In particular, I am referring to the way JCT98 separates performance-specified works and contractor-design elements, which are inextricably linked. For example:
Having been involved in the production of about 1000 performance specifications, I do not advise their use for contract purposes, and an effort should always be made before award to extract what the contractor has priced so that it can be checked, reviewed and incorporated in any agreement. The criteria can remain unaltered, but at least find out what is being bought.
- JCT98 separates performance specification and contractor design – in fact, they are necessarily linked
- This creates a blame culture at odds with the need for co-operation in the project team
If timing remains as stated in clause 42.4, the contractor is likely to make a proposal knowing that it will not be acceptable. The architect will then reject it, the contractor will submit a claim for compliance and the architect will get the blame for the cost increase and delay. All very common and unnecessary.
The only statement relevant to timing is in clause 42.5, where the architect is given 14 days to report or comment on the contractor’s statement. On many large contracts, the final design could never be agreed in that short space of time. Again, blame the architect.
Postscript
Nick Schumann is a partner in specification-writer and quantity surveyor Schumann-Smith.