| Sample of recent tender return costs | |||
| Pile type | Pile length (m) | Diameter (mm) | Pile cost (£) |
| Independent cast insitu reinforced concrete, bored | 15 | 300 | 200–250 |
| 15 | 350 | 275–300 | |
| 15 | 450 | 475–525 | |
| 20 | 350 | 375–425 | |
| 20 | 450 | 625–700 | |
| 30 | 750 | 1550-1750 | |
| 35 | 1000 | 7000–7500 | |
| Secant reinforced concrete wall, bored | 20 | 800 | 1900–2100 |
| 20 | 600 | 1750–2000 | |
| Precast concrete driven piles | 15 | 340 | 210–330 |
| 15 | 380 | 325–350 | |
| 15 | 430 | 475–500 | |
| Costs assume the placement of more than 100 piles | |||