| Cost breakdown | |||
| Element cost | cost/m2 gfa £ | % of total cost | |
| Substructure | 13,954,000 | 117.80 | 5.45% |
| Allowance for breaking out existing slabs and retaining walls Item @ 250,000 | |||
| Allowance for preparatory work and dewatering all of the excavations Item @ 600,000 | |||
| Foundations: large diameter bored piles, for example 40 m deep; 2 m thick ground slab 2,600 m2 @ 1,500 | |||
| Extra for three-level basement construction: part secant piled walls, part diaphragm walls; insitu concrete frame and floors; waterproofing; drainage 7,800 m2 @ 1,000 | |||
| Allowance for removal of obstructions Item @ 250,000 | |||
| Allowance for treatment of contaminated surfaces 2,600 m2 @ 40 | |||
| Allowance for temporary works Item @ 750,000 | |||
| Allowance for lift pits, escalator pits, tower crane bases, etc Item @ 300,000 | |||
| Frame | 41,928,000 | 353.97 | 16.38% |
| Structural steel frame to upper floors, based on 200 kg/m2 overall (avg rate) 22,130 t @ 1,200 | |||
| Secondary steelwork for cladding, trimming openings, etc 2,200 t @ 1,600 | |||
| Extra for feature steel framing in reception/other areas Item @ 500,000 | |||
| Fire protection to frame based on a combination of two-hour boarding and one-hour intumescent spray (avg rate used, based on 20 m2/tonne) 482,600 m2 @ 20 | |||
| Allowance for concrete casing or infilling to some columns Item @ 500,000 | |||
| Allowance for wind canopy structures Item @ 200,000 | |||
| Allowance for additional ductile connections Item @ 1,000,000 | |||
| Upper floors | 8,146,000 | 68.77 | 3.18% |
| Composite floor construction; 130 mm thick reinforced insitu concrete; galvanized steel decking; total design load 4.5 kN/m2 110,650 m2 @ 55 | |||
| Extra for 7.5 kN/m2 loading to plant and other areas 10,000 m2 @ 25 | |||
| Extra for forming ramps, steps, and so on Item @ 500,000 | |||
| Allowance for knock-out panels in upper floors construction Item @ 200,000 | |||
| Allowance for lift pits, escalator pits, etc in upper floors construction Item @ 150,000 | |||
| Allowance for insulation to edges of floor slabs 8,800 m @ 75 | |||
| Extra for intermediate floors to atrium at six-storey intervals Item @ 300,000 | |||
| Roof | 1,657,000 | 13.99 | 0.65% |
| Waterproofing over external slab at ground level (over basements) 124 m2 @ 80 | |||
| Composite roof slab construction, with waterproofing, insulation, ballast 2,350 m2 @ 200 | |||
| Extra for access paving to 10% of roof area 250 m2 @ 75 | |||
| Extra for stone paving to terraces 100 m2 @ 150 | |||
| Architectural balustrading to roof terraces 50 m @ 550 | |||
| Glazed atrium roof, with opening lights for ventilation/smoke extract; framing 200 m2 @ 1,200 | |||
| Allowance for roof feature/screening to roof level plant Item @ 400,000 | |||
| Allowance for perimeter safety rails, perimeter detailing & interface details Item @ 250,000 | |||
| Allowance for plant bases and base for communication mast Item @ 50,000 | |||
| Allowance for roof-level plant enclosures; structural steel frame; profiled aluminium raised seam roof cladding, insulation Item @ 175,000 | |||
| Stairs | 3,086,000 | 26.05 | 1.21% |
| Painted mild steel escape stairs in two straight flights, including all finishes 94 @ 16,000 | |||
| Precast concrete stairs serving basements 8 @ 14,000 | |||
| Allowance for feature staircases Item @ 900,000 | |||
| Steel stairs within retail areas 8 @ 15,000 | |||
| Allowance for disabled access provisions Item @ 250,000 | |||
| Allowance for ladders and catwalks in plant rooms Item @ 200,000 | |||
| External walls | 61,264,000 | 517.21 | 23.94% |
| Triple glazed “active wall” facade system: double-glazed outer skin, single-glazed inner skin with opening lights; integral motorised blinds 51,000 m2 @ 875 | |||
| Allowance for enhanced articulation in certain areas Item @ 5,000,000 | |||
| Double-glazed atrium wall 3,700 m2 @ 1,000 | |||
