| Elemental cost analysis (final costs) | |||
| (gross internal floor area 6452 m2) | Total cost (£) | Cost per m2 (£) | % of total cost |
| Demolition | 13 500 | 2.09 | 0.36 |
| Substructure and drainage | 1 029 564 | 159.58 | 27.78 |
| WC pods | 17 380 | 2.69 | 0.47 |
| Steelwork | 532 930 | 82.6 | 14.38 |
| Roof and wall cladding | 435 517 | 67.5 | 11.75 |
| Curtain walling, windows and doors | 172 550 | 26.74 | 4.66 |
| Roller and fire shutter doors | 84 704 | 13.13 | 2.29 |
| Internal blockwork | 47 752 | 7.4 | 1.29 |
| Fit-out | 240 315 | 37.25 | 6.48 |
| Signage | 4 948 | 0.77 | 0.13 |
| M&E installations | 644 841 | 99.95 | 17.4 |
| Dividing screens | 5 542 | 0.86 | 0.15 |
| Miscellaneous metalwork | 16 797 | 2.6 | 0.45 |
| Builders work in connection with services/firestopping | 63 648 | 9.87 | 1.72 |
| Hard landscaping | 100 671 | 15.6 | 2.72 |
| Soft landscaping | 12 423 | 1.93 | 0.34 |
| Preliminaries | 283 353 | 43.92 | 7.64 |
| Total cost | 3 706 435 | 574.49 | 100 |