| The indicative costs are based on a typical primary school located in Ealing, Middlesex with a gross internal floor area of 3,000m2. The building includes 14 classrooms, four group rooms, a conference room, gymnasium, music room, four miscellaneous rooms, four offices, one nursery room, two kitchens, a library, dining room, staff room, toilets and changing rooms. | |
| Item | Cost |
| Water supply 27.5m3 tank, single electric pump, underground pipework, pumproom pipework, valves and appurtenances (pump room and builders’ work by others) | £50,000 |
| Sprinkler heads 450@ £200 each (including pipework, bracketry and installation) | £90,000 |
| Sprinkler valve room | £5,000 |
| Documentation, operation and maintenance manuals | £5,000 |
| Total | £150,000 |
| Rule of thumb | £30/m2 plus water supply |