| Indicative costs of fire protection to structural steelwork | ||||||
| Fire protection period | Mineral fibre board | Gypsum board | Calcium silicate board | Cementitious spray | Intumescent spray | |
| mins | £/m2 | £/m2 | £/m2 | £/m2 | £/m2 | |
| 30 | 15-20 | 20-25 | 25-30 | 10-12 | 6-9 | |
| 60 | 15-20 | 20-25 | 25-30 | 10-12 | 8-12 | |
| 90 | 15-20 | 25-30 | 30-35 | 13-15 | 17-25 | |
| 120 | 20-25 | 30-35 | 35-40 | 16-18 | 30-40 | |
| 180 | – | – | 45-60 | 20-25 | – | |
| 240 | – | – | 50-85 | 25-35 | – | |
| Table notes | ||||||
| Rates assume straightforward access and are for quantities in excess of 1000 m2. | ||||||
| Rates for boarded solutions are measured as the area of box required. | ||||||
| Rates for spray solutions are measured as surface area covered. | ||||||
| Rates for large section work will generally be at the lower end of the range or below. | ||||||
| Rates for small section work will generally be at the higher end of the range or above. | ||||||
| Rates for hollow sections will usually be higher than the rates shown. | ||||||
| Work at height (more than 5 m above ground level) may attract higher rates (7.5–10%). | ||||||
| Intumescent rates | ||||||
| These exclude blast cleaning of steelwork and primer coat, which is normally part of off-site steel preparation. | ||||||
| Off-site application rates may be 50% higher than the rates above. | ||||||
| Decorative top-coat sealer will add £2-3 per m2 to the rates above. | ||||||
| Boarded rates | ||||||
| These exclude any subsequent decoration. | ||||||
| Metal-faced boarding may attract rates of £50-85 per m2. | ||||||