| Table 1: Building efficiency (net to gross area) of multistorey office developments | |
| Number of storeys | Efficiency (%) |
| Two to four | 83-86 |
| Five to nine | 79-83 |
| 10 to 19 | 72-80 |
| 20 to 29 | 70-78 |
| 30 to 39 | 69-75 |
| 40+ | 68-73 |
| Table 2: Weight of steel per m2 of gross floor area | |||
| Building height (m) | Steel to resist dead load (kg/m2) | Steel to resist wind load (kg/m2) | Total amount of steel (kg/m2) |
| 50 | 60 | 15-35 | 75-95 |
| 100 | 65 | 30-80 | 95-145 |
| 150 | 70 | 50-115 | 120-185 |
| 200 | 75 | 75-175 | 150-250 |
| 300 | 75 | 135+ | 225+ |
| Table 3: Office construction costs | |||||||
| UK | UK | Australia | Australia | Australia | Hong Kong | Hong Kong | |
| Medium rise | High rise | Medium rise | High rise | Super high rise | Medium rise | High rise | |
| £/m2 | £/m2 | A$/m2 | A$/m2 | A$/m2 | HK$/m2 | HK$/m2 | |
| (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | |
| Basic speculative air-conditioned | 720-1030 | n/a | 1680 | 1800 | n/a | 10,000 | n/a |
| (1130-1620) | -1310 | -1400 | -1300 | ||||
| High-quality speculative air-conditioned | 945-1450 | 1300-1700 | 1750 | 1850 | 1950 | 13,000 | 13,000 |
| (1480-2230 | (2040-2660) | -1370 | -1440 | -1520 | -1680 | -1680 | |
| High-quality owner-occupied | 1200-1480 | 1750-2250 | 1850 | 1900 | 2050 | 14,200 | 14,200 |
| (1880-2320) | (2740-3520) | -1440 | -1480 | -1600 | -1830 | -1830 | |
| Hong Kong | Malaysia | Malaysia | Indonesia | Indonesia | Indonesia | Phillipines | |
| Super high rise | Medium rise | High rise | Medium rise | High rise | Super high rise | Medium rise P/m2 | |
| HK$/m2 | RM/m2 | RM/m2 | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | |
| (US$/m2) | (US$/m2) | (US$/m2) | |||||
| Basic speculative air-conditioned | n/a | 1270 | 1690 | n/a | n/a | n/a | 15,000-16,000 |
| -510 | -680 | (575-600) | (626-650) | (900-950) | (575-615) | ||
| High-quality speculative air-conditioned | 14-15,500 | 1490 | 1910 | n/a | n/a | n/a | 17,000-19,000 |
| (1800-2000) | -600 | -770 | (650-700) | (700-750) | (950-1000) | (650-730) | |
| High-quality owner-occupied | 14,000-15,500 | 2240 | 2660 | n/a | n/a | n/a | 19,000-21,000 |
| (1800-2000) | -900 | -1070 | (775-800) | (800-850) | (1050-1150) | (730-210) | |
| Phillipines | Phillipines | Singapore | Singapore | Singapore | Thailand | ||
| High rise P/m2 | Super high rise P/m2 | Medium rise S$/m2 | High rise S$/m2 | Super high rise S$/m2 | Medium rise | ||
| (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | (US$/m2) | ||
| Basic speculative air-conditioned | 18,500-19,200 | n/a | 1900-2000 | 2000-2400 | Singapore | n/a | |
| (710-740) | (1350-1430) | (1430-1710) | (620+) | ||||
| High-quality speculative air-conditioned | 21,000-26,000 | 26,000-30,000 | 2000-2400 | 2200-2600 | 2400-2800 | n/a | |
| (810-1000) | (1000-1150) | (1430-1710) | (1570-1850) | (1710-2000) | (620-900) | ||
| High-quality owner-occupied | 28,000-32,000 | 32,000-36,000 | 2000-2400 | 2200-2600 | 2400-2800 | n/a | |
| (1080-1230) | (1230-1385) | (1430-1710) | (1570-1850) | (1710-2000) | |||
| Table 4: Design criteria - building services | |||||||
| UK | Australia | Hong Kong | Indonesia | Malaysia | Phillipines | Singapore | |
