant room roof | 40 m @ | £25 | |
| Galvanised balustrading to roof perimeter | 100 m @ | £110 | |
| Stairs | 29 300 | 4.69 | 0.55 |
| Precast concrete dogleg staircase; 3.35m rise | 4 flghts @ | £3,000 | |
| Chromium-plated balustrades to main staircase | 10 m @ | £300 | |
| Chromium-plated handrails to main staircase | 80 m @ | £100 | |
| Painted mild steel balustrade to escape stairs | 20 m @ | £90 | |
| Colour-coated mild steel handrail to escape stairs | 180 m @ | £25 | |
| External walls | 1 147 000 | 183.52 | 21.63 |
| Polyester powder-coated aluminium curtain walling system with double-glazed low-emissivity glass and insulated coated aluminium spandrel panels | 2900 m2 @ | £350 | |
| Colour-coated aluminium over-cladding, Luxalon or equivalent, on metal grid fixed to concrete and walls | 280 m2 @ | £250 | |
| Proprietary independent dry lining as back-up wall to spandrel panels | 2800 m2 @ | £20 | |
| Lightweight colour-coated steel wall cladding, Luxalon or equivalent to new plant room | 100 m2 @ | £60 | |
| Windows and external doors | 91 700 | 14.67 | 1.73 |
| Polyester powder-coated aluminium double-glazed modular windows | 90 m2 @ | £320 | |
| Polyester powder-coated aluminium double-glazed modular fire escape door 1.5 x 2.1 m including frames and furniture | 2 @ | £1,500 | |
| Feature entrance screen, doors and canopy in structural glazing | 75 m2 @ | £500 | |
| Aluminium louvres to roof plant room | 40 m2 @ | £560 | |
| Internal walls | 38 000 | 6.08 | 0.72 |
| Note: Additional partitioning to tenants' floor areas excluded | |||
| Shaft wall system to form new service risers | 220 m2 @ | £30 | |
| 150mm blockwork in partitions to new staircase tower and cores | 210 m2 @ | £15 | |
| 100mm blockwork as compartment walls generally | 280 m2 @ | £10 | |
| One-hour fire-resisting 70mm Gyproc metal stud partition 3-3.3 m high with 12.5 mm fireboard each side | 120 m2 @ | £35 | |
| WC cubicles including doors | 35 @ | £350 | |
| WC backwall duct sets; 2200mm high; IPS or similar | 90 m @ | £100 | |
| Internal doors | 50 350 | 8.06 | 0.95 |
| Veneered flush doors | 10 @ | £300 | |
| Laminate-faced solid flush single doors to toilet etc | 25 @ | £550 | |
| Laminate-faced solid half-hour fire-resisting double doors with vision panels to stairwells and lobbies | 15 @ | £1,250 | |
| Laminate-faced solid one-hour fire-resisting double doors with vision panels to stairwells and lobbies | 11 @ | £1,350 | |
| Wall finishes | 72 860 | 11.66 | 1.37 |
| Two layers 12.5mm wallboard and skim coat to existing concrete columns | 480 m2 @ | £12 | |
| 13mm plaster and paint to walls | 2400 m2 @ | £7.50 | |
| Tassoglass paper to walls and columns | 5700 m2 @ | £7 | |
| Ceramic wall tiling on plaster to toilet walls etc | 230 m2 @ | £40 | |
| Floor finishes | 365 400 | 58.46 | 6.89 |
| 150mm raised-access floor to office areas including carpet tiles | 5100 m2 @ | £50 | |
| Cavity barriers | 800 m2 | £10 | |
| Carpet on concrete make-up to common areas | 400 m2 @ | £25 | |
| Lightweight concrete make-up to lobby areas | 900 m2 @ | £25 | |
| Vinyl sheeting to treads and rises of staircases including screeds, nosings and skirtings | 190 m2 @ | £50 | |
| Ceramic non-slip tiles on screed to WCs, cleaners' cupboards, kitchenettes | 235 m2 @ | £60 | |
| Granite feature flooring to entrance foyer on screed | 50 m2 @ | £140 | |
| Entrance mat and frame | Item @ | £1,000 | |
| Hardwood skirtings to common and office areas | 1600 m @ | £8 | |
