- News

All the latest updates on building safety reformRegulations latest
- Focus

All the latest updates on building safety reform



| Cost of shell-and-core construction | |||
| element cost | cost/m² GFA £ | % of total cost | |
| Substructure | 403,000 | 66.61 | 8.06 |
| Excavation, footings, column bases, filling to levels, ground slab 3100 m² @ 130 | |||
| Frame and upper floors | 661,500 | 109.34 | 13.23 |
| Structural steelwork; UB and UC sections 300 t @ 1,400 | |||
| Composite slab, metal deck and insitu concrete 2900 m² @ 60 | |||
| Fire protection to steelwork item @ 50,000 | |||
| Allowance for miscellaneous works item @ 17,500 | |||
| Roof | 639,500 | 105.7 | 12.79 |
| Insitu concrete roof slab; metal deck and insitu concrete 3080 m² @ 60 | |||
| Insitu concrete rooflight upstand walls 120 m² @ 160 | |||
| Timber roof trusses item @ 60,000 | |||
| Monopitch roof, coated aluminium roof cladding, including purlins, trims, cappings, insulation 1780 m² @ 100 | |||
| Flat roof, asphalt, including insulation, trims, skirtings, flashings, linings to gutters, paving slabs 1500 m² @ 90 | |||
| Mansafe system item @ 12,500 | |||
| Rooflights 100 m² @ 500 | |||
| Stairs | 108,500 | 17.93 | 2.17 |
| Main steel internal staircases; handrails and balustrades (rate per flight) 4 @ 8,000 | |||
| Steel external staircases; handrails, balustrades, framing (rate per flight) 4nr @ 10,000 | |||
| Atrium balustrading 45 m @ 700 | |||
| Miscellaneous metalwork in shafts and risers Item @ 5,000 | |||
| External walls, windows and doors | 820,200 | 135.57 | 16.4 |
| Coated aluminium double glazed curtain walling 150 m² @ 375 | |||
| Extra for fire escape doors 8 @ 1,000 | |||
| Coated aluminium double glazed window system 850 m² @ 350 | |||
| Solar shading; fixed aluminium louvres 300 m @ 300 | |||
| Glazed main double entrance doors @ 6,000 | |||
| Aluminium wall cladding to roof level plant etc. 610 m² @ 45 | |||
| Render on blockwork, insulation and boarding 550 m² @ 160 | |||
| Facing brickwork in cavity walls 690 m² @ 150 | |||
| Facing brick cladding to columns 675 m² @ 100 | |||
| Miscellaneous masonry item @ 70,000 | |||
| Internal walls and partitions | 219,200 | 36.23 | 4.38 |
| Blockwork 1200 m² @ 50 | |||
| Drywall partition; 1 hour FR 570 m² @ 60 | |||
| Hardwood glazed screens; 1 hour FR 180 m² @ 500 | |||
| WC cubicles Item @ 35,000 | |||
| Internal doors | 98,000 | 16.2 | 1.96 |
| Hardwood doors and frames; stainless steel ironmongery 80 @ 1,100 | |||
| Allowance for fire containment in common areas item @ 10,000 | |||
| Wall finishes | 66,400 | 10.98 | 1.33 |
| Emulsion paint to wall surfaces generally item @ 40,000 | |||
| Plasterboard to cores and common areas 1650 m² @ 16 | |||
| Floor finishes | 75,200 | 12.43 | 1.5 |
| Screeds to cores and common areas; 150 thick to make up levels 640 m² @ 20 | |||
| Carpet tiling to common areas 170 m² @ 30 | |||
| Ceramic tiling to cores and common areas 470 m² @ 90 | |||
| Floor finishes to internal stairs Item @ 5,000 | |||
| Entrance matting 2 @ 5,000 | |||
| Ceiling finishes | 52,500 | 8.68 | 1.05 |
| Plasterboard ceiling and bulkheads; to core and common areas 1050 m² @ 50 | |||
| Furniture and fittings | 38,000 | 6.28 | 0.76 |
| Granite vanitary units item @ 27,000 | |||
| Glass surrounds to vanitary units item @ 5,000 | |||
| Miscellaneous architectural metalwork item @ 6,000 | |||
| Sanitary fittings | 24,200 | 4 | 0.48 |
| Sanitaryware and fittings; allowance 6050 m² @ 4 | |||
| Disposal Installations | 30,300 | 5.01 | 0.61 |
| Waste, soil and vent pipework 6050 m² @ 2 | |||
| Rainwater installation 6050 m² @ 3 | |||
| Hot and cold water installations | 67,300 | 11.12 | 1.35 |
| Hot and cold water pipework to landlord's areas including mains water service 6050 m² @ 5 | |||
| Hot water distribution pipework in plant rooms item @ 22,000 | |||
| Roof-mounted condensing boiler item @ 15,000 | |||
| Space heating air treatment and ventilation | 398,000 | 65.79 | 7.96 |
| Air handling units, chillers; ductwork, pipework, insulation 6050 m² @60 | |||
| Toilet extract ventilation item @ 15,000 | |||
| Cooling and ventilation installations to common areas item @ 20,000 | |||
| Electrical installation | 275,900 | 45.6 | 5.52 |
| Mains and sub-mains distribution 6050 m² @ 20 | |||
| Small power to landlord's areas 975 m² @ 15 | |||
| Electrical supplies to mechanical plant item @ 17,500 | |||
| Lighting to landlord's areas 975 m² @ 50 | |||
| External feature lighting item @ 5,000 | |||
| External lighting generally item @ 65,000 | |||
| Electric trench heating to common areas Item @ 4,000 | |||
| Gas installations | 10,000 | 1.65 | 0.2 |