| Occupational density | 1 person/10-14 m2 | 1 person/12 m2 | 1 person/10-14 m2 | 1 person/10-15 m2 | n/a | 1 person/10 m2 | 1 person/10-12 m2 |
| Ventilation rates | 8-12 litres/sec/person | n/a | 6 air changes/hour | 8-10 litres/sec/person | n/a | 5-7 litres/sec/person | 5 litres/sec/person |
| Cooling loads | 25-40 W/m2 | n/a | 1 tonne/20-25 m2 | 120-140 W/m2 | n/a | 24 W/m2 | 25 W/m2 |
| Lighting level | 400-500 lux | n/a | 400-500 lux | 500 lux | 500 lux | 500 lux average | 500 lux |
| Small power loads | 15-35 W/m2 | n/a | 20-30 W/m2 | 35-40 W/m2 | n/a | 10-20 W/m2 | 20-40 W/m2 |
| Lift provision | 1/200-250 people, max wait: 30 sec | 1/2500-3000 m2, max wait: 30 sec | 1/3500 m2 (gross), max wait: 30 sec | 1/2-3 floors, max wait: 30-38 sec | max wait: 60 sec | 1/2500-3000 m2, max wait: 30-40 sec | 4/8 lifts/zone, max wait: 30 sec |
| Life safety systems | Fire detection communications and alarm, pressurised stairs, smoke extract systems, firefighters' lifts, dry/wet risers | Fired detection communications and alarm, fire brigade communication, pressurised stairs, smoke extract systems, smoke isolated lift lobbies | Fire detection and alarm, pressurised stairs, smoke extracts, sprinklers | Fire detection and alarm, duplicate pressurised stairs, dry/wet risers, sprinklers | Fire detection and alarm, smoke spill system, dry/wet risers, sprinklers | Fire detection and alarm, smoke control, firefighers' lifts, automatic fire suppression, emergency escape equipment | Fire detection and alarms, duplicate pressurised fire stairs, sprinklers dry/wet risers, smoke isolated lobbies |
| Table 5: Design criteria - space planning | ||||||||
| UK | Australia | Hong Kong | Indonesia | Malaysia | Phillipines | Singapore | Thailand | |
| Occupational density | 1 person/10-12 m2 (nett) | 1 person/10-12 m2 | 1 person/10-12 m2 | 1 person/10-15 m2 | n/a | 1 person/10 m2 | 1 person/10-12 m2 | n/a |
| Planning grid | 1350 or 1500 mm | 500 mm | n/a | 1200-1250 mm | n/a | 1500-2000 mm | 600 mm | 1500 mm |
| Structural grid | 6 x 9 m or 9 x 9 m | n/a | 8 x 8 m to 12 x 12 m | 8 x 8 m | 8.5 x 8.5 m | 6 x 9 m | 8 x 8 m to 8 x 10 m | 6 x 9 or 9 x 9 m |
| Floor loadings (office areas) | 5 kN/m2 | n/a | 3 kN/m2 (minimum) | 2.5 kN/m2 | 3 kN/m2 | n/a | 3.5 kN/m2 | 3 kN/m2 |
| Raised floor requirement | yes | no | yes | no | no | no | yes | no |
| Raised floor zone (if required) | 150 mm | 150 mm | 290 mm | 200 mm | 300 mm | 150 mm | 150 mm | n/a |
| Table 6: Design criteria -floor plate dimensions | |||||||||
| UK | Australia | China | Hong Kong | Indonesia | Malaysia | Phillipines | Singapore | Thailand | |
| Floor plate preferred size (m2) | 2500-3000 | n/a | 1500-2600 | up to 1600 | 1770-2000 | n/a | up to 1800 | 1400 | up to 1600 |
| Minimum economic floor plate (m2) | n/a | 1200 | n/a | 1000 | 800-1000 | n/a | 1000 | 650-700 | 1000 |
| Maximum window to core depth | no statutory limit, 11-18 m | no statutory limit, 12-15 m | statutory limit 15 m | no statutory limit, 12-14 m | no statutory limit | n/a | no statutory limit, | no statutory limit, | no statutory limit, |
| Minimum slab to slab height (mm) | n/a | 3500 | 3350 | n/a | 3750 | 10-15 m | 12 m typical | 9-10 m tpical | |
