| Bus station cost breakdown | |
| Estimated final accounts | Cost £ |
| Hard and soft landscaping | 1,001,294 |
| Covered central island | 1,549,796 |
| Travel shop and supervisor’s office | 378,767 |
| Ancillary building containing toilets and stores | 149,079 |
| Drainage and external services | 251,200 |
| TOTAL | 3,330,136 |
| Elemental cost analysis: central island building | ||
| gifa: 937 m2 | Element cost £ | £/m2 gifa |
| Substructure | 82,734 | 88.30 |
| Superstructure | ||
| Frame | 165,630 | 176.77 |
| Roof | 187,805 | 200.43 |
| External walls | 442,806 | 472.58 |
| Group element total | 796,241 | 849.78 |
| Internal finishes | ||
| Floor finishes | 49,225 | 52.53 |
| Ceiling finishes | 54,493 | 58.16 |
| Group element total | 103,718 | 110.69 |
| Fittings and furnishings | 435,788 | 465.09 |
| Services | ||
| Disposal installations | 3,939 | 4.20 |
| Water installations | 3,254 | 3.47 |
| Electrical installations | 54,743 | 58.42 |
| Protective installations | 1,146 | 1.22 |
| Communication installations | 65,823 | 70.25 |
| Builder’s work in connection with services | 2,410 | 2.57 |
| Group element total | 131,315 | 140.13 |
| TOTAL | 1,549,796 | 1,653.99 |