| Double-height glass wall system to ground floor, including all supports 800 m2 @ 1,500 | |||
| Glass shop fronts 230 m2 @ 800 | |||
| Louvres as external walling to plant floors/roof plant areas 3,100 m2 @ 550 | |||
| Solid walls in loading bay/service yard Item @ 50,000 | |||
| Unitised metal cladding to exposed core areas, and loading bay 8,000 m2 @ 450 | |||
| Metal cladding to soffits Item @ 150,000 | |||
| Allowance for entrance canopy/wind canopies Item @ 350,000 | |||
| Allowance for mock-ups, testing and so on Item @ 700,000 | |||
| External doors | 916,000 | 7.73 | 0.36% |
| Double-glazed aluminium frame exit and fire escape doors 25 @ 4,000 | |||
| High-quality motorised revolving doors and side doors for disabled access 4 @ 150,000 | |||
| Shopfront automatic doors 8 @ 7000 | |||
| Access doors to roof plant areas Item @ 40,000 | |||
| Metal doors in service areas Item @ 30,000 | |||
| Motorised security shutters to car park/loading bay entrance (including cladding interfaces) 2 @ 45,000 | |||
| Internal walls and partitions | 7,153,000 | 60.39 | 2.80% |
| Two-hour metal stud partitions around cores 29,100 m2 @ 90 | |||
| One-hour metal stud partitions within core areas 17,900 m2 @ 55 | |||
| Extra for shaft wall construction Item @ 500,000 | |||
| Single-glazed wall around atriums 2,500 m2 @ 700 | |||
| Block walls in basements and plant areas 4,200 m2 @ 50 | |||
| Block walls dividing retail units 500 m2 @ 60 | |||
| Cantilevered glass balustrade around mezzanine 22 m2 @ 1,200 | |||
| Allowance for substation enclosure and access Item @ 200,000 | |||
| WC cubicles, including doors and ironmongery 450 @ 1,250 | |||
| Full height laminate-faced duct access panels to toilets 1,800 m2 @ 150 | |||
| Internal doors | 2,483,000 | 20.96 | 0.97% |
| High quality glazed double doors/side panels to lift lobbies 96 @ 7,000 | |||
| Hardwood doors in core areas, fire-rated where necessary (average rate) 575 @ 1,350 | |||
| Riser cupboard doors: fire-rated hardwood doorsets 490 @ 1,500 | |||
| Metal doors in plant/service areas, 160 @ 1,250 | |||
| Allowance for fire-rated access panels Item @ 100,000 | |||
| Wall finishes | 3,400,000 | 28.7 | 1.36% |
| Stone cladding to entrance lobby and lift lobbies 5,120 m2 @ 300 | |||
| Allowance for feature wall in main reception Item @ 200,000 | |||
| Finish to edges of slabs overlooking reception 22 m @ 300 | |||
| Emulsion to core walls/plasterboard partitions & other walls 51,700 m2 @ 5 | |||
| GRG circular casings to internal columns in office areas 3,000 m2 @ 175 | |||
| Emulsion paint to service areas, plant rooms, facilities offices, storage areas 25,000 m2 @ 5 | |||
| Good-quality ceramic tiling to toilets 6,885 m2 @ 100 | |||
| Ceramic tiling in cleaners’ cupboards and service areas 1,000 m2 @ 60 | |||
| Floor finishes | 2,771,000 | 23.39 | 1.08% |
| Granite tiles to main entrance lobby, lift lobbies, | |||
| mezzanine areas and atrium base 4,100 m2 @ 300 | |||
| Good-quality ceramic tiles to toilets, lightweight | |||
| concrete to make up levels 4,000 m2 @ 125 | |||
| Raised floors to lift lobbies 2,580 m2 @ 37 | |||
| Ceramic tiling to cleaners’ cupboards and service areas 350 m2 @ 50 | |||
| Raised floor and good-quality carpet tiles to circulation areas 3,820 m2 @ 85 | |||
| Epoxy paint on screed to plant and service areas 9,290 m2 @ 25 | |||
| Sealer/hardener/wpm/wear course to loading dock, | |||
| service areas, car park 1,700 m2 @ 65 | |||
| Allowance for making up levels in other areas Item @ 50,000 | |||
| Allowance for linoleum to facilities offices, storage areas, and so on Item @ 30,000 | |||
| Entrance mats and matwells Item @ 80,000 | |||
| Allowance for sundry floor finishes in other areas Item @ 100,000 | |||
| Ceiling finishes | 1,879,000 | 15.86 | 0.73% |
| Feature ceiling to entrance lobby, mezzanine and lift lobbies 3,900 m2 @ 250 | |||
