At this week’s CBI Annual Conference, politicians from every party lined up to say infrastructure drives growth. Skanska UK’s president and chief executive says construction has heard it all before, and sets out what would actually get work started on site

I spent Monday at the CBI Annual Conference. I went from a breakfast with the prime minister to a panel on fast-tracking infrastructure, and then on to speeches from across the political spectrum. If I’m honest, the overriding feeling from the audience that day, myself included, was fatigue.
That isn’t because any of the politicians said the wrong thing. Nothing I heard made me think “no, that’s a bad idea”. The problem is that I could have said exactly the same thing last year. There’s always a next spending review, or a Budget to wait for, or another paper coming. Now it’s the 10-year plan, which we’re promised in December. What I want to see is projects.
There is a positive here that I want to start with. I could see a genuine belief across the parties that investment in infrastructure generates growth. In the past, construction often felt as though it was on the naughty step, seen as lazy, too expensive and not worth the bother. I didn’t pick up any of that this week. The political will is there. The problem is that everyone is scratching their heads over how to afford it and where to start.
The hidden cost of flip-flopping
The biggest cost in this industry is the cost of uncertainty. When a scheme such the A46 Newark bypass has its contract cancelled, the damage goes well beyond that one job. Skanska had a team lined up for it, so we turned down other work. Even if I’m paid for that team during the bid phase, that isn’t where a contractor makes money. We make money by delivering. A pause can cost a year of profit-making work.
It isn’t only the cancellations, either. I have bids that we submitted 18 to 20 months ago and we are still waiting to hear back. I can’t keep teams hanging around, so they have to be redeployed or let go. All of that ends up in my overheads, and every contractor is carrying the same burden. If we’re not careful, construction is simply going to become unaffordable.
The effect on workforce planning is another headache. Sometimes I feel as though I’m spread betting: guessing which job will go ahead in which region, will it be the Midlands or Cambridgeshire? You can’t just pick people up and move them around the country. Business leaders are obviously concerned about the impacts of the Employment Rights Act, but the real problem for the supply chain is certainty of work. If smaller firms had a steady pipeline, taking on permanent staff wouldn’t worry them. What worries them is a job being stopped when they have people they can’t redeploy.
Have the nerve to choose
On my panel, the funders and I agreed that government has to have the nerve to decide what it is not going to do. If there are 10 good projects and the money for four, fund the four, and tell everyone else they’ll have to wait. That’s hard when voters wanted numbers five, seven and nine. But trying to do everything means we end up paralysed.
Government has to have the nerve to decide what it is not going to do
NISTA’s refreshed pipeline is a step forward. It’s most useful for seeing work added up across a region: lay the roads, rail and reservoirs over each other and you can see where the skills will be needed. But it doesn’t yet give me much more certainty than my own market intelligence does. After so many reversals, the industry’s attitude is still “we’ll believe it when we see it”.
Get contractors in early
Every project I’ve seen go well has had one thing in common: the contractor was involved early. At 105 Victoria Street, the client committed to us at RIBA stage 2, and the scheme was delivered on time, on budget and to the right quality. On the Lower Thames Crossing, we’ve been able to use the pause to work up the design and create value. We need to stick to a simple rule: get your changes made while the project is still on paper, not when you have a hundred people standing around on site waiting for a decision.
Public clients are nervous about this because they worry someone will cry foul over the procurement. Fairness and value for money matter, of course. But keeping a competition running for a very long time drives up bid costs for everyone, rules out value engineering and slows everything down. That isn’t efficient procurement.
This isn’t a new idea. Frameworks such as National Highways’ already allow more early involvement, and they’re more efficient for it. The challenge is to make that the norm across public infrastructure, not the exception.
Devolution needs to be joined up
I’m in favour of devolution. It can speed up delivery. But I’m nervous about 10 mayoral authorities each with their own forms of contract, their own terms and their own tenders, all landing at the same time. What happens when a project crosses two authorities? Will I need a business development person for each mayor?
I’m nervous about 10 mayoral authorities each with their own forms of contract, their own terms and their own tenders, all landing at the same time
NISTA could act as a centre of excellence and set common standards. Build UK’s Common Assessment Standard shows how this works, because we no longer have to repeat the same checks for our supply chain. We need the national equivalent: a “tell me once” system, so I’m not sending in my accounts with every public bid.
The same thinking applies to the government’s public control agenda for utilities infrastructure. Whatever form it takes, there can’t be a long pause while new owners work out how to be “intelligent clients”. Our water and energy programmes can’t afford one.
We need dates
My list of requests for politicians is long, but it comes down to this. Anything government says in a Budget or a spending review is always so high level. What the industry needs is granularity. First, confirm that the funding is secured. Second, tell us which projects matter most: what are your top 10 strategically important national infrastructure projects? Third, tell us when. When does procurement start, and when does work begin on site?
Give us that, and contractors can plan, the supply chain can hire and we can stop spread betting. Ministers say they believe infrastructure drives growth, and I believe them. Now they need to name the projects and give us some dates.
Katy Dowding is president and CEO at Skanska UK