| Capital costs for a typical 4000 m2 industrial unit | ||
| element cost £ | cost/m2 gifa £ | |
| Substructure | 206 100 | 51.54 |
| Excavate to reduce levels, disposal of excavated material from site | 22 000 | 5.5 |
| In situ concrete slab; granular sub base and so on; 35 KN/m2 | 127 900 | 31.98 |
| Reinforced concrete ground beams | 17 300 | 4.33 |
| Reinforced concrete column portal bases | 25 000 | 6.25 |
| Reinforced concrete column portal bases to offices | 4 100 | 1.03 |
| Facing brickwork below damp-proof course; 300 mm high | 9 800 | 2.45 |
| External walls | 100 000 | 25 |
| Blockwork inner skin to external walls of warehouse | 14 900 | 3.73 |
| Facing brickwork at low levels | 7 000 | 1.75 |
| Vertical sheet cladding, profiled metal cladding | 12 900 | 3.23 |
| Vertical sheet cladding; Ward’s Moduclad DW 1000 horizontal | ||
| flat panel cladding to suit additional height of building | 48 300 | 12.08 |
| Extra over vertical sheet cladding for fire protection | 1 900 | 0.48 |
| Curtain walling | 15 000 | 3.75 |
| Inner walls | 15 500 | 3.88 |
| Block main compartment wall | 9 300 | 2.33 |
| Fire lining to head of walls | 1 900 | 0.48 |
| Block walls to cores, reception and WCs | 4 300 | 1.08 |
| Floors | 11 000 | 2.75 |
| Precast concrete floor beams | 11 000 | 2.75 |
| Stairs | 6 200 | 1.55 |
| Steel cat ladder for roof access | 1 000 | 0.25 |
| Precast concrete staircase | 5 200 | 1.3 |
| Roof | 162 800 | 40.7 |
| Plastisol-coated profiled standing-seam metal-sheet roofing system; | ||
| 6° pitch; insulation; metal liner trays; 10% GRP profiled rooflights | 133 700 | 33.43 |
| Roof penetrations for services | 2 200 | 0.55 |
| Mansafe roof access system | 12 900 | 3.23 |
| Soffit to eaves | 14 000 | 3.5 |
| Frames | 163 800 | 40.95 |
| Steel portal frame including purlins and sheeting rails | 112 000 | 28 |
| Structural steel framing to offices | 12 100 | 3.03 |
| Fire protection and decoration to structural steelwork | 39 700 | 9.93 |
| External wall openings | 30 200 | 7.55 |
| Polyester powder-coated finished aluminium windows 1200 mm high | 20 700 | 5.18 |
| Cill boards and decoration | 700 | 0.18 |
| Electrically operated sectional overhead loading doors; | ||
| 3500 × 4500 mm; decoration; without vision panels | 5 300 | 1.33 |
| Double-skinned mild steel fire escape doors | 3 500 | 0.88 |
| Internal wall openings | 5 200 | 1.3 |
| Solid beech veneered internal single door to cores, WCs and so on | 5 200 | 1.3 |
| Balustrading | 12 000 | 3 |
| Stainless steel handrail and balustrade | 7 500 | 1.88 |
| Painted steel handrail and balustrade | 4 500 | 1.13 |
| Internal wall finishes | 11 200 | 2.8 |
| Two coats plaster; one mist and two full coats eggshell emulsion | 8 200 | 2.05 |
| Render and white glazed wall tiling (full height) | 800 | 0.2 |
| Paint to internal face of walls in warehouse and workshop | 2 200 | 0.55 |
| Floor finishes | 14 200 | 3.55 |
| Cement and sand screed; 75 mm thick | 3 500 | 0.88 |
| Carpet tiles; allow PC sum £15/m2 supply | 6 000 | 1.5 |
| Ceramic tiling and screed to reception | 1 500 | 0.38 |
| Ceramic tiling to WCs including screed and skirting | 800 | 0.2 |
| Softwood skirting; decoration | 1 500 | 0.38 |
| Ceramic tiled skirting to reception | 300 | 0.08 |
| Matwell; frame and mat | 600 | 0.15 |
| Stair finishes | 1 000 | 0.25 |
| Carpet tiles to treads of flight of stairs; nosings | 1 000 | 0.25 |
| Ceiling finishes | 7 900 | 1.98 |
| Suspended ceiling; 600 × 600 mm mineral fibre tiles; | ||
| exposed T-grid system; fire breaks | 7 700 | 1.93 |
| Suspended ceiling; 600 × 600 mm mineral fibre tiles; | ||
| exposed T-grid system; to WCs | 200 | 0.05 |
| Internal drainage | 21 900 | 5.48 |
| Soil and vent to WCs | 1 200 | 0.3 |
| Eaves and parapet gutters and fittings; | ||
| bituminious paint to inside surfaces | 16 400 | 4.1 |
| External aluminium rainwater pipes and fittings; | ||
| polyester powder-coated finish | 4 300 | 1.08 |
| Water supply | 3 600 | 0.9 |
| Cold water installation | 1 700 | 0.43 |
| Hot water installation | 800 | 0.2 |
| Local hot water heaters | 800 | 0.2 |
| Builders’ work | 300 | 0.08 |
| Space heating | 21 500 | 5.38 |
