| Typical Design Criteria for Sports Facilities | ||||||
| Facility | Plan m2 | Depth m | Height m | Temperature air (water) | Lighting lux | Notes |
| WET | ||||||
| Leisure Pool | 335 pwa | 0-2 | 9 | 30 (29) | 200-300 | Ratio of pool water area (pwa) to gross floor area (gfa) 1:4.6. Maximum floor gradient 1:15 to depth of 1.7m. 9m high for internal slides |
| Traditional 25m pool | 25 x 13 | 01-Feb | 6 | 28 (27) | 200-300 | Pwa to gfa ratio 1:3.7. Typical density 1 person/2.5m2 (pwa) |
| Learning pool | 10 x 5 | 0.6-0.9 | 4 | 30 (29) | 200-300 | Recommended sizes: 13, 16.7, or 20 x 7.5m |
| DRY | ||||||
| Medium sports hall (1000 - 2000 m2 | 37 x 33 (eight badminton courts) | - | - 7.6 (L) | 14-18 | 300 (L) | Minimum heights and lighting levels vary for leisure (L), club/county (C), and national/international competition (N) standards. Basketball court 26 ± 2 x 14 ± 1m. Large storage area required |
| - | - 9.1 (C) | 20 for | 500 (C) | |||
| - | - 9.1 (N) | social use | 750 (N) | |||
| Ancillary hall (bowls) | 40 x 30 (five greens) | - | 7 | 18-20 | 300 (L) | Greens 36.5 x 4.57 m with roll-down carpets. Hall also used roller skating |
| 500 (C) | ||||||
| 500 (N) | ||||||
| Squash courts | 187 | - | 5.64 | 14-18 | 500-750 | Clubs base use on 100-125 members per court. Each court is 9.75 x 6.4m |
| Health suite (sauna/spa etc) | 29 x 10 | - | 2.7 | 28-30 | 150 | Separate extract system may be required for sunbeds |
| Fitness suite (gymnasium / weights) | 14 x 10 | - | 2.7 | Dec-18 | 500 | Typical weight training area is 15 x 7.5m. Eight to 10 air changes an hour essential |
| Changing / toilet areas | 17 x 12 + 8 x 7 | - | 2.7 | 20-22 (dry) | 150 | Changing facilities based on: court use x 2 for overlapping changing; ancillary halls, 1 per 5-10m2 x 2 for overlap; other activity rooms, 1 per 5m2 x 2 for overlap; traditional pools, 1 per 8m2 pwa; leisure pool, 1 per 6m2 pwa; showers, 1 per 7 changing places; benches, 500mm per changing place; WCs and urinals, 1 per 7 (dry) or 1 per 10 (wet) persons; handbasins, 1 per 15 persons |
| 22-25 (wet) | ||||||
| Net to gross areas for different sports facilities | ||||||||||||
| Facility | Sports area | Surround area | Changing/ toilets | Storage / plant | Circulation / ancillary | Total | ||||||
| m2 | % | m2 | % | m2 | % | m2 | % | m2 | % | m2 | % | |
| Leisure pool | 335 pwa | 21.7 | 445 | 28.8 | 115 | 7.5 | 255 + 100* | 23 | 100 + 195* | 19.1 | 1545 | 100 |
| Traditional 25m pool | 325 pwa | 26.6 | 290 | 23.7 | 86 | 7 | 177 + 100* | 22.6 | 56 + 190* | 20.1 | 1224 | 100 |
| Learning pool | 50 pwa | 30.1 | 77 | 46.4 | 29 | 17.5 | 10 | 6 | - | - | 166 | 100 |
| Sports hall | 654 | 33 | 560 | 28.2 | 200 | 10.1 | 166 + 120* | 14.4 | 20 + 265* | 16.1 | 1710 | 100 |
| Bowls hall | 838 | 49 | 256 | 15 | 76 | 4.5 | 140 + 125* | 15.5 | 150 + 125* | 25.3 | 304 | 100 |
| Squash courts (3 nr) | 187 | 61.5 | 20 (viewing) | 6.6 | - | - | 20 | 6.6 | 53 + 24* | 25.3 | 304 | 100 |
| Health / fitness | 440 | 77.7 | - | - | 24 | 4.2 | 36 | 6.4 | 30 + 36* | 11.7 | 566 | 100 |