| Typical slab to slab height (mm) | 3700-4000 | 3800 | 3800-4000 | 3725 | 3800-4200 | 3200 | 3000 | 3850 | 3500 |
| Minimum clear ceiling zone (mm) | 450 | 400 | n/a | 850 (from soffit) | 600-700 | 3500 | 3800 | 4200-4500 | 3600 |
| Minimum floor to ceiling height (mm) | n/a | n/a | 2400 (office spaces) | n/a | `2500 | 600 | n/a | 900 (from soffit) | 300-450 |
| 2200 (circulation) | 2600 | 2400 | 2400 | 2400 | |||||
| Typical floor to ceiling height (mm) | 2600-2750 | 2700 | 2600-2700 | 2520 | 2500-2700 | 2700 | 2500-3000 | 2700-2800 | 2600-2700 |
| Typical external envelope to floor ratio | 0.26-0.42 | 0.42 | 0.35-0.50 | 0.35-0.45 | 0.4 | n/a | 0.33-0.45 | 0.4 | n/a |
| Table7: Elemental costs in eight countries | ||||||||
| United Kingdom City of London | Australia Melbourne | China Shanghai | Germany Frankfurt | Indonesia Jakarta | Malaysia Kuala Lumpur | Philippines Metro Manila | Singapore | |
| Element | US$/m2 (£/m2) | US$/m2 | US$/m2 | US$/m2 | US$/m2 | US$/m2 | US$/m2 | US$/m2 |
| Substructure | 156 (100) | 20 | 35 | 200 | 75 | 100 | 45 | 85 |
| Superstructure | ||||||||
| Frame and upper floors | 398 (255) | 170 | 245 | 730 | 95 | 145 | 205 | 190 |
| Roof | 8 (5) | in frame cost | in frame cost | 45 | 10 | 20 | in frame cost | 80 |
| Stairs | 55 (35) | 10 | in frame cost | in frame cost | 5 | 5 | in frame cost | in frame cost |
| External walls | 468 (300) | 225 | 160 | 480 | 120 | 115 | 175 | 280 |
| Windows and doors | 8 (5) | 5 | 5 | in wall cost | 40 | in wall cost | 15 | 55 |
| Internal partitions | 70 (45) | 50 | 10 | 340 | 10 | 10 | 10 | 10 |
| Internal doors | 47 (30) | 10 | in partition cost | in partition cost | 10 | 5 | in partition cost | 10 |
| Finishes | ||||||||
| Walls | 55 (35) | 35 | 25 | 140 total | 30 | 10 | 35 | 5 |
| Floors | 86 (55) | 45 | 20 | inc floors/ceilings | 20 | 10 | 35 | 40 |
| Ceilings | 70 (45) | 40 | 15 | %22 | 20 | 15 | 15 | 10 |
| Fittings | 31 (20) | 20 | 10 | 40 | 15 | 5 | 15 | 20 |
| Services | ||||||||
| Sanitary installations | 8 (5) | in disposal cost | 5 | in fittings cost | 5 | 5 | 5 | 5 |
| Disposal installations | 8 (5) | 45 | 15 | 30 | 5 | 15 | 25 | 20 |
| Water installations | 23 (15) | in disposal cost | in disposal cost | 65 | 5 | in disposal cost | in disposal cost | in disposal cost |
| Heating/ventilating/ services equipment | 312 (200) | 190 | 100 | 310 | 75 | 90 | 60 | 155 |
| Electrical installations | 125 (80) | 105 | 80 | 190 | 65 | 50 | 75 | 120 |
| Lift installations | 125 (80) | 95 | 100 | 170 | 95 | 85 | 80 | 140 |
| Protective installations | 31 (20) | 30 | 40 | in H&V cost | 25 | 20 | 15 | 30 |
| Communications installations | 31 (20) | 10 | 5 | 65 | 10 | 15 | 10 | - |
| Special installations | 47 (30) | 10 | 20 | in H&V cost | 10 | 30 | 20 | 5 |
| Builder's work in connection | 39 (25) | - | - | 60 | 5 | 10 | 15 | 10 |
| Preliminaries | 374 (240) | 195 | included | 250 | 65 | included | 55 | 150 |
| Total | 2575 (1650) | 1310 | 890 | 3115 | 815 | 760 | 920 | 1420 |
| Analysis of the model | |||
| Element cost (£) | £/m2 gifa | % of total cost | |
| Substructure | 6 597 700 | 97.74 | 6.76 |
