The landmark Wembley stadium arch is to be lifted within the next two weeks, according to a senior project source. The big lift has been delayed over the past few weeks as a result of faulty steel welds and some weak concrete discovered on one of the bases supporting the structure. It is expected that the lift will take place over four weekends.