| Floor area (m2): 10,000 | ||
| Period of analysis (years): 30 | ||
| £/m2 | Total cost (£) | |
| Construction costs | ||
| Building | 1,450 | 14,500,000 |
| Fees, 12.5% | 1,812,500 | |
| Total | 16,312,500 | |
| Maintenance costs | Per year | 30 year |
| repairs and maintenance | ||
| Fabric | 9.97 | 2,991,000 |
| Services | 10.92 | 3,276,000 |
| Redecorations | 3.34 | 1,002,000 |
| Total | 24.23 | 7,269,000 |
| Operation | ||
| Cleaning | 17.76 | 5,328,000 |
| Utilities | 9.94 | 2,982,000 |
| Admin | 21.24 | 6,372,000 |
| Total | 48.94 | 14,682,000 |
| Total lifecycle cost | 38,263,500 | |
| Total lifecycle costing £/m2/yr | 127.55 |