| Foundations: bored piles 30 m deep and 1.5-2.4m diameter; 500 mm thick ground slab | 4210 m2 @ | £370 | |
| Extra for two-level basement construction: diaphragm walls; insitu concrete frame and floors; waterproofing; drainage | 8400 m2 @ | £600 | |
| Frame | 13 882 000 | 205.66 | 14.23 |
| Insitu concrete shear wall construction to cores, average 250 mm thick | 21 800 m2 @ | £115 | |
| Structural steel frame to upper floors and roof, allowance based on 90 kg/m2 | 6000 t @ | £1,500 | |
| Additional secondary steelwork for trimming openings and so on | 300 t @ | £1,800 | |
| Fire protection: mineral wool slab | 87 750 m2 @ | £20 | |
| Concrete casing to perimeter columns at ground floor only | item @ | £80 000 | |
| Upper floors | 3 461 000 | 51.27 | 3.55 |
| Composite floor construction: 150 mm thick reinforced insitu concrete suspended slab; galvanised steel decking; total design load 5 kN/m2 | 61 400 m2 @ | £55 | |
| Extra for 7.5 kN/m2 loading to 5% of floor area | 3400 m2 @ | £10 | |
| Allowance for knocked panels in upper floor construction | item @ | £50 000 | |
| Roof | 369 600 | 5.48 | 0.38 |
| Composite roof slab construction: 150 mm thick reinforced insitu concrete; galvanised steel decking; PVC membrane; insulation; ballast | 1920 m2 @ | £100 | |
| Extra for 7.5kN/m2 loading to plant areas: heavy-duty waterproofing membrane | 1000 m2 @ | £20 | |
| Allowance for perimeter safety rails | 176 m @ | £100 | |
| Allowance for plant bases and paved access routes to plant areas | item @ | £20 000 | |
| Allowance for roof-level plant enclosures: structural steel frame; profiled aluminium raised-seam roof cladding; insulation | item @ | £120 000 | |
| Stairs | 2 530 000 | 37.48 | 2.59 |
| Precast concrete escape stairs rising 35 floors overall: balustrades; handrails; finishes | 300 flights @ | £8,000 | |
| Precast concrete escape stairs rising two floors overall from basements: balustrades; handrails; finishes | 16 flights @ | £5,000 | |
| Allowance for ladders and catwalks in plant rooms | item @ | £50 000 | |
| External walls | 20 222 900 | 299.6 | 20.73 |
| Aluminium-framed full-height curtain wall: double-glazed units; solar control glazing; toughened outer pane; laminated inner; opaque glazed spandrel panels | 22 700 m2 @ | £800 | |
| Double-glazed Planar frameless glazing includnig secondary steel supports | 1150 m2 @ | £600 | |
| Cladding to roof-level plant rooms: structural steel framing; composite panels; blockwork backing wall; louvres | 500 m2 @ | £300 | |
| Louvres as external walling to plant room floors including louvre screen to open roof-level plant areas | 1750 m2 @ | £400 | |
| Cladding to soffits, silver anodised aluminium | 270 m2 @ | £270 | |
| Column casings, silver anodised aluminium | 500 m2 @ | £300 | |
| Allowance for entrance canopy | item @ | £100 000 | |
| Allowance for mock-ups, testing and so on | item @ | £200 000 | |
| External doors | 175 000 | 2.59 | 0.18 |
| Double-glazed aluminium frame exit and fire escape doors | item @ | £50 000 | |
| Motorised revolving doors: 2.5 m diameter; glass/stainless steel enclosure | 2 @ | £35 000 | |
| Access doors to roof plant areas | item @ | £15 000 | |