| Dustproof sealer to raised floor plenum | 5100 m2 @ | £5 | |
| Ceiling finishes | 46 960 | 7.51 | 0.89 |
| Plasterboard dry lining to underside of suspended slabs | 4300 m2 @ | £7 | |
| (Trox chilled ceiling panelled system, 5100 m2, included in heat source space heating and ventilation) | |||
| M/F suspended ceiling to common areas | 570 m2 @ | £18 | |
| Feature suspended ceiling to entrance foyer | 48 m2 @ | £100 | |
| Emulsion paint to soffits of stairs and landings | 360 m2 @ | £5 | |
| Fittings and furnishings | 35 000 | 5.6 | 0.66 |
| Allow sum for kitchenette etc | £5,000 | ||
| Internal vertical louvre blinds | 1000 m2 @ | £30 | |
| Sanitary installation | 20 000 | 3.2 | 0.38 |
| 35 white glazed WCs; 5 disabled WCs and fittings; 15 urinals; 35 wash hand-basins in purpose-made vanitory units; 5 cleaners' sinks and 5 stainless steel sinks | |||
| Disposal installation | 30 000 | 4.8 | 0.57 |
| Rainwater, waste and soil disposal in PVCu | |||
| Water installation | 41 000 | 6.56 | 0.77 |
| Mains supply, hot and cold water in copper | |||
| Heating and ventilation | 1 112 150 | 177.94 | 20.97 |
| Displacement ventilation to office areas | 5150 m2 @ | £28 | |
| Chilled ceiling installation to office areas including suspended ceiling complete | 5150 m2 @ | £160 | |
| Perimeter heating to office areas | 5150 m2 @ | £22 | |
| Pressurisation to cores and staircases | 590 m2 @ | £40 | |
| Extract ventilation to toilets and kitchenettes | 235 m2 @ | £30 | |
| Electrical installations | 498 500 | 79.76 | 9.4 |
| Complete installtion, including recessed light fittings in chilled ceilings; no standby generation | 100 m2 @ | £85 | |
| Common areas and plant rooms | 1000 m2 @ | £65 | |
| Lift and conveyor installation | 50 000 | 8 | 0.94 |
| Overhaul of 2 eight-person passenger lifts serving five floors including respraying doors | 2 @ | £20 000 | |
| Internal refurbishment of lift cars | 2 @ | £5,000 | |
| Protective installations | 62 500 | 10 | 1.18 |
| Addressable fire alarm and security system | 6250 m2 @ | £10 | |
| Communication installations | 129 250 | 20.68 | 2.44 |
| Centralised building management system for zoned displacement ventilation system | 6250 m2 @ | £15 | |
| Data and telephone wiring provision in dado trunking | 5100 m @ | £5 | |
| Public address installation; clocks | Item @ | £10 000 | |
| Builders' work in connection | 146 000 | 23.36 | 2.75 |
| Associated builders' work in connection with services | allow 7.5% | ||
| Example spot items (provisional quantities) | |||
| Concrete filling to hole 100 x 100 mm in 150 mm reinforced concrete | allow 10 @ | £25 | |
| Concrete filling to hole 1000 x 600 mm in 150 mm reinforced concrete | allow 3 @ | £50 | |
| Scabbling surface of existing concrete | allow 250 m2 @ | £2 | |
| Reinforced concrete in machine bases and plinths including reinforcement and formwork | 5 m3 @ | £200 | |
| Cutting chases for conduit 25 x 25 mm; in concrete | allow 100 m @ | £7.50 | |
| Cutting chases for conduit 25 x 25 mm; in brickwork/blockwork | allow 100 m @ | £2 | |
| Diamond saw cutting rebates in reinforced concrete 25 mm wide x 100 mm deep | allow 40 m @ | £60 | |
| Diamond saw cutting holes not exceeding 55 mm diameter in slabs 100-200 mm deep | allow 20 @ | £12 | |
| Ditto 200-300 mm deep | allow 20 @ | £18 | |
| Diamond saw cutting holes 100 mm diameter in slabs 100-200 mm deep | allow 20 @ | £15 | |
| Ditto 200-300 mm deep | allow 20 @ | £20 | |
| Diamond saw cutting holes 200 mm diameter in slabs 100-200 mm deep | allow 20 @ | £25 | |