| Totals | 2829 | 3737 | 1648 | 22 | 530 | 7.1 | 1249 | 16.7 | 1244 | 16.6 | 7500 | 100 |
| *General administration, plant and reception areas have been allocated to specific facility areas to make the facility cost breakdown table easier to understand by grouping specific facilities together. | ||||||||||||
| pwa = pool water area | ||||||||||||
| Cost model | |||
| element cost (£) | £/m2 gifa | % of total cost | |
| LEISURE POOL 1250m2 | |||
| Substructure | 177 500 | 142 | 9.16 |
| Pad foundations with ground beams and reinforced concrete slab on good ground | 1125 m2 @ | £130 | |
| Sunken plant room | 125 m2 @ | £130 | |
| Frame | 175 000 | 140 | 9.03 |
| Portal steel frame 25m span over pool areas including protection and cladding rails | 1125 m2 @ | £120 | |
| Structural steel support for water slides | allow | £40 000 | |
| Upper floors | 5 500 | 4.4 | 0.8 |
| Aluminium perforated intermediate floor decking in plant room | 50 m2 @ | £110 | |
| High-level spectators' gallery included elsewhere | 500 m2 @ | £5 | |
| Roof | 120 100 | 96.08 | 6.2 |
| Rooflight over pool | 16 m2 @ | £475 | |
| High-performance insulated composite metal roof cladding | 1250 m2 @ | £100 | |
| Stairs | 25 000 | 20 | 1.29 |
| Access stair in pool for water ride starts | 1 nr @ | £20 000 | |
| SUndry plant stairs and ladders, | allow | £5,000 | |
| External walls | 30 000 | 24 | 1.55 |
| Ibstock facing bricks and blockwork cavity wall to 3m including brick and block specials | 200 m2 @ | £70 | |
| High-performance insulated composite metal wall cladding above 3m | 400 m2 @ | £40 | |
| Windows and external doors | 20 000 | 16 | 1.03 |
| Glazed aluminium curtain walling/windows | 38 m2 @ | £275 | |
| Powder-coated aluminium glazed screens and doors | 10 m2 @ | £500 | |
| Metal door sets (2 nr double; 1 nr single) | allow | £4,550 | |
| Internal walls and partitions | 29 800 | 23.84 | 1.54 |
| Block internal walls | 400 m2 @ | £25 | |
| Gyproc jumbo partition | 10 m2 @ | £60 | |
| Powder-coated aluminium single-glazed screens | 6 m2 @ | £200 | |
| Powder-coated aluminium glazed half-hour fire-resistant screens | 45 m2 @ | £400 | |
| Balustrades to galleries included elsewhere | jkl;j | j;j | |
| WC cubicles etc are integrated units included with sanitary fittings | j;j | j;jk | |
| Internal doors | 18 200 | 14.56 | 0.94 |
| Leaderflush door sets with laminated plastic veneered doors and Acrovyn finished linings | 12 nr @ | £650 | |
| Powder-coated aluminium glazed half-hour fire-resistant doors/screens | 20 m2 @ | £520 | |
| Wall finishes | 73 400 | 58.72 | 3.79 |
| Lightweight plaster | 200 m2 @ | £6 | |
| Insulated metal liner sheet | 800 m2 @ | £25 | |
| Waterproof render to pool areas | 300 m2 @ | £20 | |
| Wall render elsewhere | 580 m2 @ | £5 | |
| Emulsion paint | 200 m2 @ | £2 | |
| Portaflek paint to change areas | 180 m2 @ | £5 | |
| Ceramic tiles to straight and curved pool sides etc | 700 m2 @ | £60 | |
| Floor finishes | 97 150 | 77.72 | 5.01 |
