| Costs | |||
| element cost | cost/m2 gfa £ | % of total cost | |
| Substructure | 923,700 | 109.51 | 6.67% |
| 450 mm diameter reinforced concrete piling 1955 m2 @ 165 | |||
| Reinforced concrete slab to basement area (565 m2) and ground floor with vapour barrier, insulation; underslab ducts and drainage 1955 m2 @ 165 | |||
| Extra for formation of lift pits Item @ 17,000 | |||
| Reinforced concrete retaining walls to basement, including temporary sheet piling; blockwork lining wall 450 m2 @ 370 | |||
| Allowance for excavating basement and disposal of materials; breaking out obstructions; dewatering 1900 m3 @ 50 | |||
| Frame and upper floors | 1,434,000 | 170.01 | 10.36% |
| Reinforced concrete frame, 7.2 × 7.2 m grid; 200 mm thick flat slab; insitu concrete shear walls 8435 m2 @ 170 | |||
| Roof | 214,400 | 25.42 | 1.55% |
| Inverted roof coverings, polymeric roof coverings, insulation; flashings and copings 1955 m2 @ 80 | |||
| Mansafe system Item @ 15,500 | |||
| Extra for polycarbonate rooflights; 800 diameter; flashings 15 @ 1,100 | |||
| Allowance for entrance canopies Item @ 26,000 | |||
| Stairs | 354,000 | 41.97 | 2.56% |
| Precast reinforced concrete stair cases; including fine smooth finish to exposed surfaces 6 @ 10,000 | |||
| Balustrades, 1.1 m high, glazed with profiled timber handrails; average rate used 665 m @ 400 | |||
| Profiled timber handrails 150 m @ 120 | |||
| Miscellaneous metalwork; cat ladders; open mesh flooring in risers and so on Item @ 10,000 | |||
| External walls, windows and doors | 1,525,700 | 180.88 | 11.02% |
| Aluminium faced multicoloured curtain walling; sealed double-glazed units; insulated composite cladding panels; secondary steel supports and internal proprietary liner panel 2520 m2 @ 320 | |||
| Coloured render system on mesh, insulation, dpm and metsec backing wall 1260 m2 @ 210 | |||
| Aluminium framed windows 95 m2 @ 360 | |||
| Perforated clay tile rain screen cladding complete including vertical and horizontal support rails 1300 m2 @ 190 | |||
| Entrance door unit; aluminium-framed glazed doors; automatic operation 2 @ 16,000 | |||
| External doors; aluminium framed; polyester coated; to match windows 10 @ 3,100 | |||
| Free-standing screens to roof plant; louvre panels as required 650 m @ 170 | |||
| Internal walls and partitions | 600,000 | 71.13 | 4.33% |
| Concrete blockwork; head restraints, movement joints 2000 m2 @ 45 | |||
| Plasterboard partitions; two layers of 12.5 mm wall board to both sides; including 25 mm insulation and skim coat finish 7350 m2 @ 55 | |||
| Internal glazed screens; blinds 225 m2 @ 470 | |||
| Internal doors | 424,800 | 50.36 | 3.07% |
| Flush doors; beech veneer; fire rated; solid core; veneered frame; vision panel and ironmongery; average rate for single leaf 325 @ 850 | |||
| Glazed doors and screens; fire-rated; frames, fittings and ironmongery; average rate for double door in opening 2550 mm high 22 @ 3,000 | |||
| Riser cupboard doors; beech veneer; fire rated 66 @ 1,250 | |||
| Wall finishes | 174,000 | 20.63 | 1.26% |
| Emulsion paint to wall surfaces generally 17250 m2 @ 3 | |||
| Ceramic wall tiling 150 × 150 mm 900 m2 @ 50 | |||
| Single layer plasterboard dry lining 12.5 mm thick, to blockwork or metal studs 5150 m2 @ 15 | |||
| Floor finishes | 496,200 | 58.83 | 3.58% |
| Screed; latex self levelling screed 15 to 25 mm thick 8435 m2 @ 12 | |||
| Ceramic floor tiling 600 × 600 mm to ground floor atrium 435 m2 @ 100 | |||
| Non slip vinyl sheet flooring; skirtings 315 m2 @ 36 | |||
| Linoleum sheet; skirtings 1100 m2 @ 41 | |||
| Carpet; softwood skirtings 5500 m2 @ 42 | |||
| Carpet and nosing to stair cases serving ground to third floors 4 @ 11,000 | |||
| Allowance for entrance barrier matting Item @ 20,000 | |||
| Ceiling finishes | 276,400 | 32.77 | 2.00% |
| Suspended ceilings; 600 × 600 mm clip in metal tiles 4170 m2 @ 40 | |||
| Plasterboard MF suspended ceilings and bulkheads; generally 1280 m2 @ 47 | |||
| Plaster to soffit of reinforced concrete slabs 1900 m2 @ 16 | |||
| Painting to plasterboard ceilings and bulkheads; generally 3180 m2 @ 6 | |||
| Furniture and fittings | 563,600 | 66.82 | 4.07% |
| Supply and install group one medical equipment (fixed furniture); | |||
| fit only group two and three medical equipment (loose furniture): | |||
| Reception area, desks and fixed furniture (average cost used) 13 @ 8000 | |||
| Cafe, servery counter and fixed furniture, catering equipment by others 2 @ 9000 | |||
| Waiting area 13 @ 1300 | |||
| Consulting room 60 @ 1600 | |||
| Treatment room 18 @ 1100 | |||
