| Student accommodation | |||
| Element cost (£) | cost/m2 gfa (£) | % of total cost | |
| Substructure | 1640 | 72.29 | 7.22 |
| Piling, deep strip foundations and ground-bearing slab; reduced level dig, disposal | |||
| item @ 1,229,000 | |||
| Modules | 13,210 | 582.79 | 58.18 |
| Bedroom modules, fully furnished, complete with en-suite bathroom, including all services to final connections with below-ground installation | |||
| 750 @ 10,500 | |||
| Kitchen modules, fully fitted, including all services to final connections with below-ground installation | |||
| 125 @ 13,500 | |||
| Stair modules | |||
| 30 @ 11,500 | |||
| Envelope | 4130 | 182.28 | 18.20 |
| External walls – terracotta rainscreen; including allowances for framing and interfaces with modules | |||
| 17,000 m2 @ 140 | |||
| Roof – timber structure, roof tiles, rainwater goods | |||
| 6250 m2 @ 115 | |||
| Joinery generally | 190 | 8.24 | 0.82 |
| Internal and external doors, canopies | |||
| item @ 140,000 | |||
| Finishes generally | 1520 | 66.94 | 6.68 |
| Wall, floor and ceiling finishes to corridors only | |||
| item @ 88,000 | |||
| Ancillary buildings | 1400 | 61.77 | 6.17 |
| Allowance for conventionally constructed amenities buildings | |||
| item @ 1,050,000 | |||
| Contingencies | 620 | 27.35 | 2.73 |
| Allowance based on 3% | |||
| item @ 465,000 | |||
| Total construction cost – building only | 22,710 | 1001.66 | 100 |
| Reported costs are current in 1st quarter 2002, based on a location in south-east England. Preliminaries are included in the rates. The costs exclude site remediation costs, infrastructure and external works, professional fees and VAT | |||
| Amphion project | |||
| Element cost (£) | cost/m2 gfa (£) | % of total cost | |
| Substructure | 4500 | 53.29 | 9.37 |
| Strip foundations and ground bearing slab; reduced level dig, disposal | |||
| item @ 162,000 | |||
| Frame, upper floors and partitions | 9110 | 107.93 | 18.97 |
| Timber frame panels, external wall panels, upper floors, roof structure and internal partitions | |||
| item @ 328,100 | |||
| Roof | 2840 | 33.65 | 5.91 |
| Roof coverings; concrete roof tiles, rainwater goods | |||
| item @ 102,300 | |||
| External wall cladding | 5630 | 66.71 | 11.73 |
| Single skin outer brick wall | |||
| item @ 202,800 | |||
| Joinery generally | 6560 | 77.73 | 13.66 |
| Stairs | |||
| item @ 36,200 | |||
| Windows and external doors; timber; site finished | |||
| item @ 150,100 | |||
| Internal doors | |||
| item @ 50,000 | |||
| Finishes generally | 8910 | 105.49 | 18.54 |
| Wall, floor and ceiling finishes | |||
| item @ 320,700 | |||
| Furniture and fittings | 1540 | 18.19 | 3.20 |
| Fixtures and fittings generally | |||
| item @ 55,300 | |||
| Services generally | 8940 | 105.92 | 18.62 |
| Sanitary fittings | |||
| item @ 33,800 | |||
| Plumbing | |||
| item @ 89,800 | |||
| Heating and ventilation | |||
| item @ 126,500 | |||
| Electrical installation | |||
| item @ 71,900 | |||
| Total construction cost – building only | 48,030 | 568.91 | 100 |
| External works | 11,140 | 131.91 | – |
| Drainage, service trenches, lighting, drives, parking areas and paved areas, soft landscape, screen walls and fencing | |||
| item @ 401,000 | |||
| Adoptable works | 6970 | 82.57 | – |
| Roads, footpaths, sewers, street lighting and street furniture | |||
| item @ 251,000 | |||
| Service mains and connections | 3830 | 45.39 | – |
| item @ 138,000 | |||
| Overall construction cost | 69,970 | 828.78 | – |
| Reported costs are current in 1st quarter 2002, based on a location in southern England. Allowances for preliminaries and contingencies are included in the rates. The costs exclude site preparation costs, off-site works including services diversions, surveys, professional fees and VAT | |||