| Ceramic tiles and skirtings to floors, steps etc | 1110 m2 @ | £70 | |
| Two coats of epoxy paint on floors in plant rooms etc | 140 m2 @ | £5 | |
| Screeds and movement joints | 1250 m2 @ | £15 | |
| Fittings and furnishings | 223 500 | 178.8 | 11.54 |
| Water slides installations | allow | £135 000 | |
| Lockers | 250 nr @ | £110 | |
| Changing cubicles | 20 nr @ | £1,600 | |
| Pool hall fittings | allow | £14 000 | |
| Internal planting (artificial) | allow | £15 000 | |
| Services | 10 250 | 8.2 | 0.53 |
| Sanitary appliances | k;l'k | jk'k' | |
| Twyfords sanitaryware with Spectrum 2000 integrated plumbing system panels and cubicles; 10 nr wash-hand basins in vanity units; 2 nr cleaners' sinks; 1 nr disposal sink; 2 nr urinal bowls; 9 nr WC suites and miscellaneous fittings | 454 | 465444 | |
| Services equipment | 2500 | 2 | 0.13 |
| 6 nr catering sinks for kitchen area | allow | £2,500 | |
| Disposal installations | 22 500 | 18 | 1.16 |
| Aluminium rainwater pipes; plastic above-ground drainage; clayware and cast iron below-ground drainage; perforated plastic land drainage ring around pool areas basement tank | 1250 m2 @ | £18 | |
| Water installations | 25 000 | 20 | 1.29 |
| Hot and cold domestic water installation | 1250 m2 @ | £20 | |
| Heat source | 50 000 | 40 | 2.58 |
| 4 nr stacked pairs of gas-fired boilers with flues, pumps and controls | 1250 m2 @ | £40 | |
| Space heating and air treatment | 200 000 | 160 | 10.32 |
| Air-handling units for pool area, management suite, wet changing area etc, ductwork and insulation; grilles, diffusers and attenuators | 1250 m2 @ | £160 | |
| Electrical installations | 81 250 | 65 | 4.19 |
| LV distribution and power including cabletray and trunking | 1250 m2 @ | £30 | |
| Electric lighting and luminaires | 1250 m2 @ | £35 | |
| Gas | 1 500 | 1.2 | 0.08 |
| Gas carcassing pipework | 456456 | 465465 | |
| Protective installations | 7 500 | 6 | 0.39 |
| Fire alarm installation | 1250 m2 @ | £5 | |
| Lighting protection system | 1250 m2 @ | £1 | |
| Communication installations | 14 350 | 11.48 | 0.74 |
| Telephone and conduit/trunking installation | 1250 m2 @ | £1 | |
| Public address system | 1250 m2 @ | £8 | |
| Security system | 1250 m2 @ | £3 | |
| Special installations | 260 000 | 208 | 13.42 |
| Two filter filtration ozone water treatment | allow | £195 000 | |
| Wave machine | allow | £35 000 | |
| Other water features including rapids channel, 3 base air geysers, bubble ring, spa jet system, 2 water cannon, beach geysers to beach and kiddies areas and pumping systems for water slides | allow | £30 000 | |
| Builders work in connection with services | 15 000 | 12 | 0.78 |
| Preliminaries and contingencies | 252 500 | 202 | 13.03 |
| Contractor's management and staff, site accommodation and other prelminary items | allow | 10% | |
| Design and contingency allowance | say | 5% | |
| Total for leisure pool | 1 937 500 | 1 550.00 | 100 |
| element cost (£) | £/m2 gifa | % of total cost | |
