The lead time for rotary piling - (staying level) remains at five weeks. Although most companies were quieter than they were six months previously, workload is steady. Lead times for continuous flight auger piles are lengthening as a result of an increase in projects requiring them.
Although both concrete works - (staying level) and structural steel frame - (staying level) companies reported changes in the build up, overall lead times remained unchanged at nine and 10 weeks respectively. Reinforcement is taking up to four weeks to be delivered for insitu concrete and American surcharges on steel imports may affect supply.
Membrane roofing - (going down) fell by one week to seven. Enquiries and projects were down on the previous six months, leaving materials readily available.
Brickwork - (going up) lead times increased to five weeks (up one week) as new projects put pressure on design detailing resources. Blockwork lead-in remained at four weeks owing to a reduction in the design input being required.
Drylining - (going down) lead times decreased by two weeks to nine. Design offices have recruited staff and are also being asked to produce less detailing for projects than in the past few months. Despite the overall fall, companies have stated that plasterboard is no longer on next day delivery and plaster availability from British Gypsum is greatly reduced while their factory undergoes essential maintenance. There are not expected to be any improvements on this situation until September.
General joinery - (going down) and specialist joinery - (going down) companies reduced their lead times to 13 and 16 weeks respectively. The main reason given was reduced order books. However, lead times are expected to increase in the busy summer months.
The raised flooring - (going down) sector reduced average lead times from eight to six weeks, a fall of two weeks. Firms are quieter than six months ago and this has eased pressure in design offices and factories.
The lead times for architectural metalwork - (going down) companies fell one week to 14. The supply chain here is responding to the steady workload and has been able to reduce supply periods.
Decorating - (staying level) companies report no change to the lead time of four weeks. However, a shortage of industrial painters is expected, as firms are busy with steady workload through the summer. Most specified products are available off the shelf and even bespoke or European materials are available in just two weeks.
Thirty-eight weeks is the lead time for passenger lifts - (going up) after an unusual drop to 35 weeks. Some firms are now quoting up to 42. Manufacturing durations have risen to 29 weeks.
Three months ago the lead time for mechanical pipework - (staying level) was expected to rise, yet the average remains at 18 weeks, with a couple of firms reporting lower periods.
The lead time for sprinklers - (going up) went up two weeks to 12 as procurement and manufacture periods increased as a result of a high workload.
Air-handling units - (going up) can now be obtained in only seven weeks, a fall of two from previously quoted lead times. Companies now have better relationships with their supply chain, which is currently very reliable.
As enquiry levels and new projects fell compared with previous months, so did the lead time for Uninterruptible power supply systems - (going down) by one week to eight.
Voice and data cabling - (staying level) lead times remained unchanged at eight weeks. The only product needing advance ordering is OM3 fibre optics, but as this product is not required early in project installations the overall lead time is not usually affected.
Spotlight on Curtain walling
Lead times
Orders and workload
Tender prices
Enquiry levels
Downloads
Lead times
Other, Size 0 kbCurtain walling: Lead times
Other, Size 0 kbCurtain walling: Orders and workload
Other, Size 0 kbCurtain walling: Tender prices
Other, Size 0 kbCurtain walling: Enquiry levels
Other, Size 0 kb
Postscript
To find out about more lead times and contribute to future articles, please visit www.mace.co.uk/mace/approach/foresite.asp.