All the latest updates on building safety reform



| Elemental cost analysis | |
| Size | 10 608 m² |
| Seats | 824 |
| Total cost (£) | 7.143m |
| Element | £/m² |
| Demolition | 4.60 |
| Superstructure | 113.13 |
| Internal finishes | 56.56 |
| Fittings and furniture | 9.43 |
| Services | 172.37 |
| Preliminaries and insurance | 56.57 |
| Specialist theatre equipment | 115.37 |
| Other | 145.32 |
| Total | 673.35 |
| Typical maintenance costs for a 1200-seat theatre | |
| £/100 m² a year | |
| Cleaning | 800 |
| Utilities | 1200 |
| Administrative | 600 |
| Total | 2600 |
| BMI estimates using gross internal floor area | |
| Comparative elemental cost analysis (£/m² ) | |||
| Savoy Theatre¹ | Victoria Hall² | Stratford Circus² | |
| Demolition | 230.43 | – | – |
| Substructure | 134.26 | 64.65 | 83.30 |
| Superstructure | 1062.26 | 326.18 | 600.25 |
| Internal finishes | 682.61 | 70.67 | 122.75 |
| Fittings and furniture | 177.78 | 77.98 | 80.00 |
| Services | 819.37 | 406.10 | 421.70 |
| Preliminaries and insurance | 941.21 | 126.50 | 131.25 |
| External works | 13.09 | – | 21.85 |
| Specialist theatre equipment | 192.28 | 70.00 | 187.10 |
| Total | 4253.29 | 1142.08 | 1648.20 |
| ¹ Original 1993 costs inflated by 35% | |||
| ² Original 1997 costs inflated by 15% | |||