| SPORTS HALL 1400 m2 | |||
| (excluding adjoining changing/toilet facilities) | |||
| Substructure | 91 000 | 65 | 11.82 |
| Pad foundations with ground beams and reinforced concrete category 1 levelled slab on good ground | 1400 m2 @ | £65 | |
| Frame | 159 125 | 113.66 | 20.67 |
| Structural steel frame with roof trusses | 1400 m2 @ | £80 | |
| One-hour intumescent fire protection on steelwork | 1450 m2 @ | £32.50 | |
| Upper floors | - | - | - |
| First-floor-level spectators' gallery included elsewhere | 7 900 m2 @ | £3.50 | |
| Roof | 98 000 | 70 | 12.73 |
| Insulated composite metal roofcladding | 1400 m2 @ | £70 | |
| External walls | 42 700 | 30.5 | 5.55 |
| Ibstock facing bricks and blockwork cavity wall to 3 m including brick and block specials | 140 m2 @ | £65 | |
| Insulated composite metal wall cladding and blockwork above 3m | 560 m2 @ | £60 | |
| Windows and external doors | 7 000 | 5 | 0.91 |
| External high-level ventilation grilles | 20 m2 @ | £200 | |
| Metal door sets (2 nr double) | allow | £3,000 | |
| Internal walls and partitions | 25 000 | 17.86 | 3.25 |
| Block internal walls | 1000 m2 @ | £25 | |
| Internal doors | 20 700 | 14.78 | 2.69 |
| Leaderflush one-hour fire-resistant double door sets with laminated plastice veneered doors and Acrovyn finished linings | 4 nr @ | £1,300 | |
| Ditto - as sliding/folding doors to storage area | 2 nr @ | £2,000 | |
| Metal door set to delivery area | allow | £4,000 | |
| Roller shutter doors to storage area | 25 m2 @ | £300 | |
| Wall finishes | 3 900 | 2.78 | 0.5 |
| Eggshell paint to fair-faced block | 1300 m2 @ | £3 | |
| Floor finishes | 49 550 | 35.39 | 6.43 |
| Sports hall semi-sprung maple floor and three coats of seal | 1220 m2 @ | £40 | |
| Two coats of epoxy paint on floors in plant rooms etc | 150 m2 @ | £5 | |
| Fittings and furnishings | 40 740 | 29.1 | 5.29 |
| Bleacher seating benches (5 units) | 334 m @ | £110 | |
| Signage, lines and sundries | allow | £4,000 | |
| Sanitary appliances and water installations | - | - | - |
| See facility cost breakdown for adjoining 200m2 corridor changing rooms and toilet area | Item @ | £767 000 | |
| Disposal installations | 7 000 | 5 | 0.91 |
| Aluminium rainwater pipes | 1400 m2 @ | £5 | |
| Heat source | 20 000 | 14.29 | 2.6 |
| 3 nr shared and stacked gas-fired boilers with flues, pumps and controls | allow | £20 000 | |
| Space heating and air treatment | 14 000 | 10 | 1.82 |
| 8 nr radiant gas heaters in sports hall | 1400 m2 @ | £10 | |
| Electrical installations | 63 000 | 45 | 8.18 |
| LV distribution and power including cable tray and trunking | 1400 m2 @ | £20 | |
| Electric lighting and luminaires | 1400 m2 @ | £25 | |
| Protective installations | 7 485 | 5.35 | 0.97 |
| Fire alarm installation | 1400 m2 @ | £4.35 | |
| Lightning protection system | 1400 m2 @ | £1 | |
| Communication installations | 13 300 | 9.5 | 1.73 |
| Telephone and conduit/trunking installation | 1400 m2 @ | £0.50 | |
| Public address system | 1400 m2 @ | £7 | |