| Podiatary 3 @ 3100 | |||
| Dentistry 4 @ 25,000 | |||
| Audiology 2 @ 30,000 | |||
| Family room 12 @ 300 | |||
| Office room 34 @ 200 | |||
| Classroom 4 @ 900 | |||
| Meeting room 14 @ 60 | |||
| WC 27 @ 400 | |||
| Records/store 12 @ 500 | |||
| Utility room 9 @ 2000 | |||
| Allowance for additional fittings and furniture Item @ 90,000 | |||
| Sanitaryware | 166,000 | 19.68 | 1.20% |
| Sanitaryware generally 200 @ 830 | |||
| Disposal installations | 98,500 | 11.68 | 0.71% |
| Waste, soil and vent pipework 200 @ 330 | |||
| Extra for lift sump pumps Item @ 7200 | |||
| Rainwater installation 8435 m2 @ 3 | |||
| Hot and cold water installations | 335,200 | 39.74 | 2.42% |
| Cold water plant room installation; storage and booster unit 8435 m2 @ 6 | |||
| Hot water plant room installation; gas-fired water heaters, pumps and so on 8435 m2 @ 11 | |||
| Hot and cold water distribution pipework, insulation 8435 m2 @ 18 | |||
| Allowance for water treatment Item @ 40,000 | |||
| Space heating, air treatment and ventilation | 1,527,000 | 181.03 | 11.03% |
| Chilled water plant room installation; air cooled chiller; pumps, pipework distribution in plant rooms and risers Item @ 210,000 | |||
| LTHW plant room installation; boiler and flue; pumps, pipework distribution in plant rooms and risers Item @ 79,000 | |||
| Air-handling units; total combined capacity 10 m3/s; duct mounted heating and cooling batteries Item @ 83,000 | |||
| Chilled water distribution; pipework; valves; insulation, trace heating 3900 m2 @ 55 | |||
| LTHW heating; LST panels and trench heaters; pipework; valves; insulation 8435 m2 @ 31 | |||
| Air curtains and door heaters; generally Item @ 11,000 | |||
| Supply and extract ductwork installation serving active chilled beams 3900 m2 @ 43 | |||
| Extra for enhanced attenuation measures in ductwork Item @ 16,000 | |||
| Active chilled beam installation 3900 m2 @ 60 | |||
| Thermal insulation to ductwork 8435 m2 @ 18 | |||
| Allowance for packaged cooling systems to IT rooms Item @ 10,000 | |||
| Allowance for dedicated ventilation systems (7 systems) Item @ 21,000 | |||
| Dirty extract system 8435 m2 @ 8 | |||
| Electrical installations | 945,100 | 112.05 | 6.83% |
| Incoming supply and main LV panel Item @ 48,000 | |||
| Submains distribution, busbars in risers, distribution boards and isolators; including electrical supplies to main plant 8435 m2 @ 20 | |||
| Lighting: standard luminaires, wiring, containment, accessories 8435 m3 @ 38 | |||
| Allowance for emergency lighting 8435 m2 @ 6 | |||
| Allowance for external lighting Item @ 28,000 | |||
| General small power, including cabling, trunking and socket outlets 8435 m2 @ 35 | |||
| Allowance for standby power and UPS Item @ 34,000 | |||
| Gas installations | 11,000 | 1.3 | 0.08% |
| Incoming gas supply, including steel pipework, valves and so on Item @ 11,000 | |||
| Lift installations | 136,000 | 16.12 | 0.98% |
| Electric traction lift; 10 person; serving 4 floors 2 @ 30,000 | |||
| Electric traction lift; 10 person; serving 6 floors 2 @ 38,000 | |||
| Protective installations | 20,600 | 2.44 | 0.15% |
| Lightning protection system Item @ 8000 | |||
| Earthing and bonding Item @ 12,600 | |||
| Communication installations | 625,800 | 74.19 | 4.52% |
| Data and telephone pathway and cable infrastructure 8435 m2 @ 31 | |||
| Fire detection and alarm system 8435 m2 @ 12 | |||
| Security system; access control and intruder detection; wiring and equipment 8435 m2 @ 14 | |||
| CCTV system Item @ 31,000 | |||
| Patient call system; LED signboards Item @ 71,000 | |||
| Public address system Item @ 10,000 | |||
| Induction loop system Item @ 19,000 | |||
| Video/display monitor system in public areas Item @ 14,000 | |||
| Specialist installations | 378,300 | 44.85 | 2.73% |
| Building management and automatic control systems 8435 m2 @ 42 | |||
| Gas scavenging systems to dental rooms Item @ 11,000 | |||
| Compressor and vacuum installation to dental rooms Item @ 13,000 | |||
| Builder’s work in connection | 102,000 | 12.09 | 0.74% |
| Forming holes, chases and so on | |||
| Allowance @ 2.5% Item @ 102,000 | |||
| Preliminaries and contingencies | 2,513,000 | 297.93 | 18.14% |
| Management costs, site establishment and site supervision | |||
| Contractor's preliminaries, overheads and profit @ 18% Item @ 2,040,000 | |||
| Testing and commissioning of building services installations Item @ 70,000 | |||
| Contractor's contingency @ 3% Item @ 403,000 | |||
| Total construction cost – building only | 13,845,300 | 1641.43 | 100.00% |