| Hot rates: windows, doors and stairs | ||||
| Price movements | ||||
| Unit (£) | East Anglia (£) | Scotland (£) | Yorkshire and Humberside (£) | |
| Timber windows/rooflights | ||||
| Velux or equivalent pre-glazed red pine and aluminium-trimmed centre pivot roof window; 1140 × 1180 mm | item | 265 | 260 | 260 |
| Hardwood double-glazed vertically sliding sash and case windows with trickle vents; 1750 × 1200 mm | item | 480 | 475 | 475 |
| Plastic windows | ||||
| White PVCu double-glazed window unit; 1125 × 1125 mm | item | 200 | 200 | 198 |
| Timber doors – flush | ||||
| Lacquered sapele veneered domestic door; 826 × 2040 × 40 mm | item | 39 | 39 | 38 |
| Ply-faced solid core, external quality, for painting; 826 × 2040 × 44 mm | item | 72 | 71 | 70 |
| Ash veneered plywood-faced solid core; 926 × 2040 × 44 mm | item | 108 | 105 | 105 |
| Softwood door frames | ||||
| 140 × 38 mm jamb, plugged and screwed | m | 6.50 | 6.50 | 6.30 |
| Mastic pointing frames | m | 1.20 | 1.50 | 1.40 |
| Metal doors | ||||
| Steel single door with frame; 1810 × 2100 mm | item | 1075 | 1075 | 1075 |
| Plastic doors/hatches | ||||
| Sliding double-glazed patio doors with frames; 2025 × 2100 mm | item | 675 | 675 | 670 |
| Loft access door and frame; 740 × 550 mm | item | 60 | 60 | 55 |
| Metal stairs/balustrades | ||||
| Galvanised steel cat ladder; 3500 mm high | item | 500 | 500 | 500 |
| Isolated balustrade, galvanised mild steel, 1050 mm high, 48 mm diameter handrail, 32 mm diameter uprights at 400 mm centres, 20 mm diameter knee rail | m | 125 | 120 | 120 |
| General glazing | ||||
| Clear float laminated safety glass, 8 mm thick, in balustrade panels | m2 | 60 | 60 | 60 |
| Georgian wired polished plate; 6 mm thick | m2 | 60 | 60 | 60 |
| Key indicators | |
| % change over 12 months to March 1999 | |
| Retail price index | |
| Headline rate | +2.1 |
| All items excluding mortgage interest payments – government’s target index | +2.7 |
| All items excluding mortgage interest payments and indirect taxes | +1.7 |
| Industry | |
| Materials/fuel bought by manufacturing industry | –3.6 |
| – materials | –4.3 |
| – fuel | +1.0 |
| Materials/fuel bought by manufacturing industry other than food, beverages, petroleum and tobacco industries | –4.4 |
| Output prices of manufactured products | 0.5 |
| Output prices of manufactured products other than food, beverages, petroleum and tobacco industries | –0.6 |
| Construction industry | |
| Construction materials | –1.0 |
| Housebuilding materials | –0.2 |
| Machinery and equipment | +0.9 |
| Electrical machinery and apparatus | –2.6 |
| Commodities | |
| Aluminium | –15.3 |
| Copper | –12.3 |
| Oil | –3.5 |
| Source: Office for National Statistics | |
| Building, civil engineering and landscaping materials (% change) | |
| Powder-coated aluminium rainwater goods | +3 |
| Stainless steel reinforcement | –7 |
| Concrete blocks | +3 |
| Softwood windows and doors | +2 |
| Plaster/plasterboard | +1.5 |
| Plastisol roofing | –1 |
| Westmoreland roofing slates | +3 |
| Bitument macadam surfacing | +5 |
| Cast-iron rainwater goods | +3 |
| Clay drainage goods | +2 |
| Plastics drainage goods | +3 |
| Timber panel products | –4 |
| Ceramic tiles | –5 |
| Steel drainage products | –2 |
| Gas-fired boilers | +2 |