| Motorised security shutters to car park/loading bay entrance | item @ | £40 000 | |
| Internal walls and partitions | 3 006 800 | 44.55 | 3.08 |
| Metal stud walls to lift shafts and services risers, two-hour fire resistance | 18 300 m2 @ | £90 | |
| Metal stud partitions, one-hour fire resistance | 10 550 m2 @ | £45 | |
| Allowance for partitions to basement, plant and storage areas | 2000 m2 @ | £40 | |
| Blockwork backing walls to stone cladding in lobby areas | 1000 m2 @ | £40 | |
| WC cubicles, including doors and ironmongery | 370 @ | £1,500 | |
| Full-height laminate-faced duct access panels to WCs | 1750 m2 @ | £120 | |
| Internal doors | 2 070 000 | 30.67 | 2.12 |
| Single doors and frames to office areas: fire-rated hardwood veneered doorsets; vision panels; stainless steel ironmongery | 400 @ | £1,700 | |
| Double doors and frames to office areas: fire-rated hardwood veneered doorsets; vision panels; stainless steel ironmongery | 260 @ | £2,000 | |
| Double doors to riser cupboards:fire-rated full-heighted hardwood veneered doors; solid hardwood frame; ironmongery | 420 @ | £1,500 | |
| Doors and frames to plant room areas: steel doorsets; fire-rated where required; stainless stell ironmongery | 420 @ | £1,000 | |
| Allowance for fire-rated access panels | item @ | £200 000 | |
| Wall finishes | 73 400 | 58.72 | 3.79 |
| Stone cladding to entrance lobby walls | 100 m2 @ | £300 | |
| Plasterboard drylining to concrete shear walls in cores, emulsion paint finish | 11 200 m2 @ | £40 | |
| Self-coloured render finish to lift lobby walls on upper floors | 5800m2 @ | £120 | |
| Drylining to perimeter columns in office areas | 7800 m2 @ | £45 | |
| Glass-reinforced gypsum column casings to office areas | 500 m2 @ | £300 | |
| Emulsion paint to circulation areas, plant rooms and so on | 9800 m2 @ | £5 | |
| Ceramic tiling to toilets and cleaners' cupboards | 2900 m2 @ | £65 | |
| Floor finishes | 97 150 | 77.72 | 5.01 |
| Granite tile to lobby areas: lightweight concrete to make-up levels; screed; skirtings | 750 m2 @ | £170 | |
| Unvitrified ceramic tiles to WCs: lightweight concrete to make-up levels; screed; skirtings | 2230 m2 @ | £90 | |
| Carpet to lift lobbies and circulation areas: lightweight concrete to make-up levels; screed; skirtings | 4110m2 @ | £80 | |
| Floor finish to plant and ancillary areas: coloured epoxy resin; screed | 3900 m2 | £25 | |
| Floor finish to loading dock, parking and ramps | 1900 m2 | £10 | |
| Allowance for matwells | item @ | £20 000 | |
| Ceiling finishes | 459 200 | 6.8 | 0.47 |
| Glass-reinforced gypsum feature ceiling to entrance lobby | 750 m2 | £200 | |
| Concealed grid plasterboard suspended ceilingto lift lobbies and circulation areas and bulkheads | 3400 m2 @ | £45 | |
| Concealed grid metail tray suspended ceiling to WCs | 2230 m2@ | £40 | |
| Paint finish to sofitt of slabs to plant rooms, ancillary spaces and car parking | 5800 m2 | £5 | |
| Acoustic installation lining to car park soffit | 1900 m2 | £20 | |
| Furniture and fittings | 1 075 000 | 15.93 | 1.1 |
| Allowance for water feature to main entrance lobby | item @ | £75 000 | |
| Granite vanity tops | 500 m2 | £750 | |
| Allowance for fittings to WCs | item @ | £400 000 | |
