| Summary of contract value | |
| £ | |
| Shell refurbishment contract total (gifa 9850 m2) | 2 042 452 |
| Asbestos removal | 11 100 |
| Stripping out | 27 247 |
| Demolitions/structural alterations | 298 703 |
| Basement ramp | 32 292 |
| Timber preservation | 4 037 |
| Tanking/waterproofing | 16 146 |
| External wall refurbishment | 61 557 |
| Roof works | 417 780 |
| External walling | 95 867 |
| Internal walls | 12 110 |
| Floor structures | 13 119 |
| Lifts and stairs | 179 625 |
| Windows and doors | 221 000 |
| Finishes | 33 301 |
| Sitework | 56 511 |
| Drainage | 77 703 |
| Service entries and connections | 29 265 |
| Service installations | 25 228 |
| Dry risers | 18 164 |
| Lightning protection | 8 073 |
| Bird deterrent measures | 5 046 |
| Preliminaries | 330 966 |
| Provisional sums | 67 612 |
| Fit-out contracts total | 1 520 736 |
| 12 apartments (gifa 1565 m2) | 666 727 |
| Design office (gifa 1082 m2) | 369 733 |
| Lettable offices (gifa 1548 m2) | 384 275 |
| Total contract value | 3 463 188 |