| Ditto 200-300 mm deep | allow 20 @ | £40 | |
| Diamond saw cutting holes 200 mm diameter in brickwork/blockwork 100-150 mm thick | 50 @ | £18 | |
| Cutting away and making good for lighting, socket outlet and fittng outlet points | allow 100 @ | £5 | |
| Subtotal | 4 382 405 | 701.18 | 82.64 |
| Preliminaries | 438 295 | 70.13 | 8.26 |
| Contractor's management and staff, site accommodation and other preliminary items | |||
| Contingencies and design reserve | 482 300 | 77.17 | 9.1 |
| Total for scheme | 5 303 000 | 848.48 | 100 |
| (excluding site works) | |||
| Cost/m2 gfa (£) | |||
| Other items | |||
| Demolitions and alterations | |||
| External scaffolding - allow 2800 m2 @ £12 | 6.5 | ||
| Stripping out existing air-conditioning systems etc - 5200 m2 @ £2 | 1.66 | ||
| Removing asbestos cladding board as duct casings etc - typical rate £20/m2 | n/a | ||
| Removing asbestos lagging to pipes; including cleaning pipes - typical rate £40/m | n/a | ||
| Removing sprayed asbestos to structural beams; including cleaning steelwork - typical rate £70/m2 | n/a | ||
| Raking shoring to adjoining building - typical rate £5/m2 | n/a | ||
| Cleaning of external stone facade - typical rate £8/m2 | n/a | ||
| Cleaning of stained brickwork - typical rate £5/m2 | n/a | ||
| Cleaning of curtain walling or windows - typical rate £5/m2 | n/a | ||
| Repair/refurbishment of curtain walling - typical rate £60/m2 | n/a | ||
| Funigcidal treatment of stonework - typical rate £5/m2 | n/a | ||
| Repair and redecoration or external windows - typical rate £20/m2 | n/a | ||
| Upper floors | |||
| Localised strenghtening of 7.6 x 5.25 m bay with additional fire-protected steel beams bolted with friction anchors to existing concrete frame - 40 m2 @ £65 | 0.5 | ||
| Stairs | |||
| Foundations to new attached staircase block 4.6 x 2.5 x 17.5 m high, curtain walling to three sides, roof over and with 4 staircase dogleg flights and finishes as other escape staircases, complete - 1 @ £100,000 | 10 | ||
| [The construction of the staircase outside the building footprint will increase lettable area by 45 m2 (0.8%)] | |||
| External walls and windows | |||
| Coated steel Luxalon cladding on metal support rails including 140 mm concrete block back-up wall (2000 m2 @ £80) plus polyester-coated aluminium double-glazed windows (1300 m2 @ £350) | -90 | ||
| Coated steel Luxalon cladding on metal support rails including 140 mm concrete block back-up wall (2000 m2 @ £80) plus polyester-coated aluminium double-glazed windows with interstitial blinds (1300 m2 @ £500) | 57 | ||
| Heat source, space heating and ventilation | |||
| Radiator heating system with localised extract - 5150 m2 @ £60 | -168 | ||
| Fan-coil unit comfort cooling system - 5150 m2 @ £180 | |||
| Communications installations | |||
| Central building management services system for fan-coil unit comfort cooling system - 6250 m2 @ £20 | 6 | ||
| Protective installations | |||
| Single-level sprinklers with heads at 9 m2 - 6250 m2 @ £10 | 12 | ||
| Regional Variations | |
| All costs in this model are based on a scheme in Outer London and should be adjusted by the following location factors for schemes in other areas: | |
| Inner London | 1.08 |
| Outer London | 1 |
| East Anglia | 0.85 |
| East Midlands | 0.83 |
| North | 0.86 |
| Northern Ireland | 0.68 |
| North-west | 0.85 |
| Scotland | 0.91 |
| South-east | 0.91 |
| South-west | 0.84 |
| Wales | 0.83 |
| West Midlands | 0.84 |
| Yorkshire and Humberside | 0.85 |