| Reception desk | item @ | £45 000 | |
| Main entrance and statutory signage | item @ | £100 000 | |
| Car park bollards, column guards, entrance barrier | item @ | £50 000 | |
| Rubbish compactor | item @ | £30 000 | |
| Sanitary fittings | 324 000 | 4.8 | 0.33 |
| Allowance for sanitary fittings | 1200 m2 @ | £270 | |
| Water installations | 911 300 | 13.5 | 0.94 |
| Hot and cold water: boosted copper rising main; bulk storage; boosted cold water distribution; localised electric heating | 67 500 m2 @ | £13.50 | |
| Space heating and air treatment | 8 707 500 | 129 | 8.93 |
| Gas installation | item @ | £40 000 | |
| Low-temperature hot-water heating: perimeter heating installation to offices; emitters; pipework; insulation; gas-fired boilers | 67 500 m2 @ | £45 | |
| Air-conditioning installation: air-handling plant; refrigeration; chilled water distribution for four-pipe fan coil installation to offices; ductwork terminated at cores | 67 500 m2 @ | £75 | |
| Toilet extract installation | 67 500 m2 @ | £4 | |
| Smoke extract installation | 67 500 m2 @ | £3 | |
| Car park and loading dock extract ventilation | 1900 m2 @ | £50 | |
| Electrical installations | 2 545 000 | 37.7 | 2.61 |
| Mains and sub-mains installation | item @ | £500 000 | |
| Power supply to mechanical plant | 67 500 m2 @ | £4 | |
| Low-voltage distribution in risers to office areas | 44 300 m2 @ | £10 | |
| Lighting, emergency lighting and small power to landlord's areas | 20 200 m2 @ | £45 | |
| Lighting and emergency lighting to car park and loading bay | 1900 m2 @ | £20 | |
| Allowance for enhanced lighting to reception and lobbies | item @ | £75 000 | |
| Allowance for external lighting | item @ | £150 000 | |
| Allowance for beacon and aircraft safety lights | item @ | £10 000 | |
| Stanby power installation; life safety systems only | item @ | £150 000 | |
| Lift installations | 5 200 000 | 77.04 | 5.33 |
| 21-person, 1600 kg lift serving 18 floors, 3 m/sec | 6 @ | £200 000 | |
| 21-person, 1600 kg lift serving 35 floors, 6 m/sec | 10 @ | £280 000 | |
| 10-person, 800 kg firefighters' lift serving 35 floors | 4 @ | £200 000 | |
| Goods lift: 3000 kg serving 35 floors | 2 @ | £200 000 | |
| Protective installations | 1 474 500 | 21.84 | 1.51 |
| Sprinklers: single level to all areas; common bulk storage; split landlord/tenant pumpsets | 67 500 m2 @ | £19 | |
| Dry riser installation | item @ | £50 000 | |
| Hose reels including booster set | 140 @ | £800 | |
| Lighting protection | item @ | £30 000 | |
| Communication installations | 960 000 | 14.22 | 0.99 |
| Fire-detection, voice alarm and public address system: analogue addressable with interfaces to mechanical plant, lift controls, sprinkler installation and building management system | 67 500 m2 @ | £9 | |
| Primary vertical containment and distribution for data and communications systems | 67 500 m2 @ | £3 | |
| Security installation: closed-circuit television and intruder detection | item @ | £150 000 | |
| Special installations | 1 525 000 | 22.59 | 1.56 |
| Building management system with lighting control | 67 500 m2 @ | £18 | |
| Fully automated facade cleaning cradle | item @ | £250 000 | |