| Security system | 1400 m2 @ | £2 | |
| Builders' work in connection with services | 7 500 | 5.36 | 0.97 |
| Preliminaries and contingencies | 100 000 | 71.43 | 12.98 |
| Preliminaries | allow | 10% | |
| Design and contingency allowance | say | 5% | |
| Subtotal for sports hall | 770 000 | 550 | 100 |
| Adjoining toilet and changing facilities | 190 000 | 950 | - |
| Total for sports hall (1600 m2 ) | 960 000 | 600 | - |
| Total for whole scheme (see facility cost breakdown) | 6 600 000 | 880 | - |
| External works (equivalent to plus 8.6%) | 770 000 | 550 | 100 |
| Site works | 247 500 | 33 | - |
| Footpaths and pavings, coated macadam, Marshall Keyblocks and pastel paving slabs | 1000 m2 @ | £35 | |
| Car parks and road areas, coated macadam and Marshall Keyblocks cost | 6500 m2 @ | £25 | |
| Landscaping, seeding, turfing and planting | allow | £50 000 | |
| Drainage | 165 000 | 22 | - |
| Internal drainage | 7500 m2 @ | £17.50 | |
| Surface water drainage to paved areas | 7500 m2 @ | £4.50 | |
| External services | 75 000 | 10 | - |
| Gas water and electricity mains and trenches for services, external lighting installations including trenches. External lighting installations including trenches | allow | £75 000 | |
| Minor building works | 7 500 | 1 | - |
| Electricity substation and gas meter housing | allow | £7,500 | |
| Preliminaries and contingencies | 75 000 | 10 | - |
| TOTAL OVERALL CONSTRUCTION COST | 7 170 000 | 956 | - |
| Alternative element specifications | |
| Net extra / (saving) £/m2 gifa | |
| Combined reinforced concrete basement tank around three pools to spread load over ground - 2025 m2 @ £165-185 | 15-30 |
| Reinforced concrete ring beams and cfa piles with prestressed concrete slab over poor ground to sports and bowl halls - 2760 m2 @ £80-100 | Oct-30 |
| Frame and roof | |
| Centrally masted pitched structural steel frame over pool areas incorporating cellular roof rafters and high-performance insulated composite roof cladding (partially offset by reduced external wall height) - 2025 m2 @ £250-275 | 45-65 |
| External walls | |
| Pilkington Planar double-glazed curtain walling system to from foyer wall - 160 m2 @ £300-350 | 65-80 |
| Floor finishes | |
| Green roll-up bowls carpet including lightweight attached backing - 1100 m2 @ £15-20 | (2-5) |
| Green needlepunch bowls carpet including underlay, markings and fixing - 1100 m2 @ £20-25 | - |
| 2 mm slip-resistant vinyl cushioned flooring with heat welded joint to changing rooms - 260m2 @ £15-20 | (40-45) |
| 6.2 mm vinyl multipurpose flooring, toally adhered with heat welded joints for badminton use - 1220 m2 @ £25-30 | (8-13) |
| 6 mm embossed and spike-resistant vinyl sheet with heat welded joints for cricket or tennis - 1220 m2 @ £30-35 | (4-8) |
| Semi-sprung Junkers beech strip flooring and 3 coats of seal - 1220 m2 @ £37-42 | (3)-2 |
| 10 mm Granwood flooring and 3 coats of seal - 1220 m2 @ £40-45 | 0-4 |
| First-grade semi-sprung maple flooring to squash courts - 208 m2 @ £42-45 | - |