| Incoming gas supply item @ 10,000 | |||
| Lift installations | 25,000 | 4.13 | 0.5 |
| Ten-person hydraulic lift serving two floors 1 @ 25,000 | |||
| Protective installations | 8,500 | 1.4 | 0.17 |
| Lightning protection item @ 6,000 | |||
| Earthing and bonding item @ 2,500 | |||
| Communication installations | 36,300 | 6 | 0.73 |
| Fire alarm and smoke detection 6050 m² @ 5 | |||
| Disabled WC alarm system item @ 2,000 | |||
| Allowance for containment item @ 4,000 | |||
| Specialist installations | 90,800 | 15.01 | 1.82 |
| BMS controls 6,050 m² @ 15 | |||
| Builder’s work in connection | 10,000 | 1.65 | 0.2 |
| Forming holes and chases etc. Allowance @ 1% Item @ 10,000 | |||
| Preliminaries | 841,700 | 139.12 | 16.83 |
| Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% Item @ 702,000 | |||
| Testing and commissioning of building services installations Item @ 15,000 | |||
| Allowance for design reserve @ 3% Item @ 124,700 | |||
| Total construction cost: building only | 5,000,000 | 826.43 | 100 |
| (Square metre rate based on GIFA) | |||
| Cost of fit-out to category A | |||
| element cost | cost/m² GFA £ | % of total cost | |
| Wall finishes | 75,700 | 14.84 | 4.95 |
| Emulsion paint to walls; generally Item @ 20,000 | |||
| Plasterboard lining 740 m2 @ 65 | |||
| Plasterboard column casings 80 @ 95 | |||
| Floor finishes | 245,600 | 48.16 | 16.05 |
| Raised access floors; medium grade 5100 m2 @ 28 | |||
| Carpet tiles 5100 m2 @ 18 | |||
| Softwood skirtings; painted 1100 m @ 10 | |||
| Ceiling finishes | 140,500 | 27.55 | 9.18 |
| Mineral fibre tile suspended ceiling; exposed grid 5100 m2 @ 20 | |||
| Bulkheads and margins 550 m @ 70 | |||
| Space heating, air treatment and ventilation | 510,000 | 100 | 33.33 |
| Four pipe fancoils; hot and cold water distribution, ductwork and flexible connections, grilles and diffusers; power supply to FCUs 5100 m2 @ 100 | |||
| Electrical installation | 255,000 | 50 | 16.67 |
| Lighting, emergency lighting and lighting control 5100 m2 @ 35 | |||
| Small power 5100 m2 @ 15 | |||
| Protective installations | 3,000 | 0.59 | 0.2 |
| Earthing and bonding item @ 3,000 | |||
| Communication installations | 25,500 | 5 | 1.67 |
| Fire detection and alarm system 5100 m2 @ 5 | |||
| Builder’s work in connection | 8,000 | 1.57 | 0.52 |
| Forming holes and chases etc. Allowance @ 1% Item @ 8,000 | |||
| Preliminaries | 266,700 | 52.29 | 17.43 |
| Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% Item @ 213,700 | |||
| Testing and commissioning of building services installations Item @ 15,000 | |||
| Allowance for design reserve @ 3% Item @ 38,000 | |||
| Total cost: category A fit-out only | 1,530,000 | 300 | 100 |
| (Square metre rate based on NIFA) | |||
| Cost of external works | |||
| element cost | cost/m² GFA £ | % of total cost | |
| Site works | 506,000 | 83.64 | 56.86 |
| Concrete block pavings 6100 m² @ 35 | |||
| Granite sett pavings 1250 m² @ 90 | |||
| Precast concrete paving slabs 970 m² @ 40 | |||
| Granite chippings 665 m² @ 30 | |||
| Precast concrete edgings 100 m @ 10 | |||
| Precast concrete kerbs 1490 m @ 30 | |||
| Retaining walls; facing brick 35 m @ 155 | |||
| Tree grilles 27 @ 1,100 | |||
| Miscellaneous external works item @ 10,000 | |||
| Allowance for topsoiling, turfing, planting item @ 30,000 | |||
| Drainage | 136,000 | 22.48 | 15.28 |
| Foul and surface water drain runs 850 m @ 45 | |||
| Foul and surface water manholes 18 @ 800 | |||
| Sewer and surface water drainage connection item @ 6,000 | |||
| Road gullies 35 @ 200 | |||
| Petrol inteceptors 2 @ 4,000 | |||
| Surface water attenuation; storage chambers 13 @ 4,800 | |||
| External services | 100,000 | 16.53 | 11.24 |
| Water connection charge item @ 6,000 | |||
| Electricity connection charge item @ 30,000 | |||
| Gas connection charge item @ 18,000 | |||
| Builders work in connection with external services including service trenches and access chambers item @ 46,000 | |||
| Preliminaries | 148,000 | 24.46 | 16.63 |
| Management costs, site establishment and site supervision. Contractor's preliminaries, overheads and profit @ 17% item @ 126,100 | |||
| Allowance for design reserve @ 3% item @ 22,300 | |||
| Total construction cost: external works only | 890,000 | 147.11 | 100 |
| (Square metre rate based on GIFA) | |||
| Location factors | |
| Outer London | 1.03 |
| South-east | 1.00 |
| South-west | 0.97 |
| East Midlands | 0.93 |
| West Midlands | 0.93 |
| East Anglia | 0.97 |
| Yorkshire and Humberside | 0.95 |
| North-west | 0.94 |
| Northern | 0.94 |
| Scotland | 0.92 |
| Wales | 0.91 |
| Northern Ireland | 0.75 |