Mr Derek Vago engaged Wimbledon Construction to build an extension and refurbish his house in London. Disputes arose and they were referred to adjudication. The adjudicator awarded the contractor £122,923.34 inclusive of VAT. Mr Vago refused to pay, and commenced arbitration.

The contractor sought summary judgment and the defendant sought a stay on the basis of the contractor’s financial position.