| 10 mm Granwood semi-sprung flooring and 3 coats of seal - 1220 m2 @ £50-55 | 08-Dec |
| Fully sprung Junkers prime beech strip flooring and 3 coats of seal - 1220 m2 @ £50-55 | 08-Dec |
| 14 mm Purlastic SP spike-resistant seamless polyurethane flooring on rubber underlay - overally thickness 70 mm - 1220 m2 @ £55-65 | Dec-20 |
| Polydor full impact absorbing aerobatic vinyl, polyurethane and foam floor - overall thickness 40 mm - 1220 m2 @ £65-70 | 20-30 |
| Special installations | |
| Cholorine water treatment to 25 x 13 m traditional pool - allow £120 000 - 130 000 | - |
| Ozone water treatment to 25 x 13 m traditional pool - allow £180 000 - 200 000 | 55-75 |
| Stand-alone ozone water treatment to health suite spa - allow £50 000 | - |
| 7.5 m long x 13 mm thick movable floor for traditional pool including hydraulics, electrics etc - allow £120 000 - 130 000 | 110-120 |
| 13 m telescopic retractable boom to separate movable and rigid floor swimming areas, allow £60 000 - 65 000 | 55-60 |
| Facility areas costs | |||||||||||
| Leisure pool inc. changing | 25m trad plus learner pool inc. changing | Sports hall no changing | Adjacent and other toilet / changing | Gallery walkway / viewing areas | Bowls hall including changing | Squash courts (3 nr) | Health suite - sauna and spa | Gym / weight training / high tech | Reception / admin | Common plant | |
| (1250 m2) | (1100 m2) | (1400 m2 ) | (260 m2) | (290 m2) | (1460 m2) | (260 m2) | (260 m2) | (140 m2) | (590 m2) | (500 m2) | |
| £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | |
| Substructure | |||||||||||
| Group elemental total | 142 | 110 | 65 | 46 | - | 65 | 60 | - | - | 44 | - |
| Superstructure | |||||||||||
| Frame | 140 | 100 | 113.66 | 50 | 125 | 75 | 50 | 50 | 52 | 50 | 60 |
| Upper floors | 4.4 | 5 | - | 5 | 30 | 2 | - | 20 | 25 | 5 | 30 |
| Roof | 96.08 | 100 | 70 | 45 | 57 | 58 | 60 | 60 | 60 | 75 | 3 |
| Stairs | 20 | 2 | - | - | 40 | - | - | - | - | 31 | 24 |
| External walls | 24 | 28 | 30.5 | 15 | - | 30 | 53 | 30 | 7 | 20 | - |
| Windows and external doors | 16 | 25 | 5 | 10 | - | 6 | 7 | 11 | 4 | 33 | - |
| Internal walls and partitions | 23.84 | 10 | 17.86 | 28 | 108 | 6 | 40 | 36 | 26 | 67 | 17 |
| Internal doors | 14.56 | 8 | 14.78 | 25 | 22 | 9 | 13 | 46 | 28 | 78 | 20 |
| Group elemental total | 338.88 | 278 | 251.8 | 178 | 382 | 186 | 223 | 253 | 202 | 359 | 154 |
| Internal finishes | |||||||||||
| Wall finishes | 58.72 | 60 | 2.78 | 70 | 7 | 22 | 55 | 128 | 14 | 36 | - |
| Floor finishes | 77.72 | 75 | 35.39 | 60 | 52 | 23 | 30 | 88 | 30 | 70 | 5 |
| Ceiling finishes | - | 8 | - | 10 | - | 1 | - | 34 | 32 | 34 | - |
| Group elemental total | 136.44 | 143 | 38.17 | 140 | 59 | 46 | 85 | 250 | 76 | 140 | 5 |
| Fittings and furnishings | |||||||||||
| Group elemental total | 178.8 | 80 | 29.1 | 130 | - | 25 | 2 | 230 | 78 | 97 | - |
| Services | |||||||||||
| Sanitary appliances | 8.2 | 10 | - | 80 | - | 10 | - | 75 | - | 43 | - |