| Non-standard metal suspended ceiling to circulation areas 3,820 m2 @ 100 | |||
| Metal suspended ceiling to toilets 4,000 m2 @ 50 | |||
| Paint finish to soffit of slabs to plant areas 9,290 m2 @ 10 | |||
| Acoustic insulation lining to car park soffit 950 m2 @ 30 | |||
| Allowance for other ceiling finishes/detailing Item @ 200,000 | |||
| Furniture and fittings | 4,092,000 | 34.55 | 1.60% |
| Granite vanity tops in toilets 650 m @ 1,100 | |||
| Fittings to toilets (including allowance for disabled fittings) 4,000 m2 @ 500 | |||
| Wall protection in goods lift lobbies 860 m2 @ 60 | |||
| Main reception desk/screen Item @ 100,000 | |||
| Main entrance and statutory signage; external signage Item @ 250,000 | |||
| Car park bollards, column guards, entrance barriers Item @ 75,000 | |||
| Cycle racking and cycle changing area fit-out Item @ 50,000 | |||
| Dockmaster/security room fit-outs Item @ 30,000 | |||
| Rubbish compactor/bailer Item @ 35,000 | |||
| Allowance for main entrance features/fittings/objets d’art Item @ 500,000 | |||
| Traffic management system Item @ 35,000 | |||
| Allowance for sundry fittings Item @ 250,000 | |||
| Sanitary fittings | 785,000 | 6.63 | 0.31% |
| Allowance for WCs, basins, cleaners’ sinks, urinals (average rate used) 800 @ 700 | |||
| Extra for disabled toilets 100 @ 2,000 | |||
| Shower installations 20 @ 750 | |||
| Water softeners 2 @ 5,000 | |||
| Disposal installations | 1,808,000 | 15.26 | 0.71% |
| Allowance for rainwater disposal 118,450 m2 @ 5 | |||
| Soil waste and vent installation 118,450 m2 @ 9 | |||
| Extra for drainage to retail units Item @ 150,000 | |||
| Water installations | 1,176,000 | 9.93 | 0.46% |
| Cold water: boosted rising main, bulk storage, treatment, etc 118,450 m2 @ 6 | |||
| Hot water services by local electric water storage heaters 118,450 m2 @ 3 | |||
| Water services for vending areas Item @ 60,000 | |||
| Extra for supplies to retail units Item @ 50,000 | |||
| Space heating and air treatment | 15,728,000 | 132.78 | 6.15% |
| Gas installation Item @ 175,000 | |||
| Low temperature hot water heating installation (including gas-fired boilers) 118,450 m2 @ 22 | |||
| Air-conditioning installation: air-handling plant, refrigeration, | |||
| chilled water distribution for four-pipe fan coil installation to offices 118,450 m2 @ 70 | |||
| Toilet extract installation 118,450 m2 @ 7 | |||
| Smoke extract installation 118,450 m2 @ 12 | |||
| Dedicated extract system for external wall void Item @ 1,150,000 | |||
| Extra for smoke extract and ventilation to atrium spaces Item @ 600,000 | |||
| Car park and loading bay extract ventilation 118,450 m2 @ 3 | |||
| Stair/lobby pressurisation Item @ 300,000 | |||
| Electrical installations | 8,329,000 | 70.32 | 3.26% |
| Mains and submains installations 118,450 m2 @ 29 | |||
| Power supply to mechanical plant 118,450 m2 @ 4 | |||
| Small power installations 118,450 m2 @ 4 | |||
| Power and controls for window blinds Item @ 450,000 | |||
| Lighting, emergency lighting and small power to landlord’s areas 118,450 m2 @ 15 | |||
| Lighting and emergency lighting to basement areas, | |||
| car park and loading bay 7,812 m2 @ 60 | |||
| Allowance for enhanced lighting to reception and lift lobbies Item @ 600,000 | |||
| Allowance for external lighting Item @ 200,000 | |||
| Standby power installation (life safety systems only), including oil system Item @ 450,000 | |||
| Lift installations | 21,090,000 | 178.05 | 8.24% |
| 21-person 1600 kg passenger lift 3 m/s serving low-rise floors 8 @ 600,000 | |||
| 21-person 1600 kg passenger lift 3.5 m/s serving mid-rise floors 8 @ 750,000 | |||
| 21-person 1600 kg passenger lift 6 m/s serving high-rise floors 8 @ 900,000 | |||
| Goods lifts 3000 kg 3.5 m/s serving all floors above ground 2 @ 700,000 | |||
| Passenger lift serving car park, doubling as fire-fighting lift 1 @ 150,000 | |||
| Fire-fighting lifts serving all floors 2 @ 400,000 | |||
