| Cost information | ||
| Element | Total cost of element (£) | Cost/m2 (£) (gfa is 8107 m2) |
| substructure | 323 283 | 40 |
| frame | 96 332 | 12 |
| upper floors | 263 823 | 33 |
| roof | 643 674 | 79 |
| stairs | 82 001 | 10 |
| external walls | 1 229 841 | 152 |
| windows and external doors | 124 354 | 15 |
| internal walls and partitions | 292 221 | 36 |
| internal doors | 327 148 | 40 |
| wall finishes | 183 547 | 23 |
| floor finishes | 333 748 | 41 |
| ceiling finishes | 156 683 | 19 |
| painting and decorating | 83 612 | 10 |
| fittings and furnishings | 40 000 | 5 |
| sanitary appliances | 174 581 | 22 |
| mechanical installations | 2 730 000 | 337 |
| electrical installations | 1 148 138 | 142 |
| lift and conveyor installations | 206 183 | 25 |
| special installations | 488 250 | 60 |
| builders work in connection with services | 204 976 | 25 |
| external works | 169 264 | 21 |
| preliminaries | 1 383 237 | 171 |
| total | 10 684 898 | 1 318 |