All articles by Tony Bingham – Page 2
-
Comment
Please stop arguing with the arbitrator
The courts are pushing back against losers’ attempts to challenge arbitration rulings on dubious procedural grounds
-
Comment
The fury of a homeowner
Tony Bingham is alarmed by an MP’s draconian suggestions for regulating domestic building works – and has a much better idea
-
Comment
Good faith strikes again
A new ruling shows you can’t breach part of a contract then use the contract machinery to turn that breach in your favour, explains Tony Bingham
-
Comment
Stop deifying the institution
The RICS needs to move out of the Middle Ages: its true role is as a club that supports and trains its members, says Tony Bingham
-
Comment
£1 notices aren’t worth the paper they’re printed on
A payment notice is invalid if it fails to set out the amount genuinely considered due – placeholder notices don’t count, says Tony Bingham
-
Comment
A liquid situation over damages
Tony Bingham tells of a subcontractor defending a liquidated damages claim that decided it did want to pay them after all, when the client changed tack
-
Comment
On too great expectations
Tony Bingham on a client who paid dearly for taking her builder’s quote and completion date too literally – with a whole lot of variations on top
-
Comment
Challenges to adjudication: keep it plain and simple
Any challenge to a purported right to adjudicate must be plain, specific and certain if it is to succeed in court
-
Comment
Homebuyer surveys: consultants, beware the faults you can’t see
A surveyor who failed to seek certification for a refurbished home has been stuck with massive rebuild costs
-
Comment
Adjudicate first, litigate after
A Scottish court has upheld the NEC3 provision that makes adjudication mandatory before litigation can be sought
-
Comment
A question of scope
A party that wants to limit the scope of an adjudication must be wary of asking questions that accidentally widen the dispute
-
Comment
Adjudication in insolvency: any further questions?
The latest instalment in the saga of adjudications involving insolvent companies brings more questions than answers
-
Comment
Can’t pay, won’t pay
How many steps does it take to get the losing party to pay up as ordered? Extraordinarily many, at times, as this case shows
-
Comment
Good in parts: clarity on severance
An adjudication that is partially flawed can still be upheld in the areas in which it is sound, according to a recent appeal decision
-
Comment
Let’s act in good faith, always – not just during covid
Emergency government guidance on contracts urges us to ‘behave responsibly’ during the pandemic. But why only now?
-
Comment
Fair play to relational contracting
Good faith is becoming a central tenet of construction law, as highlighted in two recent publications
-
Comment
Why are some process plants not covered by the Construction Act?
Let’s end the immunity of certain types of project from the Construction Act – it was always more about power than logic
-
Comment
A desire to punish can cost dearly
A couple who sued their architect neighbour after she helped out for free are paying heavily for pursuing a speculative case
-
Comment
Part 8 applications: What kind of question is that?
A Part 8 application in relation to an adjudicator’s decision on an extension of time took a novel approach
-
Comment
NEC contracts: Ours is not to reason why
Adjudicators need not give detailed reasons for their decisions – and can use a little help without accounting for that either