| Escalators serving reception and mezzanine 4 @ 110,000 | |||
| Car lift 2 @ 150,000 | |||
| Protective installations | 1,939,000 | 16.37 | 0.76% |
| Wet/dry riser installation, with pumps, etc 118,450 m2 @ 1 | |||
| Sprinkler installation: common bulk storage, split pump sets 118,450 m2 @ 12 | |||
| Hose reels including booster set 118,450 m2 @ 3 | |||
| Lightning protection 1 @ 45,000 | |||
| Communications installations | 2,026,000 | 17.10 | 0.79% |
| Fully addressable fire alarm, smoke detection, voice alarm and | |||
| public address systems, interfaced to building management system 118,450 m2 @ 14 | |||
| Primary containment for data and communications wiring 118,450 m2 @ 1 | |||
| Security: CCTV/detection systems to building perimeter and in car park Item @ 250,000 | |||
| Special Installations | 2,640,000 | 22.29 | 1.03% |
| Building management system 118,450 m2 @ 13 | |||
| Complete facade and atrium cleaning installations Item @ 1,000,000 | |||
| Communications mast Item @ 100,000 | |||
| Builder’s work in connection | 2,775,000 | 23.43 | 1.08% |
| Builder’s work in connection with services installations, | |||
| including machine bases, steel stacking framework for double-height | |||
| plant, firestopping, holes, chases, etc (allow 5% of services costs) Item @ 2,775,000 | |||
| Preliminaries and contingencies | 44,850,000 | 378.64 | 17.53% |
| Construction manager’s pre-construction staff costs Item @ 1,000,000 | |||
| Construction manager’s preliminaries, staff costs, overheads | |||
| and profit (allow 15%) Item @ 31,650,000 | |||
| Design reserve and construction contingency (allow 5%) Item @ 12,200,000 | |||
| Total for shell-and-core construction | 255,875,000 | 2160.18 | 100% |
| Category A fit-out | |||
| Element cost | cost/m2 gfa £ | % of total cost | |
| Based on net internal office area of 74,880 m2 | |||
| Wall finishes | 84,000 | 0.71 | 0.26% |
| Emulsion paint to external walls of cores and to internal columns 16,850 m2 @ 5 | |||
| Floor finishes | 4,568,000 | 38.56 | 14.12% |
| Medium-grade access floor; fire breaks; dust sealant 74,880 m2 @ 37 | |||
| Carpet tiles 74,880 m2 @ 24 | |||
| Ceiling finishes | 3,370,000 | 28.45 | 10.42% |
| Concealed grid metal tray suspended ceiling to office areas; | |||
| acoustic quilt and fire breaks 74,880 m2 @ 45 | |||
| Fittings | 70,000 | 0.59 | 0.22% |
| Allowance for statutory signage Item @ 70,000 | |||
| Space heating and air treatment | 9,435,000 | 79.65 | 29.17% |
| Extension of four-pipe fan coil installation into office areas including | |||
| distribution ductwork; fan coil units; grilles and diffusers; insulation; | |||
| condensate drainage; interface with building management system 74,880 m2 @ 126 | |||
| Electrical installation | 5,616,000 | 47.41 | 17.36% |
| Lighting and emergency lighting to office areas; | |||
| power to fan coil units; supply only floor boxes | |||
| (small power distribution excluded); earthing and bonding 74,880 m2 @ 75 | |||
| Communications installation | 1,123,000 | 9.48 | 3.47% |
| Final connections to fire, smoke detection, alarm and public address systems 74,880 m2 @ 15 | |||
| Protective installation | 1,198,000 | 10.11 | 3.70% |
| Extension of sprinkler installations into office areas (one head per 9 m2) 74,880 m2 @ 16 | |||
| Special installations | 824,000 | 6.96 | 2.55% |
| Extension of building management system into office areas 74,880 m2 @ 11 | |||
| Builder’s work in connection | 503,000 | 4.25 | 1.56% |
| Allowance for associated builder’s work (say 4% of services costs) Item @ 503,000 | |||
| Preliminaries and contingencies | 5,550,000 | 46.86 | 17.16% |
| Construction manager’s preliminaries, staff costs, | |||
| overheads and profit (allow 15%) Item @ 4,000,000 | |||
| Design reserve and construction contingency (allow 5%) Item @ 1,550,000 | |||
| Total for category A fit-out | 32,341,000 | 273.03 | 100% |