| Services equipment | 2 | - | - | - | - | - | - | - | - | 4 | - |
| Disposal installations | 18 | 18 | 5 | 50 | - | 2 | - | 40 | - | 5 | - |
| Water installations | 20 | 15 | - | 70 | - | 5 | - | 60 | - | 14 | - |
| Heat source | 40 | 40 | 14.29 | 8 | - | 8 | 8 | 24 | 7 | 9 | - |
| Space heating and air treatment | 160 | 160 | 10 | 75 | 60 | 50 | 57 | 100 | 70 | 100 | - |
| Electrical installations | 65 | 66 | 45 | 30 | 16 | 25 | 23 | 40 | 33 | 55 | 8 |
| Gas installations | 1.2 | 2 | - | - | - | - | - | - | - | 3 | - |
| Lift installations | - | - | - | - | - | - | - | - | - | 45 | - |
| Protective installations | 6 | 6 | 5.35 | - | - | 1 | - | - | - | - | - |
| Communication installations | 11.48 | 12 | 9.5 | 6 | - | 8 | 8 | 12 | 7 | 10 | - |
| Special installations | 208 | 180 | - | - | 4 | - | - | 120 | - | - | - |
| Builders' work in connection with services | 12 | 10 | 5.36 | 13 | - | 4 | 4 | 13 | 5 | 7 | 7 |
| Group elemental total | 551.88 | 519 | 94.5 | 332 | 80 | 113 | 100 | 484 | 122 | 295 | 15 |
| BUILDING SUBTOTAL | 1 348.00 | 1 130.00 | 478.57 | 826 | 521 | 435 | 470 | 1 217.00 | 478 | 935 | 174 |
| Preliminaries - allow 10% | 134.7 | 113 | 47.62 | 82.6 | 52 | 43.5 | 47 | 122 | 48 | 94 | 17 |
| Design and contingency - allow 5% | 67.3 | 57 | 23.81 | 41.4 | 27 | 21.5 | 23 | 61 | 24 | 46 | 9 |
| Building cost (excluding external works) | 1 550.00 | 1 300.00 | 550 | 950 | 600 | 500 | 540 | 1 400.00 | 550 | 1 075.00 | 200 |
| Functional unit | 335 m2 pwa* | 375 m2 pwa* | 654 m2 net | - | - | 838 m2 net | 187 m2 net | - | - | - | - |
| Functional unit cost £ | 5 782.00 | 3 813.00 | 1 468.00 | - | - | 871 | 750 | - | - | - | - |
| Sports equipment | 14 | 22 | 38 | - | - | 6 | 0.5 | 120 | 700 | - | - |
| Kitchen and catering equipment | 40 | - | - | - | - | - | - | - | - | 80 | - |
| Furniture and general equipment | 6 | 6 | 6 | - | - | 6 | 6 | 6 | 6 | 200 | - |
| Cleaning equipment | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 |
| Maintenance equipment | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 | 1.5 |
| Building cost (separate buildings) £ | 1 650.00 | 1 400.00 | 650 | - | - | 525 | 575 | - | - | - | - |
| AVERAGE COST RANGE £/m2 | 1000 - 1800 | 900 - 1600 | 400 - 800 | 250 - 1800 | 500- 700 | 300-0600 | 430 - 650 | 1100 - 1500 | 300 - 0800 | 900 - 1100 | 200 - 400 |
| RANGE OF AREAS m2 | 1000 - 3500 | 730 - 2300 | 1000 - 1900 | - | - | 1300 - 3500 | 160 - 1760 | - | 150 - 2400 | - | - |
| AVERAGE AREA m2 | 1700 | 1400 | 1400 | - | - | 2100 | 600 | - | 780 | - | - |
| *pwa = pool water area | |||||||||||
| Regional variations | |
| All costs in this article are based on a scheme in the South-East and should be adjusted by the following location factors for schemes in other regions: | |
| Inner London | 1.2 |
| Outer London | 1.06 |
| East Anglia | 0.98 |
| East Midlands | 0.96 |
| Northern | 0.98 |
| Northern Ireland | 0.84 |
| North-west | 1.02 |
| Scotland | 1.04 |
| South-east | 1 |
| South-west | 0.98 |
| Wales | 0.96 |
| Yorkshire and Humberside | 0.98 |