| Radiators | +3 |
| Tube fittings | –15 |
| Mechanical and electrical services and materials (% change) | |
| Expansion joints | +4 |
| Fans | +2.5 |
| Insulation | +5 |
| Clock systems | +1.5 |
| Fire-detection and alarm systems | +3 |
| Cabling trunking systems | +2 |
| Packages with the biggest cost changes | ||
| Index title | % change July 98-April 99 | |
| Upward movers | ||
| Stonework | +2 | |
| Windows and doors: steel | +4 | |
| Finishes: rigid tiles and terrazzo work | +2 | |
| Pipes and accessories: plastics | +3 | |
| Downward movers | ||
| Concrete: reinforcement | – 3.7 | |
| Metal: decking | – 8.4 | |
| Metal: miscellaneous | – 5.6 | |
| Cladding and covering: coated steel | – 6.5 | |
| Cladding and covering: aluminium | – 7.9 | |
| Cladding and covering: copper | – 8.9 | |
| Cladding and covering: glazed | – 3.5 | |
| Raised access floors | – 3.9 | |
| Pipes and accessories: copper | – 11.4 | |
| Employer’s NI contribution | |||
| 6 April 1998-5 April 1999 | 6 April 1999-5 April 2000 | ||
| Weekly earnings | % | Weekly earnings | % |
| up to £64 | nil | up to £83 | nil |
| £64-109.99 | 3 | ||
| £110-154.99 | 5 | more than £83 | 9.2 for contracted- |
| £155-209.99 | 7 | out contributions | |
| £210-485 | 10 | 12.2 on all earnings | |
| more than £485 | 10 | not contracted-out | |
| Dayworks | |||
| Operative | Pre 6 April effective from | Pre 6 April £/hour | From 6 April £/hour |
| Building craftsman | 3 August 1998 | 6.80 | 6.66 * |
| Building general operative | 3 August 1998 | 5.22 | 5.18 |
| Trained plumber | 24 August 1998 | 7.69 | 7.55 |
| Senior H&V craftsman (plus second welding skill) | 5 October 1998 | 9.09 | 8.98 |
| H&V mate (over 18) | 5 October 1998 | 5.99 | 5.98 |
| Approved electrician (national rate) | 4 January 1999 | 9.33 | 9.22 |
| Electrical senior apprentice (Stage 2 – first year) (national rate) | 5 October 1998 | 6.02 | 6.03 |
| Approved electrician (Scotland) | 4 January 1999 | 9.22 | 9.12 |
| Electrician (Scotland) | 4 January 1999 | 8.41 | 8.29 |
| * See below for build-up information | |||
| ** Definition of prime cost of daywork carried out under a building contract (RICS and Building Employers Confederation); definition of prime cost of daywork carried out under a heating, ventilating, air-conditioning, refrigeration, pipework and/or domestic engineering contract (RICS and Heating and Ventilating Contractors Association); definition of prime cost of daywork carried out under an electrical contract (RICS and Electrical Contractors Association). | |||
| Typical tender adjustments (%) | |||
| Building contracts | HVAC contracts | Electrical contracts | |
| Labour | 90 | 120-150 | 120-150 |
| Materials | 15-20 | 15 | 15 |
| Plant * | 10-30 | 10-15 | 10-15 |
| * based on RICS Schedule of Basic Plant Charges 1990 | |||
| Build-up of hourly rate for building craftsmen from 6 April 1999 | |||
| Time | Weekly rate | Cost (£) | |
| Basic pay | 47.8 weeks | £214.50 | 10 253.10 |
| Employer’s National Insurance contribution | 47.8 weeks | £16.04 | 766.71 |
| Construction Industry Training Board levy | 0.38% | 38.96 | |
| Holiday pay and benefits contribution | 47 weeks | £20.10 | 944.7 |
| Annual labour cost | 12 003.47 | ||
| Hourly labour rate | 1801.8 hours | 6.66 | |