| Base building, air-conditioned office | |
| Basic information | |
| Gross internal floor area | 12,000 m2 |
| Construction | Steel frame of 44 kg/m2 |
| Substructure | 200 mm ground-bearing slab |
| Roof | Pitched, “Sarna” single membrane proprietary roofing system with parapets |
| External walls | Mostly reconstituted stone wall cladding with 20% is polyester powder coated aluminium curtain-walling, fully glazed to clear height with double-glazed low-emissivity glass |
| Window frames | Aluminium |
| Windows | Double-glazed, low-emissivity glass; non-opening |
| Air-conditioning | fan-coil units |
| Lifts | Four passenger and two goods |
| Capital costs (£) (excluding fees) | |
| Substructure | 652,246 |
| Structure | 1,884,274 |
| External envelope | 2,212,538 |
| Internal divisions | 549,591 |
| Finishings and fittings | 2,450,866 |
| Mechanical | 3,503,101 |
| Electrical and communications | £1,701,463 |
| Lifts | 855,581 |
| Preliminaries, overheads and profit | 1,554,701 |
| Total | 17,343,000 |
| Net present costs for energy consumption (£) | |
| Space heating | 3,779 |
| Cooling and fans | 20,753 |
| Lighting | 22,000 |
| Other energy costs | 42,850 |
| Total (over 30-year period) | 89,385 |
| Net present costs (£) of maintenance and replacement over 30 years | |
| (limited to just the main elements that are changed) | |
| Roof edge and parapet gutter | 3,393 |
| Wall cladding | 26,840 |
| Curtain walling | 56,673 |
| Windows and brise soleil | 168,352 |
| Heat source | 287,371 |
| Air-conditioning | 1,292,772 |
| Ventilation | 728,460 |
| Stand-by generator | 143,990 |
| Light fittings | 365,504 |
| Total | 2,993,912 |
| Net present cost for base building | |
| (does not include soft FM items such as cleaning and rates) | |
| TOTAL | 20,426,297 |