| Total cost (£) | £/m2 (gifa) | % | |
| Substructure | 41,900 | 135.16 | 9.05 |
| Roof | 56,400 | 181.94 | 12.18 |
| External walls | 35,200 | 113.55 | 7.6 |
| Windows,external doors | 33,700 | 108.71 | 7.28 |
| Internal walls/partitions | 13,600 | 43.87 | 2.94 |
| Internal doors | 10,900 | 35.16 | 2.35 |
| Wall finishes | 16,100 | 51.94 | 3.48 |
| Floor finishes | 17,300 | 55.81 | 3.74 |
| Ceiling finishes | 11,000 | 35.48 | 2.38 |
| Fixtures and fittings | 21,400 | 69.03 | 4.62 |
| Sanitary appliances | 7,000 | 22.58 | 1.51 |
| Disposal installations | 6,200 | 20 | 1.34 |
| Water installations | 10,900 | 35.16 | 2.35 |
| Space heating | 40,300 | 130 | 8.7 |
| Ventilation installation | 5,600 | 18.06 | 1.21 |
| Electrical installation | 37,200 | 120 | 8.03 |
| Gas services | 1,900 | 6.13 | 0.41 |
| Protective installations | 1,200 | 3.87 | 0.26 |
| Communication installations | 13,800 | 44.52 | 2.98 |
| Builder’s work | 6,000 | 19.35 | 1.3 |
| Preliminaries | 75,500 | 243.55 | 16.3 |
| Total building cost (based on gifa) | 463,100 | 1,493.87 | 100 |
| Primary healthcare centres | |||
| Total cost (£) | £/m2 (gifa) | % | |
| Substructure | 66,450 | 130.29 | 8.8 |
| Roof | 99,790 | 195.67 | 13.3 |
| External walls, windows,doors | 94,000 | 184.31 | 12.5 |
| Internal walls and partitions | 18,650 | 36.57 | 2.5 |
| Internal doors | 30,950 | 60.69 | 4.1 |
| Wall finishes | 19,800 | 38.82 | 2.6 |
| Floor finishes | 28,580 | 56.04 | 3.8 |
| Ceiling finishes | 17,580 | 34.47 | 2.3 |
| Fixtures and fittings | 35,650 | 69.9 | 4.7 |
| Sanitary appliances | 16,200 | 31.76 | 2.2 |
| Disposal installations | 7,650 | 15 | 1 |
| Hot and cold water installations | 15,750 | 30.88 | 2.1 |
| Space heating | 61,200 | 120 | 8.1 |
| Ventilation installation | 23,000 | 45.1 | 3.1 |
| Electrical installation | 52,530 | 103 | 7 |
| Gas services | 1,700 | 3.33 | 0.2 |
| Protective installations | 2,300 | 4.51 | 0.3 |
| Communication installations | 27,430 | 53.78 | 3.6 |
| Specialist installation | 5,500 | 10.78 | 0.7 |
| Builder’s work in connection | 5,000 | 9.8 | 0.7 |
| Preliminaries | 122,690 | 240.57 | 16.3 |
| Total building cost (based on gifa) | 752,400 | 1,475.29 | 100 |
| Small industrial units | |||
| Total cost (£) | £/m2 (gifa) | % | |
| Substructure | 127,400 | 141.56 | 20.6 |
| Frame and upper floors | 65,350 | 72.61 | 10.6 |
| Roof | 67,680 | 75.2 | 11 |
| External walls, windows and doors | 132,140 | 146.82 | 21.4 |
| Internal walls and partitions | 36,500 | 40.56 | 5.9 |
| Internal doors | 3,300 | 3.67 | 0.5 |
| Wall finishes | 5,100 | 5.67 | 0.8 |
| Floor finishes | 900 | 1 | 0.1 |
| Ceiling finishes | 600 | 0.67 | 0.1 |
| Sanitary appliances | 6,000 | 6.67 | 1 |
| Disposal installations | 1,980 | 2.2 | 0.3 |
| Hot and cold water installations | 3,500 | 3.89 | 0.6 |
| Electrical installation | 34,300 | 38.11 | 5.6 |
| Incoming services | 16,000 | 17.78 | 2.6 |
| Protective installations | 990 | 1.10 | 0.2 |
| Communication installations | 9,900 | 11 | 1.6 |
| Builder’s work | 800 | 0.89 | 0.1 |
| Preliminaries | 105,060 | 116.73 | 17 |
| Total building cost (based on gifa) | 617,500 | 686.11 | 100 |
| Cost model | |
| Rates are for the South-east and should be adjusted for location using this table: | |
| Inner London | 1.09 |
| Outer London | 1.03 |
| South-east | 1.00 |
| South-west | 0.95 |
| East Midlands | 0.93 |
| West Midlands | 0.92 |
| East Anglia | 0.95 |
| Yorkshire & Humberside | 0.95 |
| North-west | 0.92 |
| Scotland | 0.99 |
| Wales | 0.92 |
| Northern Ireland | 0.75 |