| Low-pressure hot water radiator heating to first-floor offices | 19 800 | 4.95 |
| Builders’ work | 1 700 | 0.43 |
| Ventilation | 9 500 | 2.38 |
| Mechanical ventilation to WCs | 9 000 | 2.25 |
| Builders’ work | 500 | 0.13 |
| Power supplies | 46 200 | 11.55 |
| Sub-mains distribution to first floor and reception | 5 900 | 1.48 |
| Twin switched socket outlets to cores/reception | 600 | 0.15 |
| Skirting trunking to offices | 9 800 | 2.45 |
| 600 × 600 mm recessed lighting to offices/reception | 14 200 | 3.55 |
| 600 × 600 mm lighting to WCs/cores | 2 100 | 0.53 |
| Emergency lighting to warehouse | 1 700 | 0.43 |
| Lightning protection | 5 700 | 1.43 |
| Power to overhead doors | 1 000 | 0.25 |
| Working drawings and manuals | 3 500 | 0.88 |
| Builders’ work | 1 700 | 0.43 |
| Lifts | 31 500 | 7.88 |
| Eight-person passenger lift | 26 000 | 6.5 |
| Lift pit base | 4 000 | 1 |
| Builders’ work | 1 500 | 0.38 |
| Security | 700 | 0.18 |
| Fire alarm conduit to offices | 700 | 0.18 |
| General fittings | 3 650 | 0.91 |
| Duct panel full height to WC | 1 200 | 0.3 |
| Vanity top/base unit | 1 250 | 0.31 |
| WC partition two-door | 1 200 | 0.3 |
| Sanitary fittings | 4 800 | 1.2 |
| Lavatory basins | 500 | 0.13 |
| WC suites | 600 | 0.15 |
| Urinals | 200 | 0.05 |
| Mirrors | 1 200 | 0.3 |
| Disabled WC/hand basin complete with grab rails and so on | 2 300 | 0.58 |
| General siteworks | 238 900 | 59.73 |
| Excavate to reduce levels; remove from site | 26 300 | 6.58 |
| Service yard and feeder road comprised of concrete; | ||
| reinforcement and granular sub-base | 125 000 | 31.25 |
| Car parking area comprising macadam paving | 28 000 | 7 |
| Pedestrian paving | 11 500 | 2.88 |
| Soft landscaping to planting beds | 25 600 | 6.4 |
| External watering points and landscaping maintenance | 2 000 | 0.5 |
| Steel painted bollards to loading doors | 1 400 | 0.35 |
| External lighting | 13 300 | 3.33 |
| External floodlight to goods door | 800 | 0.2 |
| Crossover works | 5 000 | 1.25 |
| Drainage | 96 200 | 24.05 |
| Drainage; pipework; surrounds; brick manholes; | ||
| trapped gullies; sewer connections | 96 200 | 24.05 |
| Installations | 13 400 | 3.35 |
| Water supply | 900 | 0.23 |
| 440 V electrical supply | 2 600 | 0.65 |
| 100 mm diameter PVCu duct | 3 200 | 0.8 |
| Gas supply | 1 500 | 0.38 |
| Service trenches | 5,200 | 1.3 |
| Preliminaries | 222 000 | 55.5 |
| Preliminaries | 200 000 | 50 |
| Inflation to start on site | 22 000 | 5.5 |
| Total | 1 460 950 | 365.24 |
| Maintenance costs for a 4000m2 industrial unit over 25 years | ||||||
| Basic project | Project typical of current market trends | |||||
| Specification | Capital cost | Maintenance costs/year | Specification | Capital cost | Maintenance costs/year | Comments |
| Roof | ||||||
| Profiled steel sheet | 112 000 | 9 000 | Standing seam roof | 133 700 | 7 500 | Maintenance costs for basic project exclude potential disruption to tenants’ operation caused by effect of roof leaks. |
| Insulation (0.45 U-value) | 16 000 | 4 200 | Insulation (0.25 U-value) | 32 000 | 3 700 | Improved insulation is particularly attractive to tenants of larger units and those with specific heating requirements. |
| External walls | ||||||
| Brickwork cavity wall | 44 000 | 120 | Profiled steel sheet composite cladding panel | 13 000 | 1 100 | Damage to brickwork is more difficult to match, which can have longer-term effects on building aesthetics. |
| Gutters | ||||||
| Valley gutter | 9 500 | 275 | Eaves gutter | 16 500 | 150 | Leaking valley gutters can have long-term corrosion implications on steel frames |
| Protection | ||||||
| No protection to openings | – | 600 | Steel bollards to door openings, high-profile kerbs to vulnerable areas | 4 400 | 100 | Bollards may need replacing. |
| External surfaces | ||||||
| 60 mm block paviours | 15 000 | 160 | 80 mm block paviours | 17 500 | 0 | Replacement of paviours to damaged areas can cause considerable disruption to tenants’ operations. |
| Landscaping | ||||||
| Low-quality | 15 000 | 1 700 | High-quality low-maintenance | 26 000 | 1 400 | Low-quality landscaping may need to be replaced more regularly. |