| Communications mast | item @ | £60 000 | |
| Builders work in connection | 1 086 000 | 16.09 | 1.11 |
| Associated builder's work: services ducts and risers; holes; sleeves; chases; bases; firestopping, and so on, allow 5% | item @ | £1 086 000 | |
| Preliminaries and contingencies | 17 592 200 | 260.63 | 18.03 |
| Construction manager's fee, site supervision, multi-service gangs, site establishment and trade contractor's preliminaries, allow 17% | item @ | £13 594 000 | |
| Design and contingency allowance, allow 5% | item @ | £3 998 200 | |
| Total for shell-and-core construction | 97 557 000 | 1445.29 | 100 |
| Element cost (£) | £/m2 gifa | % of total cost | |
| Category A fit-out | |||
| Wall finishes | 243 600 | 3.61 | n/a |
| Vinyl wallpaper to drylining in office areas | 20 300 m2 @ | £12 | |
| Floor finishes | 2 879 500 | 42.66 | n/a |
| Medium-grade access floor, dust sealant | 44 300 m2 @ | £35 | |
| Carpet tiles | 44 300 m2 @ | £30 | |
| Ceiling finishes | 2 436 500 | 36.1 | n/a |
| Concealed grid metal tray suspended ceiling to office areas: acoustic quilt; fire breaks | 44 300 m2 @ | £55 | |
| Fittings | 264 000 | 3.91 | n/a |
| Manually operated blinds to office areas | 8800 m2 @ | £30 | |
| Space heating and air treatment | 4 651 50 | 68.91 | n/a |
| Extension of four-pipe fan coil installation into office areas: distribution ductwork; fan coil units; grilles and diffusers; insulation; condensate drainage; interface with building management system | 44 300 m2 @ | £105 | |
| Electrical installations | 3 012 400 | 44.63 | n/a |
| Small power to office areas: under floor distribution with one outlet per 5 m2 | 44 300 m2 @ | £25 | |
| Lighting and emergency lighting to office areas | 44 300 m2 @ | £43 | |
| Communications installations | 354 400 | 5.25 | n/a |
| Final connections to fire, smoke-detection, alarm and public address systems in office areas | 44 300 m2 @ | £8 | |
| Protective installations | 708 800 | 10.5 | n/a |
| Single-leve sprinklers to office areas with one head per 9 m2 | 44 300 m2 @ | £16 | |
| Special installations | 310 100 | 4.59 | n/a |
| Extension of building management system into office areas | 44 300 m2 @ | £7 | |
| Builders' work in connection | 452 000 | 6.7 | n/a |
| Associated builder's work: holes; sleeves; chases; bases; firestopping and so on, allow 5% | item @ | £452 000 | |
| Preliminaries and contingencies | 3 369 200 | 49.91 | n/a |
| Contruction manager's fee, site supervision, multi-service gang, site establishment and trade contractor;s prelminaries, allow 17% | item @ | £2 603 400 | |
| Design reserve and contingency allowances, allow 5% | item @ | £765 800 | |
| Total for category A fit-out | 18 682 000 | 276.77 | n/a |
| TOTAL CONSTRUCTION COST | 116 239 000 | 1722.06 | n/a |
| Tender price inflation | ||
| Forecast for tender price inflation (%) | ||
| 1997 | 1998 | |
| UK | 5 | 8 |
| Australia | 3 | 2 to 4 |
| China | -5 to -10 | -5 to -10 |
| Hong Kong | 12.7 | 15 |
| Indonesia | 1 to 2 | 1 |
| Malaysia | 5 | 5 |
| Philippines | 12 | 10 to 12 |
| Singapore | 4 to 5 | 4 to 5 |
| The table below gives forecasts for annual average changes to tender levels in the UK and Far East. | ||