| Projected refurbishment costs | |||
| capital cost, 1-10 years (£) | capital cost, 10-30 years (£) | ||
| Superstructure | |||
| Total | 319 600 | 301 700 | |
| Internal finishes | |||
| Total | 129 200 | 171 000 | |
| Fittings | |||
| Total | 25 000 | 34 800 | |
| M&E installations | |||
| Total | 599 900 | 249 500 | |
| Servicing | |||
| Total | 99 200 | 198 400 | |
| Total expenditure | 1 172 900 | 955 400 | |
| Total expenditure | 333/m2 | ||
| Gross floor area: 3518 m2 | |||
| Number of pupils: 3360.0 | |||
| Projected refurbishment costs | |||
| capital cost, 1-10 years (£) | capital costs, 10-30 years (£) | ||
| Superstructure | |||
| Total | 242 600 | 102 100 | |
| Internal finishes | |||
| Total | 50 100 | 100 500 | |
| Fittings | |||
| Total | 9 000 | 21 800 | |
| M&E installations | |||
| Total | 394 000 | 232 600 | |
| Servicing | |||
| Total | 49 600 | 99 200 | |
| Total expenditure | 745 300 | 556 200 | |
| Total expenditure | 666/m2 | ||
| Gross floor area: 1119 m2 | |||
| Number of pupils: 243 | |||
| Construction Costs | |||||
| Gross floor area: 11 791 m2 | |||||
| Number of pupils: 1450 (by 2004) | |||||
| total costs (£) | cost/m2 (£) | cost/pupil (£) | |||
| Demolition | |||||
| Total | 300 000 | 25.44 | 206.90 | ||
| Substructure | |||||
| Total | 764 625 | 64.85 | 527.33 | ||
| Superstructure | |||||
| External walls | 451 021 | 38.25 | 311.05 | ||
| Internal walls | 450 969 | 38.25 | 311.01 | ||
| Upper floors | 336 987 | 28.58 | 232.40 | ||
| Stairs | 33 000 | 2.80 | 22.76 | ||
| Roof | 567 984 | 48.17 | 391.71 | ||
| Frame | 590 493 | 50.08 | 407.24 | ||
| Completion | |||||
| External wall openings | 846 135 | 71.76 | 583.54 | ||
| Internal wall openings | 90 711 | 7.69 | 62.56 | ||
| Balustrading | 42 145 | 3.57 | 29.07 | ||
| Finishes | |||||
| Internal wall finishes | 318 440 | 27.00 | 219.61 | ||
| Floor finishes | 548 046 | 46.48 | 377.96 | ||
| Stair finishes | 15 606 | 1.32 | 10.76 | ||
| Ceiling finishes | 299 256 | 25.38 | 206.38 | ||
| Roof finishes | 617 496 | 52.37 | 425.86 | ||
| Mechanical services | |||||
| Total | 1 430 248 | 121.30 | 986.38 | ||
| Electrical services | |||||
| Total | 1 187 927 | 100.75 | 819.26 | ||
| Fixed fittings | |||||
| Total | 48 000 | 4.07 | 33.10 | ||
| Siteworks | |||||
| Total | 1 516 496 | 128.61 | 1 045.86 | ||
| Total direct costs | |||||
| Total | 10 455 585 | 886.75 | 7 210.74 | ||
| Total | 17 000 000 | ||||
| including school equipment, preliminaries, consultants’ fees, contingency, overheads and profits | |||||
| What a typical primary school should cost to maintain | ||
| Typical occupancy costs* | ||
| school 1 £/100m2 | school 2 £/100m2 | |
| Decorations | 344 | 329 |
| Internal | 302 | 222 |
| External | 42 | 107 |
| Fabric | 526 | 579 |
| External walls | 21 | 20 |
| Roof | 107 | 163 |
| Internal walls | 6 | 0 |
| Windows and external doors | 5 | 13 |
| Internal doors | 7 | 2 |
| Wall finishes | 20 | 0 |
| Floor finishes | 238 | 207 |
| Ceiling finishes | 5 | 0 |
| Fittings | 48 | 57 |
| Fabric wear and tear | 70 | 117 |
| Services | 1 266 | 1 523 |
| Sanitary appliances | 32 | 35 |
| Disposal installation | 22 | 28 |
| Water installation | 42 | 55 |
| Heating and ventilating | 530 | 630 |
| Electrical installation | 205 | 274 |
| Communications installation | 126 | 168 |
| Special installations | 290 | 306 |
| Services wear and tear | 20 | 26 |
| Cleaning | 978 | 1 259 |
| Windows | 19 | 92 |
| External services | 46 | 92 |
| Internal | 912 | 1075 |
| Utilities | 421 | 421 |
| Gas | 179 | 179 |
| Electricity | 133 | 133 |
| Water rates | 62 | 62 |
| Effluent/drainage charges | 47 | 47 |
| Administrative costs | 1 020 | 1 337 |
| Laundry | 24 | 32 |
| Porterage | 216 | 287 |
| Rubbish disposal | 86 | 115 |
| Property management | 647 | 862 |
| Structural inspections | 47 | 40 |
| Overheads | 1 153 | 1 153 |
| Property insurance | 152 | 152 |
| Rates | 1 001 | 1 001 |
| Total occupancy cost | 5 707 | 6 601 |
| External works | 129 | 147 |
| Repairs and decoration | 35 | 22 |
| External services | 20 | 19 |
| Cleaning | 35 | 75 |
| Gardening | 36 | 27 |
| Wear and tear | 2 | 4 |
| Total including external works | 5 836 | 6 748 |
| *Data from the RICS Building Maintenance Information report Occupancy Costs for Typical Primary Schools. | ||